02618-2025 Standard Specification Book_official.pdf

PDF 149 KB Posted

Attached to
UDOT- Fold and Form Culvert Piper Liners
Solicitation number
UDOT250204JB
Issued by
Utah

About this file

This is a technical specification document (Section 02618) from the Utah Department of Transportation's 2025 Standard Specifications detailing requirements for drainage pipe liner installations. The document covers three main types of drainage lining methods: polyvinyl chloride (PVC) fold-and-form, cured in place pipe (CIPP), and segmental thermoplastic and metal pipe. The specification outlines detailed requirements for materials, preparation, and installation procedures, including host pipe cleaning, inspection requirements, and specific installation methods for each liner type. For pipes less than 48 inches in diameter, closed-circuit television (CCTV) inspection is required, while visual inspection is permitted for larger pipes.

The technical requirements specify that PVC resin must be manufactured from virgin materials with no fillers and cannot exceed 30 inches in diameter. CIPP liners must meet minimum physical properties including initial flexural modulus of 250,000 PSI and flexural strength of 4,500 PSI at 73°F. The grout specifications require compressive strength between 100-400 psi, with fly ash content not exceeding 30% of cementitious material and shrinkage limited to 1% by volume. The document includes specific ASTM and AASHTO standards that must be followed for various aspects of the work, as well as detailed submittal requirements including engineering calculations, work area plans, and installation procedures.

View the file

Other files

File Type Posted
1297248-event.pdf PDF
Changing-Your-Time-Zone.pptx PPTX presentation
Notice of Bid System Change.docx DOCX document
Form-Claim of Business Confidentiality-check fields.doc DOC document
Scope of Work for Fold and Form 3_03_2025.docx DOCX document
T&C-9.16.24.docx DOCX document
IFB-General Bid Information.doc DOC document
NEW-Form-Vendor Set Up Form_2024-06-27.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Drainage Pipe Liner 02618 – Page 1 of 7

2025 Standard Specifications Latest Revision: December 7, 2023

SECTION 02618

DRAINAGE PIPE LINER

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Drainage lining methods such as polyvinyl chloride (PVC) fold-and-form, cured in place pipe (CIPP), and segmental thermoplastic and metal pipe.

1.2 RELATED SECTIONS

A. Section 02610: Drainage Pipe

1.3 REFERENCES

A. AASHTO M 326: Polyethylene (PE) Liner Pipe, 300- to 1600-mm Diameter, Based on Controlled Outside Diameter

B. AASHTO LRFD Bridge Design Specifications

C. ASTM D 790: Flexural Properties of Unreinforced and Reinforced Plastics and Electrical Insulating Materials

D. ASTM D 1784: Rigid Poly (Vinyl Chloride) (PVC) Compounds and

Chlorinated Poly (Vinyl Chloride) (CPVC) Compounds

E. ASTM D 5813: Cured-In-Place Thermosetting Resin Sewer Piping

Systems

F. ASTM F 1216: Rehabilitation of Existing Pipelines and Conduits by the

Inversion and Curing of a Resin-Impregnated Tube

G. ASTM F 1504: Folded Poly (Vinyl Chloride) (PVC) Pipe for Existing

Sewer and Conduit Rehabilitation

H. ASTM F 1743: Rehabilitation of Existing Pipelines and Conduits by

Pulled-in-Place Installation of Cured-in-Place Thermosetting Resin Pipe

(CIPP)

I. ASTM F 1867: Installation of Folded/Formed Poly (Vinyl Chloride) (PVC)

Pipe Type A for Existing Sewer and Conduit Rehabilitation https://drive.google.com/file/d/1vdUPLr3ZOwyA0rZurtU2ydsx5qEzPfSn/view?usp=drive_link

02618 – Page 2 of 7

2025 Standard Specifications Latest Revision: December 7, 2023

J. ASTM F 1871: Folded/Formed Poly (Vinyl Chloride) Pipe Type A for Existing Sewer and Conduit Rehabilitation

K. ASTM F 1947: Installation of Folded Poly (Vinyl Chloride) (PVC) Pipe into

Existing Sewers and Conduits

L. ASTM F 2019: Rehabilitation of Existing Pipelines and Conduits by the

Pulled in Place Installation of Glass Reinforced Plastic (GRP) Cured-in- Place Thermosetting Resin Pipe (CIPP) Using the UV-Light Curing Method

1.4 DEFINITIONS Not Used

1.5 SUBMITTALS

A. Include the following information into a single submittal for each drainage pipe to be lined, for review. Use the naming convention used in the plans for each location. Provide the seal of a Professional Engineer (PE) or Professional Structural Engineer (SE) for engineering calculations. Divide information into the sections listed below.

