This is a Statement of Work (SOW) for the procurement of a High Frequency (HF) E-Field Meter by the Naval Surface Warfare Center, Dahlgren Division (NSWCDD). The Government seeks commercially-off-the-shelf (COTS) or modified COTS equipment to replace an aging HF Meter used for Radiation Hazard (RADHAZ) surveys and electromagnetic environmental effects measurements to ensure warfighter safety and capability.
The contractor must deliver a total of 10 compliant units plus provide option pricing for 10 additional units. The hardware specifications require a frequency range of 1.5-30 MHz with 1 kHz frequency resolution, minimum and maximum operational E-field limits of 0.05 V/m and 400 V/m respectively, maximum survivability E-field of 1000 V/m, measurement precision of ±0.1 dB with 1 dB accuracy, battery operating time of 12 hours (objective) or 6 hours (threshold), operating temperature of 14-130°F, USB-C data port, and storage capacity exceeding 1 GB. The device must include a rechargeable battery with fast-charging capability, proprietary or N-Type SMA antenna ports, water resistance, and a display readable in both sunlight and nighttime conditions with selectors and push buttons. Software requirements include JSON-based application programming interface for integration with E3TO and HF meter systems, user display menu supporting antenna number selection, frequency selection, test point location, and battery level, and read/write formats in XML, CSV, and TXT. Delivery schedule calls for the First Article Test unit within 8 months after receipt of order, followed by nine production units within 2 months of FAT approval, with optional units available 10 months after options exercise. The contractor must perform acceptance testing and functional checkout before FAT shipment with Government witness, provide onsite training on fundamentals and hardware operation, furnish technical documentation per CDRL A001, and deliver reports per CDRL A002. The Government will notify the contractor within 7 calendar days of FAT receipt regarding approval or disapproval; if disapproved, the contractor must furnish a corrected unit at no additional cost, provide prepaid return shipping authorization, and bear all costs for additional testing. All work is unclassified, and the contractor must coordinate travel with the Technical Point of Contact, conducting all travel in accordance with Federal Travel Regulations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3.3 The Contractor shall adhere to the following schedule:
Item # Description Quantity Delivery Date 0001 First Article Test (FAT) 1 8 Months After Receipt of Order (ARO) 0002 HF Meter 9 2 Months after receiving FAT Approval 0003 Shipping 1 0004 Optional – HF Meter 10 10 Months After Options Exercise (AOE)
3.4 The Contractor shall fabricate one (1) HF E-Field Meter according to the minimum performance specifications provided in Section 2.0 prior to fabrication of any full production run.
3.4.1 The Contractor shall deliver the first article quantity eight (8) months after receipt of the order.
NOTE: The Government will perform testing on the first article unit.
3.4.2 The Contractor shall furnish a corrected First Article unit at no additional cost to the Government for subsequent testing if the first article fails any testing or the visual inspection.
The Government will notify the Contractor seven (7) calendar days after receipt of the First Article, in writing, of the approval or disapproval of the First Article. The notice of approval or disapproval shall not relieve the contractor from complying with all requirements of the specifications and all other terms and conditions of this order. A notice of disapproval shall cite reasons for disapproval. The Contractor shall make any necessary changes, modification, or repairs to the First Article or select another First Article for testing. All costs related to Contractor performed tests are to be born by the contractor, including all costs for additional tests following a disapproval. If the First Article is disapproved, the Contractor shall provide a pre-paid request for authorization (RMA) for returned shipping costs so the unit may be returned for correction, repair or replacement. Any repaired units must be clearly identified when returned to the Government for subsequent inspection and acceptance testing.
3.4.3 The Contractor shall deliver nine (9) HF E-Field Meter (also referred to as a HF Meter) that meets the minimum performance specifications identified in Section 2.0 after approval of FAT from the Government. The final product shall be easily re-producible.
3.4.4 The Contractor shall email shipment tracking information to the Technical Point of Contact (TPOC) on the day the units are shipped.
3.4.5 The Contractor shall ensure the units provides testing capabilities and environmental characterizations for shore and shipboard surveys.
3.4.6 The Contractor shall provide reports in accordance with (IAW) CDRL A002.
3.5 Capability Demonstration and Testing: The Contractor shall perform acceptance test/functional checkout before the FAT unit is shipped.
NOTE: The Government will witness the test/functional checkout process.
3.5.1 The event can be performed at the Contractor’s site or the Government’s site. The determination of the time, date and location shall be coordinated with the TPOC identified below at least 30 days prior to the scheduled event.
3.6 The Contractor shall provide onsite training on the fundamentals and operations of the HF Meter.
3.6.1 The Contractor shall provide hands-on training regarding the use and maintenance of the hardware.
3.6.2 The Contractor shall provide technical documentation IAW CDRL A001.
3.6.3 The Contractor shall coordinate with the TPOC identified below to schedule the training during the period of performance of the contract.
3.7 The Contractor shall provide option pricing to produce 10 additional units.
NOTE: The Government reserves the right to waive any optional first article requirements.
*The Contractor shall not fabricate and deliver any additional optional units until the Government applies the appropriate funding to exercise the option and the Contracting Officer provides a subsequent contract modification..
*The Government reserves the right to modify this contract at a later date to cover additional repair services/components identified during the initial inspection.
4.0 DATA DELIVERABLES
4.1 The Contractor shall provide data IAW CDRL A001; and
4.2 The Contractor shall provide data IAW CDRL A002.
5.0 GOVERNMENT-FURNISHED PROPERTY/MATERIAL/INFORMATION
(GFP/GFM/GFI)
The Government does not anticipate any government furnished property/materials/information for this effort.
6.0 SECURITY
All work under this SOW is Unclassified.
7.0 TRAVEL
The Contractor will be required to travel in performance of this contract. The number of trips and types of personnel traveling shall be limited to the minimum required to accomplish work