This is a conceptual construction phasing document for the Michigan School for the Deaf (MSD) Residence Hall project in Michigan. The project involves the construction of a new residence hall and apartments on the MSD campus, with a comprehensive phasing strategy designed to minimize disruption to ongoing operations. The project schedule spans from July 2025 through September 2027, beginning with the relocation of play areas and hazardous material abatement in July 2025. Subsequent phases include the razing of Gilbert Hall and relocation of utilities in December 2025, followed by the main construction of the residence hall and apartments from December 2025 through February 2027. The final phases include furniture installation and occupant move-in from March 2027 through July 2027, partial razing of Stevens Hall from June 2027 through August 2027, and exterior repairs with site landscaping completion from August 2027 through September 2027.
The document provides a conceptual overview of building massing, site location, and architectural elements including building entry and residence wings. No specific pricing, funding amounts, contract terms, or procurement details are included in this phasing document. The file serves as a planning and coordination tool to outline the sequential construction activities and site management strategies necessary to execute the residence hall project while maintaining campus functionality throughout the construction period.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 5, 2023
State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall
SITE
BUILDING
tray Text Box Conceptual Construction Phasing Approach
MSD – Residence Hall | Existing Site Plan tray
Conceptual Building Massing and Site Location tray
Conceptual Building Massing and Site Location
MSD – Residence Hall | Project Phasing Strategy
Buildings to be affected
Conceptual Residence
Hall Overlay
MSD – Residence Hall | Project Schedule
July 2025
Relocate Play
Areas
Hazardous
Material
Abatement
December 2025
Raze Gilbert Hall
Relocate Utilities
Initial grading and sitework
December 2025 Thru
February 2027
Construct
Residence Hall and Apartments
March 2027 thru July 2027
Furniture and
Move-in
June 2027 thru
August 2027
Raze portion of
Stevens Hall
August 2027 thru
September 2027
Stevens Hall
Exterior Repairs
Site Landscaping and Plantings
MSD – Residence Hall | New Buildings tray
Conceptual Building Entry and Residence Wings