02 - 2026 Basewide Sewer Repair Drawings.pdf

PDF 187 KB Posted

Attached to
PANG Sanitary Sewer Repair
Solicitation number
S-24800-00016465
Issued by
Oregon

About this file

2026 Basewide Sewer Repair - Portland Air National Guard Base

This is a drawing and specifications document for a sanitary sewer repair project at Portland Air National Guard Base in Oregon, dated March 2026. The project involves the repair and approximately complete replacement of sewer lines in Quadrant 3 of the base, specifically between Manhole 11 to Manhole 40, with additional repairs to the section from Manhole 40 to Manhole 47. The primary objective is to address an area where E. coli contamination may be affecting groundwater. Three buildings will be directly impacted by the required line shutdown. The project encompasses multiple trades including excavation, concrete work, asphalt repair, plumbing, potential soil testing, and security fencing work. Key operational constraints include maintaining at least one open traffic lane to accommodate base mission operations, keeping parking lot access available to building users, and restricting total shutdown timeline with an installation plan demonstrating efforts to minimize downtime. The base plumber inspector must approve the work after demolition and installation before backfill can proceed, and the contractor must provide the full base sanitary map upon project award.

The contractor must submit a repair solution in writing prior to project start and comply with all applicable Unified Facilities Criteria (UFC) standards, OSHA guidelines, and confined space permit requirements where applicable. Additional requirements include installing tracer wire on the project, providing photographic documentation throughout the construction process, supplying traffic control devices (cones and caution tape), repairing any security fencing on building B455 perimeter if affected, and submitting as-built sewer line documentation prior to project closeout. The specifications for this project are detailed in the OregonBuys appendix.

View the file

Other files

File Type Posted
PANG Sanitary Sewer Repair ITB.pdf PDF
Sewer Repair Specifications Complete.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Name: 2026 Basewide Sewer Repair Date: March 2026 Drawing No:

Drawing Title:

2026 Basewide Sewer Repair Portland Air National Guard Base, Oregon

Title

G-01

Sheet Index (Example)

G-01 COVER SHEET

G-02 DRAWINGS AND SPECIFICATIONS

Project Name: 2026 Basewide Sewer Repair Date: March 2026 Drawing No:

Drawing Title:

Title

G-02

REFERENCES:

UFC 3-201-01 STORM DRAIN

UFC 3-240-04A WASTEWATER COLLECTION

UFC 3-420-01 PLUMBING SYSTEMS

UFC 3-220-05 DEWATERING AND GROUNDWATER CONTROL

UFC 3-250-04 CONCRETE PAVEMENT

UFC 3-270-01 ASPHALT MAINTENCE AND REPAIR

UFC 3-220-01 GEOTECHNICAL ENGINEERING

PROJECT SPECIFIC NOTES

1. THE MAIN PROJECT IS LOCATED IN QUADRANT 3.

2. THE GOAL OF THE PROJECT: REPAIR AREA WHERE E.COLI MAY BE CONTAMINATING THE GROUND WATER.

APPROXIMATELY COMPLETE REPLACEMENT OF SEWER LINE BETWEEN MANHOLE 11 TO MANHOLE 40. MANHOLE

40 TO MAHOLE 47 SHALL ALSO BE REPAIRED.

a) TOTAL SHUTDOWN OF LINE MUST BE RESTRICTED IN TIMELINE. INSTALLATION PLAN TO SHOW EFFORT

IN REDUCING TIMELINE. 3 BUILDINGS WILL BE DIRECTLY AFFECTED BY THIS SHUTDOWN.

3. POTENTIAL TRADES ON PROJECT: EXCAVATION, CONCRETE, ASPHALT, PLUMBING, POSSIBLE SOIL TESTING, FENCING.

4. SECURITY FENCING CURRENTLY LOCATED ON B455 PERIMETER, IT MAY AFFECT THE SCOPE. CONTRACTOR TO

REPAIR FENCE IF AFFECTED.

5. FULL BASE SANITARY MAP WILL BE GIVEN TO BIDDER UPON AWARD OF PROJECT.

6. BASE PLUMBER INSPECTOR TO INSPECT AFTER DEMOLITION AND INSTALLATION. WRITTEN APPROVAL FROM

BASE PM TO PRIME IS REQUIRED BEFORE BACKFILL.

7. PHOTOS DURING PROCESS ARE REQUIRED FROM CONTRACTOR.

8. ALL CURRENT APPLICABLE UFC’S SHALL BE FOLLOWED THAT APPLY TO THIS PROJECT.

9. CONTRACTOR TO ALWAYS KEEP ONE LANE OF TRAFFIC OPEN, TO ACCOMMODATE THE MISSION.

10. CONTRACTOR TO KEEP ACCESS TO PARKING LOTS OPEN TO BUILDING USERS.

11. CONTRACTOR TO PROVIDE CONES AND CAUTION TAPE WHERE NECESSARY.

12. CONTRACTOR TO FOLLOW ALL OSHA GUIDELINES AND TO PROVIDE CONFINED SPACE PERMIT WHERE/WHEN

APPLICABLE.

13. REPAIR SOLUTION SHALL BE SUBMITTED IN WRITING PRIOR TO START OF PROJECT.

14. FULL BASE SANITARY MAP WILL BE GIVEN TO BIDDER UPON AWARD OF PROJECT.

15. CONTRACTOR TO ENSURE TRACER WIRE IS INSTALLED ON THIS PROJECT.

16. SEWER LINE ASBUILTS ARE REQUIRED AS A SUBMITTAL PRIOR TO PROJECT CLOSEOUT.

SPECIFICATIONS:

SEE OREGONBUYS FOR SPECIFICATIONS APPENDIX.

Slide Number 1
Slide Number 2