PERFORMANCE WORK STATEMENT (PWS)

B912 Repair Electrical Panel A

Part 1

General Information

1. GENERAL: This is a non-personnel services contract to provide replacement of electrical Panel A and fused disconnect feeding Panel A along with installing LED lighting controls and necessary wiring. Repair masonry and paint walls impacted by this work scope accordingly. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform:

replacement of electrical Panel A and fused disconnect feeding Panel A along with installing LED lighting controls and necessary wiring. Repair masonry and paint walls impacted by this work scope accordingly. As defined in this

Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.

1.2 Background: Building 912 is the Main Shaw AFB Chapel facility. Electrical Panel A is installed outside the

Chaplin’s Office in the Corridor leading into the Nave. See Attachment 4-Technical Exhibit 4 - B912 Electrical

Layout. Electrical Panel A is a Federal Pacific 100 Amp, 208/120 VAC, 3 Phase panel that feeds receptacles and lighting to the Chapel and adjacent offices. The J & K string of Light Emitting Diode (LED) light fixtures do not have LED light dimmer switches and have been operated with branch circuit breakers in positions 2, 4, 5, and 24.

The panel breakers are worn and create a humming noise and is a nuisance to the Chaplin staff.

All work shall meet Shaw AFB Design and Construction Stands and appropriate Unified Facilities Criteria (UFC).

1.3 Objectives: Replace electrical Panel A, fused disconnect, and install lighting controls. Repair masonry and paint walls as required with the impact of replacing Panel A.

1.4 Scope: Construction work to replace electrical panel A, fused disconnect and lighting controls for the B912 and masonry and painting as required.

Electrical:

• Refer to Attachment 4-Technical Exhibit 4 - B912 Electrical Layout

• Contractor shall replace or refurbish Electrical Panel A with an appropriate Panel that meets the branch circuit requirements. Contractor has the option to rebuild or refurbish the exiting panel. The objective is to provide a serviceable electrical panel that does not create a buzzing or humming noise.

• Contractor shall replace the Fused Disconnect A that feeds Panel A.

• The Disconnect A and Panel A are rated for 208/120 VAC / 100 Amps.

• Replace feeder cable to the Fused Disconnect A. Replace feeder cable from Fused Disconnect A to Panel

A.

• Install an LED light dimmer control for the string of “J” fixtures in the Nave area. This string of lights is controlled by breakers 2 and 4 in panel A. One breaker position in Panel A should be sufficient for these

LED lights.

• Install an LED light dimmer control for the string of “K” fixtures in the Chancel area. This string of lights is controlled by breakers 5 and 24 in panel A. One breaker position in Panel A should be sufficient for these

LED lights.

• Breakers and Fuse interrupt rating shall be a minimum of 22 KAIC.

• Contractor shall assess panel branch circuit loads and balance across the three phases as required.

• Install a Surge Suppression Device (SPD) At Panel A that meets UFC and Shaw AFB Design and

Construction Standard requirements.

Masonry:

• Repair and plaster corridor wall where new Panel A is installed as required.

Painting:

• Paint the section of the corridor wall where the new Panel A is installed.

• Paint the wall new raceway, junction boxes, and LED light dimmer control switches which are installed in the Nave area.

• Paint shall exactly match the existing color of the walls in these locations.

PHASING:

• Coordinate all work with the B912 Facility Manager so that religious services are not impacted by power outages or work activities. No work is to be conducted that disturbs religious services at this Chapel.

• Stage and pre-construct all work to minimize facility power outage time that would jeopardize the use of the Chapel for religious services.

1.5 Period of Performance: The period of performance shall be 552 calendar days. 52-66 weeks shall be allowed for material delivery. 90 days shall be allowed to perform work once materials are secured.

1.6 General Information

1.6.1 Quality Control: The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. As a minimum, the contractor shall develop quality control procedures that address the areas identified in Technical Exhibit 1, Performance Requirement

Summary. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. The Quality Control Plan QCP is to be delivered with the contractor’s proposal. After acceptance of the quality control plan the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his QC system.

