01 45 00.00 10AT.pdf
PDF 651 KB Posted
- Solicitation number
- W9128F21R0007
About this file
This document contains a sample quality control report for a federal construction contract and details of a related federal contract opportunity. The quality control report provides daily logs from November to December 2004 for a fire station construction project under contract number W9128F-04-C-0013 with the Department of Defense. The logs indicate no work was performed on the project during the reported period.
The related federal contract opportunity is a $99 million Rapid Disaster Infrastructure Multiple Award Task Order Contract set aside for HUBZone small businesses. The U.S. Army Corps of Engineers, Omaha District is seeking proposals due by January 15, 2021 for indefinite delivery indefinite quantity task orders for rapid disaster infrastructure support across the contiguous U.S., Alaska, Hawaii and outlying areas. Task orders will be issued on an as-needed basis and may be firm-fixed price or cost reimbursement. There is no limit on the number of task orders that can be awarded under the contract.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTORS QUALITY CONTROL REPORT (QCR)
DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
25 Nov 2004 - Thursday
W9128F-04-C-0013 NAD/B Main Fire Station
CONTRACTOR WEATHER
Weather Not EnteredBryan Construction
QC NARRATIVES
No QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
No activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
No labor hours were Reported today
Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported today Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1CONTRACTORS QUALITY CONTROL REPORT (QCR)
DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
26 Nov 2004 - Friday
W9128F-04-C-0013 NAD/B Main Fire Station
CONTRACTOR WEATHER
Weather Not EnteredBryan Construction
QC NARRATIVES
No QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
No activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
No labor hours were Reported today
Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported today Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1CONTRACTORS QUALITY CONTROL REPORT (QCR)
DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
29 Nov 2004 - Monday
W9128F-04-C-0013 NAD/B Main Fire Station
CONTRACTOR WEATHER
Weather Not EnteredBryan Construction
QC NARRATIVES
No QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
No activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
No labor hours were Reported today
Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported today Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1CONTRACTORS QUALITY CONTROL REPORT (QCR)
DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
30 Nov 2004 - Tuesday
W9128F-04-C-0013 NAD/B Main Fire Station
CONTRACTOR WEATHER
Weather Not EnteredBryan Construction
QC NARRATIVES
No QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
No activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
No labor hours were Reported today
Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported today Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1CONTRACTORS QUALITY CONTROL REPORT (QCR)
DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
01 Dec 2004 - Wednesday
W9128F-04-C-0013 NAD/B Main Fire Station
CONTRACTOR WEATHER
Weather Not EnteredBryan Construction
QC NARRATIVES
No QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
No activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
No labor hours were Reported today
Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported today Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1CONTRACTORS QUALITY CONTROL REPORT (QCR)
DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
02 Dec 2004 - Thursday
W9128F-04-C-0013 NAD/B Main Fire Station
CONTRACTOR WEATHER
Weather Not EnteredBryan Construction
QC NARRATIVES
No QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
No activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
No labor hours were Reported today
Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported today Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1CONTRACTORS QUALITY CONTROL REPORT (QCR)
DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
03 Dec 2004 - Friday
W9128F-04-C-0013 NAD/B Main Fire Station
CONTRACTOR WEATHER
Weather Not EnteredBryan Construction
QC NARRATIVES
No QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
No activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
No labor hours were Reported today
Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported today Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1CONTRACTORS QUALITY CONTROL REPORT (QCR)
DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
06 Dec 2004 - Monday
W9128F-04-C-0013 NAD/B Main Fire Station
CONTRACTOR WEATHER
Weather Not EnteredBryan Construction
QC NARRATIVES
No QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
No activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
No labor hours were Reported today
Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported today Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1CONTRACTORS QUALITY CONTROL REPORT (QCR)
DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
07 Dec 2004 - Tuesday
W9128F-04-C-0013 NAD/B Main Fire Station
CONTRACTOR WEATHER
Weather Not EnteredBryan Construction
QC NARRATIVES
No QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
No activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
No labor hours were Reported today
Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported today Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1CONTRACTORS QUALITY CONTROL REPORT (QCR)
DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
09 Dec 2004 - Thursday
W9128F-04-C-0013 NAD/B Main Fire Station
CONTRACTOR WEATHER
Weather Not EnteredBryan Construction
QC NARRATIVES
No QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
No activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
No labor hours were Reported today
Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported today Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
01 45 00.00 10AT - SAMPLE QUALITY CONTROL REPORT