This document is a conceptual construction phasing plan for the Michigan School for the Deaf (MSD) Residence Hall project, prepared by the State of Michigan. The project involves the design and construction of new residence hall and apartment facilities on the MSD campus. The phasing strategy outlines a multi-year timeline beginning in July 2025 with the relocation of play areas and hazardous material abatement, followed by the December 2025 razing of Gilbert Hall and relocation of utilities with initial grading and sitework. The primary construction phase for the residence hall and apartments is scheduled from December 2025 through February 2027, with furniture installation and move-in activities occurring from March 2027 through July 2027. Additional site work includes razing a portion of Stevens Hall from June 2027 through August 2027 and completing Stevens Hall exterior repairs and site landscaping from August 2027 through September 2027. The document provides conceptual site plans, building massing layouts, and visual representations of the new building entries and residence wing configurations.

The file does not contain specific pricing information, contract terms, bid response dates, or award details. No information is provided regarding set-asides, incumbent contractors, funding sources, or budget amounts. The document functions primarily as a visual and temporal planning reference for the project phases and site impacts during the construction period.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

April 5, 2023

State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall

SITE

BUILDING

tray Text Box Conceptual Construction Phasing Approach

MSD – Residence Hall | Existing Site Plan tray

Conceptual Building Massing and Site Location tray

Conceptual Building Massing and Site Location

MSD – Residence Hall | Project Phasing Strategy

Buildings to be affected

Conceptual Residence

Hall Overlay

MSD – Residence Hall | Project Schedule

July 2025

Relocate Play

Areas

Hazardous

Material

Abatement

December 2025

Raze Gilbert Hall

Relocate Utilities

Initial grading and sitework

December 2025 Thru

February 2027

Construct

Residence Hall and Apartments

March 2027 thru July 2027

Furniture and

Move-in

June 2027 thru

August 2027

Raze portion of

Stevens Hall

August 2027 thru

September 2027

Stevens Hall

Exterior Repairs

Site Landscaping and Plantings

MSD – Residence Hall | New Buildings tray

Conceptual Building Entry and Residence Wings