1.6.2 Quality Assurance: The Government shall monitor and evaluate the Contractor’s performance to ensure services are received IAW requirements set forth in this PWS. The method of surveillance will be spelled out in the

Governments’ Quality Assurance Surveillance Plan. The COR will periodically inspect by watching actual task performance, physically checking an attribute of the completed task, checking a management information report, investigating customer complaints, or otherwise inspecting the task or its result to determine whether or not the performance meets the standards contained in this PWS. The COR may also inspect tasks not specifically mentioned in the Services Summary. The COR will document the results of the surveillance and this documentation will become the official Air Force (AF) record of the Contractor’s performance. When a performance threshold has not been met or Contractor performance has not been accomplished, the COR will initiate and provide a report to the

CO for action concerning the Contractor. The Contractor shall respond to the CO within ten (10) calendar days of receipt. The surveillance results shall be maintained as past performance information of the Contractor’s overall compliance with contract terms and conditions. The Government will neither supervise contractor employees nor control the method by which the contractor performs the required tasks. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the contractor believes that any actions constitute, or are perceived to constitute personal services, it shall be the contractor's responsibility to notify the Contracting Officer immediately.

The COR will be identified by separate letter. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance: maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.6.3 Recognized Holidays: [The contractor is not required to perform services on holidays but may with prior coordination with the COR and the building Facility manager.]

New Year’s Day Labor Day

Martin Luther King Jr.’s Birthday Columbus Day

President’s Day Veteran’s Day

Memorial Day Thanksgiving Day

Juneteenth National Independence Day Christmas Day

Independence Day

1.6.4 Hours of Operation: The contractor is responsible for conducting business, between the hours of 0730 to 1630 hours, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

1.6.5 Base Closure: The Government will notify the contractor of anticipated closure of the facility due to inclement weather or any other authorized closure. In the event of an unplanned closure of the facility the contractor will be notified using the contact information provided. The Contractor is not authorized to bill the Government for those hours unless the Contractor can perform productive duties from an alternate worksite. Work scheduled but not accomplished because of base closure, will be accomplished as soon as possible after reopening the base.

1.6.6 Place of Performance: The work to be performed under this contract will be performed at Building 912 Base

Chapel.

1.6.7 Type of Contract: The government will award a firm fixed price contract.

1.6.8 SECURITY REQUIREMENTS.

1.6.8.1. The Contractor should have no contact with classified materials and /or information

1.6.9 Special Qualifications: The Contractor shall maintain copies of employee’s current DHEC license and current respirator fit testing as required by SCDHEC. Records shall be available to the Shaw AFB COR/Inspector prior to work being accomplished.

1.6.10 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal

Acquisition Regulation Subpart 42.5. The contracting officer, Contracting Officers Representative (COR), and other

Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced.

Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government. Other topics may include (as applicable): opportunities to improve the contract, any modifications required of the contract, unsatisfactory performance inspections results, and valid customer complaints against each performance objective observed, and the results of corrective and preventive action measures. The Contractor will also notify the CO in writing, of work being requested or performed, if any, that the Contractor considers over and above the requirements of the contract. Appropriate action shall be taken to resolve outstanding issues. The

Government will provide the Base Environmental Plan at this meeting. The minutes of these meetings will be documented in writing, signed by the CO and any other signatures as deemed appropriate, and distributed to the

COR functional area and the Contractor. Should the Contractor not concur with the minutes, the Contractor will set out in writing to the CO any areas of non-concurrence. These meetings shall be held as needed, but not less than bi-annually after the contract is awarded. There will also be an initial meeting to take place 30 days after the contract has been awarded.

1.6.16 STANDARDS: The Government is authorized to restrict employment under this contract of any Contractor personnel or prospective Contractor personnel, who is identified as a potential threat to the health, safety, security, general well-being, or the operational mission of the installation (to include annexes such as Poinsett and Wateree) and its population. A determination may also remove Contractor personnel for, but is not limited to, incidents involving most immediately identifiable types of misconduct or delinquency such as: disorderly conduct, use of abusive or offensive language, intimidation by words or actions, fighting, participation in disruptive activities which interferes with the normal operations or brings discredit to the Government, theft, vandalism, sexual harassment, or any criminal actions. This also includes selling, consuming, or being under the influence of intoxicants, drugs, or substances which produce similar effects while in or on Federally-controlled property. Contractor personnel shall only smoke and/or use tobacco products in designated and approved smoking/tobacco use areas. If the CO directs removal of Contractor personnel for violating the above provisions, the Contractor shall immediately remove the individual(s) at no cost to the Government. Removal of employees for misconduct does not alleviate the Contractor from providing services. Per Shaw AFB Plan 31- 101, the installation commander has authority to debar any individual from the installation who commits a crime or offense prejudicial to good order and discipline. All disputes to the CO’s decision must be filed within ten (10) days of the decision to the Base Operations Support

Flight Chief. The removed Contractor personnel may not resume work unless/until a decision is made by the

Government CO overturning the removal decision.

