0003687 Attachment F - DPS Program of Requirements.pdf
PDF 11 MB Posted
- Solicitation number
- 0003687
- Issued by
- Williamson County, Texas
About this file
This Program of Requirements (POR) document was prepared for the Texas Department of Public Safety (TXDPS) Training Academy project in Florence, TX, in coordination with the Texas Facilities Commission (TFC) and Broaddus Companies. The document outlines requirements for Phase I of a new training academy campus on a 135.58-acre site, including an administration building (80,738 SF), classroom building (41,477 SF), recruit dormitories (106,941 SF), cafeteria (26,623 SF), indoor physical fitness facilities (106,462 SF), and various support facilities. The project schedule indicates design services will commence July 31, 2024, with construction completion targeted for April 30, 2027, followed by a 12-month warranty phase ending April 30, 2028. The project will utilize a Construction Manager at Risk (CMAR) delivery method.
The total project budget is $366,833,963, with current cost estimates at $320,178,378 including a 10% program contingency ($24.5M). The project includes significant infrastructure components such as a 16-inch water line extending 32,300 LF, a 2-million-gallon water tower, wastewater treatment plant, and detention basins. Future Phases II and III are planned but not currently funded, which would add in-service personnel dormitories, a 400-stall parking garage, and indoor aquatics facility. The document provides detailed space programming requirements for each facility, including specific room sizes, quantities, and technical specifications for building systems and site improvements.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Texas Department of Public Safety (TXDPS)
Program of Requirements (POR) V2
TXDPS Training Academy
Florence, TX
July 23, 2024
RFQ #0003687 Commisssioning Services for DPS Training Academy Attachment F
TXDPS Training Academy | B24228.00
Program of Requirements | July 23, 2024
2 | P a g e
Table of Contents
Table of Contents
Section I: General Information
Section II: Project Team Members
2.1 Steering Committee
Section III: Executive Summary
3.1 Budget
3.2 Schedule
3.3 Project Planning Assumptions
3.4 Project Phasing
Section IV: Project Budget & Schedule
4.1 Project Budget
4.2 Project Schedule Narrative
4.3 Phase I: Project Schedule
Section V: Project Requirements
5.1 General Requirements
5.2 Codes, Standards, & Regulations
5.3 Energy Conservation
5.4 Risk
5.5 Project Specifications Assumptions
5.6 Program Buildings & Site Elements
Section VI: Site Planning
6.1 Site Location Maps
6.2 Existing Site Conditions
6.3 Parking Requirements
6.4 Site Investigations
6.5 Availability & Location of Utilities
6.6 Site Test Fit
Section VII: Space Program
Section VIII: POR Certification & Sign Off
8.1 User Group
Section IX: Appendices
Appendix A: Master Schedule
Appendix B: Construction Cost Estimate
Appendix C: TXDPS Water Service PVC Option
Appendix D: 2023 Project Analysis vs. 2024 Program of Requirements
3 | P a g e
Section I: General Information
Project Details
Project Name TXDPS Training Academy
Project Number B24288.00
Location Near the City of Florence, TX
Date Prepared July 23, 2024
Prepared By Broaddus Companies & Kimley-Horn
Delivery Method CMAR
Type of Project New Construction & Addition / Renovation
New Site Construction
Air-Conditioned Buildings Area 362,241 SF
Site Elements Area 891,732 SF
Total Area 1,253,973 SF
Section II: Project Team Members
2.1 Steering Committee
Steering Committee
User Coordinator James “Eddie” King
Title Deputy Administrator Construction
Office Phone 512.424.2219
Email James.King@dps.texas.gov
Committee Member Kevin Sandberg
Title TFC Senior Project Manager
Office Phone 512.463.8198
Email Kevin.sandberg@tfc.texas.gov
Committee Member Jason Griffin
Title Major
Office Phone 512.424.5784
Email jason.griffin@dps.texas.gov
Committee Member Derek Prestridge
Title Assistant Chief
Office Phone 512.424.5783
Email derek.prestridge@dps.texas.gov
Committee Member Shannon Hamby
Title Captain
Office Phone 512.424.7132
Email shannon.hamby@dps.texas.gov
4 | P a g e
Section III: Executive Summary
According to the Project Analysis (PA) document dated January 18, 2023, “TXDPS has established a long-term goal to establish a modernized facility for training sworn personnel within TXDPS as well as officers of federal, state, and local law enforcement partners. To this end, TXDPS proposes moving all TOD activities to Williamson County and significantly enhancing the Williamson County facilities.”
The existing site in Williamson County has been expanded to the northeast by 135 acres of new land.