1. Work Area

a. Locations and dimensions of any temporary access roads

b. Locations and dimensions of pipe liner assembly and insertion area “footprints” or area of disturbance.

c. Distance of insertion footprint from the traveled way

d. Amount of time the footprint will be exposed

e. Shoring method when excavation is proposed

f. Written access agreements from property owners when work area is outside Department Right of Way

2. Preparation

a. Host pipe cleaning

b. Management of flows in the host pipe

c. Initial pipe inspection

3. Installation

a. Method of pipe liner installation and finishing

b. Bulkhead and grouting details for segmental thermoplastic and metal liner

c. Curing method identifying required curing times, temperatures, and pressures

d. Any potential for producing contaminant concentrations in excess of surface water quality standards or ambient groundwater quality standards, as applicable

e. Control and disposal of any contaminants from materials or installation methods during and after installation

f. Final pipe inspection

02618 – Page 3 of 7

2025 Standard Specifications Latest Revision: December 7, 2023

4. Product Data

a. Engineering calculations and recommended size and wall thickness of pipe liner for products not specified in Section 02610.

1) The host pipe is considered to be fully deteriorated and unable to carry loads.

2) Meet or exceed AASHTO HL-93 or interstate alternate loading according to AASHTO LRFD Bridge Design Specifications and interim specifications for pipe liner load capacity.

b. Maximum allowable external grouting pressure on pipe liner and joints for segmental thermoplastic and metal liners.

5. Certificate of compliance.

6. Mix Designs

a. Grout Mix design

b. Trial batch test data

PART 2 PRODUCTS

2.1 PVC FOLD-AND-FORM LINER

A. PVC resin manufactured from virgin materials containing no fillers.

1. Meet or exceed the physical property requirements in ASTM F 1504 or ASTM F 1871 for the cell classification as defined in ASTM D 1784.

B. Do not use greater than 30 inch diameter.

2.2 CIPP LINER

A. Fabric tube consisting of one or more layers of absorbent non-woven felt fabric, felt/fiberglass, or fiberglass meeting the requirements of ASTM D 5813 and ASTM F 1216, ASTM F 1743, or ASTM F 2019.

1. Use a CIPP liner that meets or exceeds the following physical properties outlined in Table 1.

Table 1

Minimum Physical Properties

Property Test Method

ASTM Value Initial Flexural Modulus ASTM D 790 250,000 PSI @73º F

Flexural Strength ASTM D 790 4,500 PSI @73º F

02618 – Page 4 of 7

2025 Standard Specifications Latest Revision: December 7, 2023

2. Use a sufficient quantity of resin for impregnation to fill the volume of air voids in the pipe liner with additional allowance for polymerization and for any migration of resin into the cracks and joints in the host pipe.

a. Color the resin with a pigment compatible with the resin system as specified by the resin manufacturer.

2.3 SEGMENTAL THERMOPLASTIC LINER

A. Solid wall polyethylene pipe. Refer to AASHTO M 326.

B. Profile wall thermoplastic pipe. Refer to Section 02610.

2.4 SEGMENTAL METAL LINER

A. Metal Pipe. Refer to Section 02610.

2.5 GROUT

A. Cementitious low density grout mixture having the following characteristics.

1. Suitable with the site conditions, construction methods, and pipe liner structural capacity.

2. Compressive strength between 100 and 400 psi

a. Determine strength from trial batches at 28 days

3. Fluidity to completely fill voids and the annular space between the host pipe and the pipe liner without segregating

4. Fly ash not to exceed 30 percent of cementitious material

5. Shrinkage not to exceed 1 percent by volume

PART 3 EXECUTION

3.1 GENERAL

A. Furnish the type of drainage pipe liner shown with the following exception:

1. Select from any of the drainage pipe liner products listed in this

Section, Part 2 meeting the allowable pipe size reduction when no specific product is shown.

