02-MSD_Phasing_2024_06_25_v2.pdf
PDF 2 MB Posted
- Solicitation number
- RFI 171 260000000011 3
- Issued by
- Genesee County, Fife Lake Village, Michigan
About this file
This document is a conceptual construction phasing plan for the Michigan School for the Deaf (MSD) Residence Hall project, prepared by the State of Michigan. The project involves the design and construction of new residence hall and apartment facilities on the MSD campus. The phasing strategy outlines a multi-year timeline beginning in July 2025 with the relocation of play areas and hazardous material abatement, followed by the December 2025 razing of Gilbert Hall and relocation of utilities with initial grading and sitework. The primary construction phase for the residence hall and apartments is scheduled from December 2025 through February 2027, with furniture installation and move-in activities occurring from March 2027 through July 2027. Additional site work includes razing a portion of Stevens Hall from June 2027 through August 2027 and completing Stevens Hall exterior repairs and site landscaping from August 2027 through September 2027. The document provides conceptual site plans, building massing layouts, and visual representations of the new building entries and residence wing configurations.
The file does not contain specific pricing information, contract terms, bid response dates, or award details. No information is provided regarding set-asides, incumbent contractors, funding sources, or budget amounts. The document functions primarily as a visual and temporal planning reference for the project phases and site impacts during the construction period.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 5, 2023
State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall
SITE
BUILDING
tray Text Box Conceptual Construction Phasing Approach
MSD – Residence Hall | Existing Site Plan tray
Conceptual Building Massing and Site Location tray
Conceptual Building Massing and Site Location
MSD – Residence Hall | Project Phasing Strategy
Buildings to be affected
Conceptual Residence
Hall Overlay
MSD – Residence Hall | Project Schedule
July 2025
Relocate Play
Areas
Hazardous
Material
Abatement
December 2025
Raze Gilbert Hall
Relocate Utilities
Initial grading and sitework
December 2025 Thru
February 2027
Construct
Residence Hall and Apartments
March 2027 thru July 2027
Furniture and
Move-in
June 2027 thru
August 2027
Raze portion of
Stevens Hall
August 2027 thru
September 2027
Stevens Hall
Exterior Repairs
Site Landscaping and Plantings
MSD – Residence Hall | New Buildings tray
Conceptual Building Entry and Residence Wings