TXDPS has determined the best location for the new TXDPS Training Facility to be located at the new site. The program for this new building includes only Phase I. Phases II and III are to be completed later pending legislative approval. The new land has space for the initial program. There is available remaining space to accommodate 100% expansion of the recruit and in-service dorms, and related programming.
3.1 Budget
The TXDPS Phase I Total Project Cost Budget is $366,833,963. The current Total Project Cost (TPC) estimate based on the new programming input from the end users, change in phase elements, and updated cost of work is $320,178,378, including a 10% program contingency ($24.5M).
A summary cost breakdown has been categorized as follows:
• Construction. Expenses associated with constructing or renovating the training facility buildings and site elements
• Professional Services. Fees for project management, architectural, engineering, and other technical expertise involved in design and construction
• Support Expenses. Owner procured costs for real estate acquisition, furniture, training equipment, and technological hardware/software, TAB, CMT, and miscellaneous expenses
• Technology. Expenses for IT, telecommunications, and security infrastructure
• Miscellaneous Expenses. Expenses for move costs, commissioning, and wayfinding
• Contingency. Reserve allocation for unforeseen costs that may arise during project execution
3.2 Schedule
The overall schedule is for the A/E to start on 7/31/2024 and the construction finishes on 4/30/2027, and the 12-month warrantee phase concludes on 4/30/2028. A comprehensive project timeline will be provided by CMAR for the awarded phases. The anticipated schedule will address key milestones, including:
• Completion of environmental assessments and permitting processes.
• Finalization of design documents for all project phases.
• Construction milestones for site work, building construction, and FF&E installation.
• Facility testing, occupancy approvals, and training commencement.
This information is crucial for securing funding approvals, managing project resources, and ensuring the timely delivery of a modernized training facility for the TXDPS.
3.3 Project Planning Assumptions
The 2023 program has been validated to the stated program elements and space requirements to confirm the noted figures will accomplish the desired outcomes. The Site Test Fit has been developed to show the approximate functional relationships and illustrate the space required for program elements.
The Cost Estimate has been developed to verify the program details to assure all projects costs are
5 | P a g e captured, including soft cost expectations to validate the Total Project Cost (TPC) allocation for the project.
The TXDPS Training recruit class model description and daily activities are:
Recruit Class Training Calendar
• 125-member recruit class.
• 30 weeks per class, 3 classes per year, 6 months long, rotating about 2- to 3-month intervals.
• Might have 2 to 3 classes on site concurrently.
Typical Daily Schedule for Recruit Class
• 5:00am – 6:30am: PT Field
• 6:30am – 7:15am: Hygiene / Breakfast
• 7:15am – 11:00am: Classroom
• 11:00am – 12:00pm: Lunch / Uniforms / Administration
• 12:00pm – 5:00pm: ACT (Arrested Control Tactics) Classroom
• 5:00pm – 6:00pm: Dinner
• 6:00pm: End the day of training
• Studying in their own time, sometimes structured evening training if needed.
Operational Hours
The facility is operational 24 hours per day, 7 days per week, 365 days per year.
6 | P a g e
3.4 Project Phasing
The project is to be built in three phases.
Phase I (Funding Available for Phase I Only)
1. Administration Building (3 Story)
2. Classroom Building (1 Story)
3. Dorms for Recruits (2 Story – Can Expand 100%)
4. Cafeteria (1 Story)
5. Indoor Physical Fitness (2 Story)
a. Indoor Gym, Fitness, & Wellness Unit – Separate Pricing
b. Arrest & Control Tactics – Separate Pricing
6. Outdoor Physical Fitness (Track & Field)
7. Central Utility Plant (1 Story)
8. Maintenance / Warehouse Building (1 Story)
9. Water Tower
10. Water & Pump Station
11. Outdoor Physical Fitness Pavilion (1 Story)
12. Perimeter Fence for New Site
13. 1.5-Mile Fitness Trail
14. Parking Lot for 800 Stalls
15. Detention Basin Water Quality Basin
16. Bullet Traps (Existing Site)
17. Mobile Targeting System (Existing Site)
18. Wastewater Treatment Plant
Phase II (Future Phase is Not Funded)
19. Dorms for In-Service Personnel (2 Story – Can Expand 100%)
20. Parking Garage for 400 Stalls (2 Story)
21. Maintenance / Warehouse Building (Combined with #22)
22. Central Utility Plant (Can Expand 100%)
Phase III (Future Phase is Not Funded)