1.6.17 SUBCONTRACTOR COMPLIANCE: The Contractor shall be responsible for ensuring Subcontractors satisfy the requirements set forth in the contract. The Contractor shall include a provision in all subcontracts to require Subcontractor compliance with terms and conditions of this contract.

1.6.18 EMPLOYING GOVERNMENT PERSONNEL: The Contractor shall not employ any person who is an employee of the United States Government if the employment of that person would create a conflict of interest.

Further, the Contractor shall not employ any person who is an employee of the Department of the Air Force, either military or civilian, unless such person seeks and receives approval in accordance with DODD 5500.7R, Joint Ethics

Regulation. In addition, the Contractor shall not employ any person who is an employee of the Department of the

Air Force if such employment would be contrary to the policies contained in AFI 64-106, Industrial Labor Relations

Activities. All questions of “conflict of interest” shall be referred to the CO. The Contractor is cautioned that off duty active military personnel hired under this contract are always subject to Permanent Change of Station (PCS), change in duty hours or deployment. Military Reservists and National Guard members may be subject to recall to active duty. The abrupt absence of these personnel could adversely affect the Contractor's ability to perform. Their absence at any time shall not constitute an excuse for nonperformance under this contract.

1.6.19 COMPLIANCE WITH LABOR LAWS: The Contractor shall comply with all applicable laws pertaining to wages, worker’s compensation, equal opportunity, Service Contract Act, and so forth, as implemented by Air Force directives and required by law.

1.6.20 Continuation of Essential Contractor Services: This requirement is not considered mission essential, and services will be suspended during a declared emergency. Contractor personnel will not be required or expected to perform maintenance in such an event as a hurricane or when travel is deemed “unsafe” by local authorities.

Inspections and/or maintenance actions due during this time will be completed as soon as the condition warranting the delay is lifted. This maintenance will not be withheld until the next service interval and contractor personnel are expected to perform the maintenance that was to be performed prior to the delay within 5 days.

1.6.21 Safety Requirements: The Contractor shall perform work in a safe manner as required by OSHA Safety and

Health Requirements and applicable Department of Labor, Department of Defense and Air Force safety standards.

The Contractor shall provide a verbal report to the CO as soon as possible following an occurrence of damage to

Government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Provide a completed copy of the required Accident Investigation Report to the CO within five (5) calendar days of each occurrence. The Accident Investigation Report shall be prepared and submitted IAW AFI 91-204.

1.6.24.1 Mishaps: In the event of an accident/mishap, the Contractor shall take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the CO.

1.6.24.2 Investigations: If the Government elects to conduct an investigation of the accident/mishap, the Contractor shall cooperate fully and assist Government personnel in the conduct of investigation until the investigation is completed.

1.7. Environmental Management System, Executive Summary For Contractors:

1.7.1. Introduction. In accordance with Air Force Instruction 32-7001, Environmental Management, Shaw Air

Force Base (SAFB) has implemented an ISO 14001 based Environmental Management System (EMS). The goal of the EMS is to improve the core business processes of SAFB, as they relate to the environment, seeking to improve and enhance performance in support of the overall mission. The EMS supports a transition from a compliance driven program to one that focuses pollution prevention efforts on managing both environmental and mission risks.

1.7.2. Environmental Policy. Central to the SAFB EMS is the base environmental policy set by Wing Leadership.

The policy establishes fence-to-fence applicability to include all 20th Fighter Wing organizations, all tenants, and contractors conducting business on SAFB property. It further extends applicability to the areas under SAFB control at Wateree Recreational Area and the Poinsett Electronic Combat Range. As indicated in the policy, SAFB leadership is committed to continual improvement, pollution prevention, regulatory compliance, the conservation of natural resources, and the integration of environmental awareness into day-to-day operations.

Through such commitments, SAFB is able to set environmental objectives and targets with focus on enhancing the mission through environmental management.

