TRABUCO HOLY JIM DAM DEMOLITION

WORK RESTRICTIONS Section 01 14 00-1

SECTION 01 14 00 - WORK RESTRICTIONS

PART 1 – GENERAL

1.1 SCOPE: This work consists of the use by the Contractor of areas and facilities owned by the Government during the construction of this project. Work must be completed between December 1 2019, and February

April 30 2020.

1.2 MEASUREMENT AND PAYMENT

A. No separate measurement or payment will be made for work specified in this section.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 The Contractor will have full use of the site within the project area within twenty-five feet of stream centerline for demolition operations. The Contractor may store equipment along San Juan Creek. The

Contractor shall be responsible for providing for the security of the equipment and materials delivered and stored at the jobsite. Contractor’s use of the delineated portion of the premises is limited by the

Government’s right to perform work or to retain other Contractors on portions of the project.

3.2 The Contractor shall take all reasonable precautions to ensure a safe construction area.

3.3 The Contractor's operations shall at no time interfere with emergency vehicle traffic.

3.4 The Contractor shall park equipment only in areas designated by COR.

3.5 Stockpile and equipment placement or storage areas shall be approved by Contracting Officer.

3.6 No welding or cutting operation shall proceed until an approved welding permit has been issued by qualified

Forest Service personnel.

END OF SECTION 01 14 00