23. Indoor Aquatics
7 | P a g e
Section IV: Project Budget & Schedule
4.1 Project Budget
Notes
1 Offsite Utilities Cost of $15M is included in the Construction Line
2 Cost / Fee is Known Amount
3 Building Uses are Administrative, Educational, Food Service, Residential, & Physical Training
4 Bollards, Electrical Door Strikes, Card/Badge Readers, etc.
5 Texas Facilities Commission Project Fee is current actual cost as provided by DPS and TFC
6 Percentages are calculated as a portion of the Construction Cost
Project Budget Detail
Total Project Costs Estimate Perc.6
Construction (Includes 5% Design & 5% Contractor Contingency) 1 $245,492,324
Professional Services $31,743,640 12.30%
Project Management Fee 2 $8,104,671 2.76%
Project Management Reimbursables (Above) 2 0 0.00%
Project Management Contingency (Above) 2 0 0.00%
TFC Project Manager 5 $2,751,255 0.94%
A/E Basic Design Fee $20,866,848 8.50%
A/E Reimbursables $20,867 0.10%
Support Expenses (Owner Procured) $9,064,482 2.33%
Real Estate Costs 2 $3,131,889 1.07%
Boundary Survey & Assessment 2 $175,174 0.06%
Tree and Topo Survey 2 $27,400 0.01%
Moveable Furniture (FF&E) $3,906,012 1.59%
Special Equipment (Based on 5 Different Building Uses) 3 $490,985 0.20%
Test & Air Balance $245,492 0.10%
Material Testing $736,477 0.30%
Geotechnical $184,119 0.07%
Interior Branding $122,746 0.05%
ADA/TDLR Consultant (in A/E Fee) 0 0.00%
Printing & Reprographics $24,549 0.01%
Postage & Shipping $19,639 0.01%
Technology $7,364,769 3.00%
Data – Hardware & Equipment $3,068,654 1.25%
Data - Software (by owner) 0 0.00%
Audio / Visual $859,223 0.35%
Telecommunications $368,238 0.15%
Security (Miscellaneous Building Hardening) 4 $3,068,654 1.25%
Miscellaneous Expenses $1,963,938 0.80%
Advertising & Bid (Incurred Cost by Owner) 0 0.00%
Signs / Graphics / Wayfinding (Exterior Signage) $122,746 0.05%
Commissioning $1,841,192 0.75%
Sub-Total $295,629,154
Owner Contingency (10% min.) $24,549,232 10.00%
Total Project Cost for Phase 1 Program $320,178,387
Total Project Cost Budget $366,833,963
Variance (Under Budget) $46,655,576 16.05%
8 | P a g e
4.2 Project Schedule Narrative
The initial Phase I project schedule, outlined in 2023, gave an anticipated completion date of December
2029. A summary of the initial master schedule is shown on the following page and the full master schedule is included in Appendix A.
While this POR provides a high-level project timeline, a more detailed schedule will be established after the CMAR is selected. Following the CMAR's proposal outlining their phasing and construction sequencing plan, a further schedule validation process will be required. This validation will involve collaboratively refining the schedule with the CMAR to account for the agreed upon packaging strategy, their specific construction methodology, resource availability, and potential risk mitigation strategies.
This collaborative effort will ensure a realistic and achievable project timeline that considers all aspects of construction execution.
4.3 Phase I: Project Schedule
Schedule Detail
Milestone Start Date Completion Date
Owner Selections
Project Management Services 1/1/2024 3/1/2024
A/E Services 4/10/2024 7/30/2024
CMAR Services 4/15/2024 9/15/2024
Pre-Construction Services
Design Programming Phase & Reviews 2/26/2024 8/22/2024
Schematic Design Phase & Reviews 7/31/2024 12/2/2024
Design Development Phase & Reviews 12/3/2024 2/11/2025
Construction Document Phase & Review 2/12/2025 6/24/2025
Early Release Packages (ERP)
Site Civil 7/31/2024 12/10/2024
Long Lead MEP 7/31/2024 12/10/2024
Structural 7/31/2024 12/10/2024
Offsite Water Line 7/31/2024 12/10/2024
Guaranteed Maximum Price (GMP)
Bid/Award Construction Contract Phase 5/28/2025 9/3/2025
Construction
Offsite Water Line Construction 12/11/2024 1/14/2026
Construction Phase 3/14/2025 4/29/2027
Commissioning & Move In
Commissioning & Move In 1/14/2027 4/30/2027
1-Year Warranty Period 3/30/2027 4/30/2028
Texas Legislature Schedule
Texas 89th Legislature Session 1/14/2025 6/2/2025
9 | P a g e
Section V: Project Requirements
5.1 General Requirements
The A/E team is responsible for the design for this project. The POR is intended only to establish basic design criteria. This POR does not include all User requirements that may be identified in the project during the design process. Further, it is to be used in conjunction with the TFC “Owner’s Project
Requirements” (OPR), dated June 22, 2021, found here:
https://www.tfc.texas.gov/divisions/facilities/prog/construct/formsindex/2021%20TFC%20OPR%20Upd ate%20Document_062221%20signed.pdf and the Agreement for A/E Services to establish the responsibilities of the Project A/E team. The OPR provides general criteria, design processes, and general requirements applicable to TXDPS construction projects. The design team shall make professional evaluations of design problems and issues related to this project, analyze the advantages and disadvantages of each, evaluate, and recommend solutions to the design issues during the design process.