1.7.3. What is EMS? An EMS is that part of an overall management system that includes organizational structure, planning activities, responsibilities, practices, procedures, processes, and resources for developing, implementing, achieving, reviewing, and maintaining the environmental program and achieving environmental goals based on continual-improvement. The EMS is intended to help SAFB balance its mission with maintaining regulatory compliance and developing sustainability strategies to secure this base’s ability to support current and future mission requirements.

1.7.4. Significant Aspects. An aspect is any interaction with the environment caused by activities on SAFB.

Through the EMS, these aspects have been systematically inventoried and evaluated based on the following ranking criteria.

• Relative financial cost

• Risk to the environment

• Risk of regulatory non-compliance

• Potential mission degradation

• Community Concerns

These criteria are scored and weighted for each aspect as recommended by Wing

Leadership to establish those environmental aspects deemed most critical to address.

1.7.5. What is My Role? As a contractor performing work on SAFB property you must understand that any activities that directly or indirectly impact the environment, especially the significant aspects listed above, must be communicated with the 20th Civil Engineer Squadron, and the greatest precaution should be taken to avoid negative impacts in these areas. Think of EMS the same way you think about safety. Just as you are aware of all safety hazards associated with your job, you must also be aware of all environmental impacts associated with your job and mitigate those to the extent possible.

To find out more about the SAFB EMS or to discuss potential impacts of contracted activities, contact the 20th

Civil Engineer Squadron at 803.895.9987.

1.7.6. 20th Fighter Wing Commander Memorandum on Shaw AFB Commitment to Environmental Protection:

PART 2

DEFINITIONS & ACRONYMS

2. DEFINITIONS AND ACRONYMS:

2.1. DEFINITIONS:

2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5. DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8. QUALITY ASSURANCE. The government procedures to verify that services being performed by the

Contractor are performed according to acceptable standards.

2.1.9. QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.12. WORK WEEK. Monday through Friday, unless specified otherwise.

2.2. ACRONYMS: [List all acronyms used in the PWS and what they represent. At a minimum, insert the acronyms provided below].

ACOR Alternate Contracting Officer's Representative

AFFARS Air Force Federal Acquisition Regulation Supplement

AFI Air Force Instruction

CFR Code of Federal Regulations

CONUS Continental United States (excludes Alaska and Hawaii)

COR Contracting Officer Representative

ACOT Alternate Contracting Officer's Representative

COTS Commercial-Off-the-Shelf

DD250 Department of Defense Form 250 (Receiving Report)

DD254 Department of Defense Contract Security Requirement List

DFARS Defense Federal Acquisition Regulation Supplement

DMDC Defense Manpower Data Center

DOD Department of Defense

FAR Federal Acquisition Regulation

HIPAA Health Insurance Portability and Accountability Act of 1996

CO Contracting Officer

OCI Organizational Conflict of Interest

OCONUS Outside Continental United States (includes Alaska and Hawaii)

ODC Other Direct Costs

PIPO Phase In/Phase Out

POC Point of Contact

PRS Performance Requirements Summary

PWS Performance Work Statement

QA Quality Assurance

QAP Quality Assurance Program

QASP Quality Assurance Surveillance Plan

QC Quality Control

QCP Quality Control Plan

TE Technical Exhibit

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. GOVERNMENT FURNISHED ITEMS AND SERVICES:

3.1. Services: (N/A):

3.2 Facilities : The Government will provide access all areas of B912 as needed to complete the requirement.

3.3 Utilities: The Government will provide required utilities for the repair, i.e., electrical power. The Contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment.

3.4 Equipment (N/A):

3.5 Materials (N/A):

Security Police: The Government will provide general on-base security police service. Use the following numbers as needed:

Security-Police and Fire Protection: Call phone number 911.

Security Police Crime Stop Numbers: Crime Stop Number is 803-895-3669/3670.

Emergency Medical Service: The Government will provide emergency medical treatment for Contractor personnel while they are performing duties associated with this contract. The Contractor shall reimburse the Government for the cost of medical treatment and patient transportation at the current inpatient or outpatient treatment rate as appropriate.

Forms and Publications: The Government will provide forms and publications to perform the work required by the contract. If network access is included in this contract, the Government will provide electronic access to required forms and publications. Publications can be accessed on-line at http://www.e-publishing.af.mil.

Base Civil Engineers: The Government will provide fire prevention inspections and maintenance of Government furnished fire systems.

