This document contains sections from a state and local contract opportunity issued by the Eugene Water & Electric Board (EWEB) for construction services to provide and install fire detection systems at EWEB's hydroelectric project at Carmen Smith in Linn County, Oregon. The contract requires bidders to meet specific Minimum Contractor and Specialty Subcontractor Qualifications, and to comply with all Bureau of Labor and Industries (BOLI) and Construction Contractors Board (CCB) requirements. The project involves the completion of the work within a specified period, the issuance of a Certificate of Substantial Completion, and the final completion of all contract requirements, excluding warranty work.
The contract opportunity indicates that EWEB is requesting bids for the fire detection systems project at the Carmen Powerhouse located in Linn County, Oregon. Bidders must meet the defined Minimum Contractor and Specialty Subcontractor Qualifications, and comply with all relevant state and local requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 2 22-046-PW.pdf | ||
| 00430-A First Tier Sub.docx | DOCX document | |
| Addendum 3 22-046-PW.pdf | ||
| 22-046-PW Fire Detect Install.pdf | ||
| Addendum 1 22 046 PW.pdf | ||
| Notice of Intent to Award- All Bidders.pdf | ||
| Procurement Information~48.docx | DOCX document | |
| Pre-Bid Sign in March 2022.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Eugene Water & Electric Board Section 00620-A
Rev 8/17 Section 00620-A
CONTRACTOR AFFIDAVIT - PAYMENT OF ALL ACCOUNTS
STATE OF: ___________________________
COUNTY OF: _________________________
I, , A representative of __________ being duly sworn, do depose and say that I pay, or supervise payment, for all labor, materials, services and supplies used by same in the construction of the ____ and other related work, under contract with the Eugene Water & Electric Board; that all persons employed on said project have been paid the full wages earned at not less than the minimum rates specified for each worker classification; that all bills for materials, services and supplies have been fully paid; and that there are no liens or encumbrances of any nature whatsoever pending against the work performed or material furnished, to the best of my knowledge and belief.
CONTRACTOR / PRINCIPAL
Signature
Name and Title - Print
Company Name
NOTARY:
Sworn to before me this day of _______, 20___.
Notary Public for Oregon - Signature
Printed Name of Notary Public
My Commission Expires:
CERTIFICATE OF SUBSTANTIAL COMPLETION
PROCEDURE FOR PROCESSING
Substantial Completion is the stage in the progress of the Work when the Work or designated portion is sufficiently complete in accordance with the Contract Documents and EWEB can fully occupy or use the
Work for its intended function.
When the Contractor considers that the Work, or a portion that EWEB agrees to accept separately, is substantially complete, the EWEB Contract Administrator shall prepare a punchlist to be completed or corrected. The Contractor shall proceed promptly to complete and correct items on the list. Failure to include an item on this list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. If the Contract Administrator's inspection discloses any item, whether included on the Contractor's list or not, that is not in accordance with the requirements of the
Contract Documents, the Contractor shall, before issuance of the Certificate of Substantial Completion, complete or correct such item upon notification by the Contract Administrator. The Contractor shall then submit a request for another inspection by the Contract Administrator to determine Substantial
Completion. When the Work or designated portion is substantially complete, the Contractor will prepare a Certificate of Substantial Completion that shall establish the date of Substantial Completion and shall establish responsibilities of EWEB and Contractor for security, maintenance, utilities, damage to the Work and insurance, and shall fix the time within which the Contractor shall finish all items on the list accompanying the Certificate. The Certificate of Substantial Completion shall be considered valid only when all parties' signatures appear on this document.
CERTIFICATE OF SUBSTANTIAL COMPLETION
PROJECT NAME: ___________________________________________________________________
CONTRACT ADDRESS: _______________________________________________________________
CONTRACT NUMBER: TASK ORDER NUMBER: ____________________
CONTRACT NAME: __________________________________________________________________
CONTRACTOR NAME: ______________________
DATE OF CERTIFICATE ISSUANCE:
PROJECT OR DESIGNATED PORTION SHALL INCLUDE: _____________________________________
The work performed under this Contract has been reviewed and found to be substantially complete.
The Date of Substantial Completion of the Project or portion thereof designated above is hereby established as ______________ which is also the date of commencement of applicable warranties required by the Contract Documents, except as stated below.
DEFINITION OF DATE OF SUBSTANTIAL COMPLETION
The Date of Substantial Completion of the Work or designed portion thereof is the Date certified by the EWEB Contract Administrator when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.
A Punch List (as defined in Section 00700), prepared by the EWEB Contract Administrator, is attached hereto. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents.
The Owner (EWEB) accepts the Work or designed portion thereof as substantially complete and will assume full possession thereof at (time) on (date).
EWEB CONTRACT ADMINISTRATOR Date
The Contractor will complete or correct the Work on the list of items attached hereto within ________ days from the above Date of Substantial Completion.
CONTRACTOR BY Date
NOTICE OF FINAL COMPLETION
CONTRACT NAME: ___________________________________________________________________
CONTRACT NUMBER: TASK ORDER NUMBER: ________________________
PROJECT ADDRESS: ___________________________________________________________________
CONTRACTOR NAME: _________________________________________________________________
CONTRACTOR ADDRESS: _______________________________________________________________
OWNER: EUGENE WATER & ELECTRIC BOARD
PO BOX 10148
EUGENE, OR 97440-2148
The work performed under this Contract has met the requirements of Final Completion, defined as the final completion of all requirements under the Contract, including Contract Closeout, as described in Section 00700 General Conditions, but excluding Warranty Work, further described in Section 00700, and the final payment and release of all retainage, if any.
EWEB CONTRACTOR
Signature of EWEB Contract Administrator Signature of Representative
Name - Print Representative Name and Title - Print
Date Representative's Phone
END OF SECTION 00620