02618 – Page 5 of 7

2025 Standard Specifications Latest Revision: December 7, 2023

3.2 PREPARATION

A. General

1. Perform all work within the limits of the Department right of way unless written agreements are in place with adjacent property owners.

2. Provide adequate control of water in the host pipe when necessary.

a. Repair damage caused as a result of flow control or lack thereof.

3. Provide the necessary controls to prevent pollutants from being transported downstream.

B. Host Pipe Cleaning

1. Remove material to include sediment, rocks, and miscellaneous debris to inspection and install the pipe liner.

2. Use a cleaning method and tools that will not cause damage to the pipe or surrounding roadway features.

a. Notify the Engineer when cleaning could result in damage.

b. Do not cause erosion of surrounding areas from cleaning operations.

c. Minimize sediment from being transported downstream.

3. Collect and properly dispose of all material removed.

C. Host Pipe Inspection

1. Perform remote inspection for pipes with a nominal diameter less than 48 inches using a closed-circuit television (CCTV) crawler.

2. Perform a visual inspection for pipes with diameter greater than 48 inches.

3. Inspect the condition of the host pipe and the suitability of the pipe liner installation. Document and notify the Engineer of the following:

a. Collapsed or impassable sections of the pipe

b. Horizontal or vertical alignment deviations

c. Structural concerns

d. Loss of material surrounding the pipe exterior

e. Infiltration of water

f. Repairs required to perform the installation

D. Drainage Pipe Liner

1. Verify host pipe internal size and length before ordering pipe liner.

2. PVC fold-and-form and CIPP liner dimensions

a. Size the pipe liner to have an outside diameter that will tightly fit the inside of the host pipe.

02618 – Page 6 of 7

2025 Standard Specifications Latest Revision: December 7, 2023

b. Provide sufficient pipe liner length to continuously line the host pipe with no intermediate joints.

3. Segmental Thermoplastic and Metal liner dimensions

a. Size the pipe liner to have an outside dimension that will freely pass through the host pipe and accommodate grout placement.

b. Use only one type of pipe liner and joint system in any single host pipe.

3.3 INSTALLATION

A. General

1. Remove sediment and debris that might have accumulated after the initial cleaning immediately before installing the pipe liner.

2. Handle and install the pipe liner in a manner that will not cause damage to the pipe liner.

3. Provide a smooth finish and a tight seal between the pipe liner and the drainage structure walls at pipe penetrations.

4. Restore lateral and inlet connections.

5. Inspect the rehabilitated pipe upon completion and before acceptance by the Engineer.

a. Evaluate pipe liners that contain dry spots, wrinkles, delamination, holes, cracks, joint gaps, soft spots, blisters, or other defects.

B. PVC fold-and-form and CIPP Liner

1. Meet minimum installation requirements according to ASTM F

1867 or ASTM F 1947 for PVC fold-and form

2. Meet minimum installation requirements according to ASTM F

1216 or ASTM F 1743 for CIPP.

3. Follow the manufacturer’s recommended curing and relaxation period required to hold the pipe liner against the host pipe.

a. Provide sufficient gauges, monitoring devices, and tests to determine the effectiveness of the curing.

C. Segmental Thermoplastic and Metal Liner

1. Construct a bulkhead at each end of the host pipe to fully support the fluid thrust loads exerted by the placement of grout.

a. Vent bulkheads to allow release of trapped air as the grout flows into the annular space.

2. Provide a minimum of 24 hours for the pipe liner temperature to equalize within the host pipe before placing grout.

02618 – Page 7 of 7

2025 Standard Specifications Latest Revision: December 7, 2023

3. Fill the entire full length of annular space between the host pipe and the pipe liner with grout.

a. Provide sufficient gauges, monitoring devices, and tests to determine the effectiveness of the grout placement.

4. Do not exceed the pipe liner maximum specified grouting pressure.

a. Use a pumping unit with a pressure meter and valves capable of limiting grout pumping pressures to the maximum pressure recommended by the manufacturer at the end of the discharge pipe.

5. Place grout in lifts to avoid excessive buoyant forces or grouting pressures.

a. Allow each lift to cure sufficiently before proceeding with next lift.

6. Remove any internal braces or bands once the grout is sufficiently cured and before acceptance.

END OF SECTION