02378 Riprap and Rock Lining.docx

DOCX document 20 KB Posted

Attached to
SF ELK CREEK GUZZLER INSTALLATION Federal contract opportunity
Solicitation number
140L6221Q0026
Issued by
Department of the Interior Bureau of Land Management Wyoming Region

View the file

Other files for this federal contract opportunity

Other files attached to SF ELK CREEK GUZZLER INSTALLATION, newest first.
File Type Posted
Sol_140L6221Q0026_Amd_0001.pdf PDF
140L6221Q0026_AMD_001_UPDATED_BID_SCHEDULE_ELK_CREEK_GUZZLER_0001.xlsx XLSX spreadsheet
140L6221Q0026_QUESTIONS_AND_ANSWERS_AMD_0001_0001.pdf PDF
Bid Schedule Elk Creek Guzzler Installation.xlsx XLSX spreadsheet
Sol_140L6221Q0026.pdf PDF
Guzzler Layout.pdf PDF
01009 Gen Info Req SFElkCreekWildlifeGuzzlerProject.docx DOCX document
NE Nevada Water Catchment.pdf PDF
Guzzler Layout2.pdf PDF
SFElkCreek Guzzler.pdf PDF
SFElkCreek Guzzler Access.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 02378

RIPRAP AND ROCK LINING

PART 1: GENERAL

1.1 SUMMARY

A. Section Includes: Providing riprap used for HDPE liner weight.

1.2 DEFINITIONS

A. Satisfactory Materials: Materials classified in ASTM D 2487 as GW, GP, SW and free from roots and other organic matter, trash, debris, and frozen materials and stones larger than 100 mm (4 inches) in dimension are satisfactory.

PART 2: PRODUCTS

2.1 MATERIALS

A. Riprap Source: The Contractor shall furnish the riprap source.

B. Loose Riprap: Stone shall consist of hard, durable stone, cobbles, or spalls, angular in shape, resistant to weathering and to water action. The riprap shall meet the gradation specified below.

Table 1: Riprap Gradation

Sieve Designation
Percentage Passing
100 mm (4 inch)
100
50 mm (2 inch)
50 – 100
19 mm (3/4 inch)
10 – 25
4.75 mm (No. 4)
0 5

PART 3: EXECUTION

3.1 INSTALLATION

A. Loose Riprap: Place on the BOSS HDPE liner as per Boss Tank Manufacture’s Installation instructions “NE Nevada Water Catchment”. Place riprap to its full course thickness in one operation and avoid displacing the underlying material. Placing of riprap by dumping into chutes, or by similar methods likely to cause segregation, shall not be permitted. Hand placing or rearranging of individual stones by mechanical equipment shall not be permitted.

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT

A. Units: The work described in this section will be measured and paid by the cubic yard.

4.2 BASIS OF PAYMENT

A. Payment:

Prices and payment will be full compensation for the work described in this section. Payment will be made under:

Pay Item Pay Unit

02378(01) Loose Riprap Cubic Yard

END OF SECTION