Postal/Installation Distribution: The Government will provide Federal Government official mail service only to

Shaw AFB and its annexes to include inter-office distribution within the base. All commercial mail services are the responsibility of the Contractor.

Parking: Space is available for common vehicles at the parking lot adjacent to the facilities.

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1 General : The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.

4.2 Secret Facility Clearance (N/A):

4.3. Materials. The Contractor shall provide all materials required for the completion of this project, i.e. electrical equipment and components, wire, masonry, paint, etc.

4.4. Equipment:. The Contractor shall provide all equipment required to complete this project, i.e. respirators, filters, coveralls, any and hand tools.

PART 5

SPECIFIC TASKS

5. Specific Tasks:

5.1. Basic Services. The contractor shall provide construction services for Building 912 to install a fused disconnect, electrical panel, lighting controls, wiring, masonry work, and painting.

5.3. CONTRACTOR MANAGEMENT REPORTING (CMR): The Contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via secure data collection site. The contractor is required to complete all required data fields at the Air Force CMRA link http://www.ecmra.mil. Reporting inputs will be for the labor executed during the period of performance for each Government Fiscal Year (FY), which runs 1 October through 30 September. While inputs may be reported any time during the FY, all data shall be reported no later than 31 October of each calendar year. Contractors may direct questions to the CMRA help desk.

Uses and Safeguarding of Information: Information from the secure web site is considered to be proprietary in nature when the contract number and contractor identity are associated with the direct labor hours and direct labor dollars. At no time will any data be released to the public with the contractor name and contract number associated with the data.

http://www.ecmra.mil/

PART 6

APPLICABLE PUBLICATIONS

6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)

6.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.

Shaw AFB Design and Construction Standards. Applicable Unified Facilities Criteria (UFC).

PART 7

ATTACHMENT/TECHNICAL EXHIBIT LISTING

7. Attachment/Technical Exhibit List:

7.1. Attachment 1-Technical Exhibit 1 – Services Summary

7.2. Attachment 2-Technical Exhibit 2 – Deliverables Schedule

7.3. Attachment 3-Technical Exhibit 3 – Estimated Workload Data

7.4. Attachment 4-Technical Exhibit 4 - B912 Electrical Layout

TECHNICAL EXHIBIT 1

Services Summary

The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective

(The Service required—usually a shall statement)

Standard PERFORMANCE

THRESHOLD (THIS IS THE

MAXIMUM ERROR RATE. IT

COULD POSSIBLY BE “ZERO

DEVIATION FROM

STANDARD”)

Method of

Surveillance

SS # 1.

The contractor shall provide labor and equipment to perform replacement of electrical Panel A and fused disconnect feeding Panel A along with installing

LED lighting controls and necessary wiring. Repair masonry and paint walls impacted by this work scope accordingly.

The contractor provided services as noted.

Work shall be done 100% with no deviation from the standard.

Periodic surveillance from the government

COR.

TECHNICAL EXHIBIT 2

DELIVERABLES SCHEDULE

DELIVERABLE FREQUENCY

# OF

COPIES MEDIUM/FORMAT SUBMIT TO

Submittals shall include, but not be limited to:

1. Submittals to include any and all drawings, calculations and materials that are necessary to provide a complete and constructible document that meets the intent of the SOW. No engineered/stamped drawings are required.

2. All building electrical equipment layout location and details. Service sizing and major electrical equipment shall be shown at this time. Layouts for any new receptacles or updated receptacles.

3. Electrical material submittals for cable, panels, breakers, dimmer switches, surface mount raceway, and fused disconnect, etc. for

Government review and approval.

4. Finish materials for masonry and paint.

Submittal approval and material delivery time: 52-66 weeks.

Construction time – 90 calendar days

Hard copies

Electronic in dwg and pdf format

20 CONS

As- Builts:

Provide after construction completion (all will include one bound copy and an electronic copy):

1. Completed DD Form 1354 including all costs and quantity breakouts.

2. All construction documents/ submittal including all as-built drawings, field modifications and design corrections made during the process of construction. All drawings shall meet the Shaw AFB design standards and be in

AutoCAD V2017 or later format.

Submittals shall be provided by email.

As-Builts

The final product shall be delivered at the completion of the project.

Hard copies

Electronic in dwg and pdf format

20 CONS