The A/E team is responsible to TXDPS for performing professional evaluations and any needed detailed studies using sound architectural and engineering principles required to establish the most functional, economical, and efficient use of materials, the site, and construction methods to provide the requested facilities within an approved budget during the design phases. The CMAR delivery method will be used.
The A/E team is charged with the responsibility of establishing the final locations, configuration, and layout taking into consideration site conditions and requirements established in this program.
5.2 Codes, Standards, & Regulations
The list of codes, standards, and regulations adopted by the TFC is available in the document “TFC OPR
Version 1” dated June 22, 2021, under Chapter 5, Architectural and Engineering Criteria.
5.3 Energy Conservation
The complete list of Sustainability Requirement adopted by the TFC is available in the document “TFC
OPR Version 1” dated June 22, 2021, under Section 2.3, Sustainability.
5.4 Risk
Barriers to the success of the project could be among the following:
1) Offsite Water Utility Connection and Easement
2) Critical permits that take extended periods of time to obtain
3) Equipment or materials with long lead times require early procurement to mitigate schedule impacts. Items may include:
a. Generators & Automatic Transfer Switches (ATS)
b. Electrical Switchgear
c. Packaged WWTP
4) A/E Design and Construction Budget Approval Process
10 | P a g e
5.5 Project Specifications Assumptions
1. Sitework & Paving
A. Temporary Controls – We have included monies associated with the on-site controls.
B. Demolition is included for allowing access of construction vehicles.
C. Clearing and Grubbing
D. Mass Excavation
E. Concrete Vehicle Paving
F. Concrete Parking Lots
G. Decomposed and compressed granite running trail
2. Central Utility Plant & Warehouse
A. Foundations
a. Drilled straight shaft piers assumed adequate at 18-inch diameter by 40-ft deep.
b. 8-inch Reinforced concrete slab w/integral Grade Beam.
B. Building Shell
a. Pre-Engineered Metal Building (Structure, Roof, & Siding).
C. Exterior Wall
a. 6-inch Metal Stud w/Dens Glass; one side, with Type – X Gypsum Wall Board; two sides and Batt Insulation in the stud-bay cavities.
b. Vapor Barrier(s), Flashings, Insulated Metal Panel, Storefront Entrance and Egress
Doors.
D. Roofing
a. Standing Seam Metal Roofing – Factory Finish, Preformed aluminum parapet caps.
E. Interior Finish
a. The interior finishes commensurate with the building’s intended end-use.
F. MEP Systems
a. Wet pipe sprinkler systems to satisfy NFPA – 13.
b. Plumbing to satisfy occupancy and code requirements.
c. Package Chillers to serve all campus buildings. Assume adequate cooling at 2,636
Tons.
d. Code minimum lighting for occupancy and life safety.
G. Low Voltage Systems
a. Fire Alarm, Voice Data, Electronic Safety, & Security.
3. Administration Building
A. Foundations
a. Drilled straight shaft piers assumed adequate at 18-inch diameter by 40-ft deep.
b. 6-inch Reinforced concrete slab-on-grade w/integral Grade Beam.
B. Building Shell
a. Structural Steel Framing System (Columns, Beams, Bar joist and decking)
b. 10#’s/SF @ Floors
c. 8#’s/SF @ Roof
d. 1.5#’s/SF for Misc.
C. Exterior Wall
a. 6-inch Metal Stud w/Dens Glass; one side, with Type – X Gypsum Wall Board; two-sides and Batt Insulation in the stud-bay cavities.
b. Vapor Barrier, Flashings, Masonry Veneer – 80%, Cut-Stone Veneer – 10%, Punched
Window openings – 10% (for maximum natural light), Egress Doors.
D. Roofing
11 | P a g e
a. Modified Bitumen roofing system with integral flashing to parapets, Preformed aluminum parapet caps.
E. Interior Finish
a. Interior finishes commensurate with the “POR” and the building’s intended end-use.
(See estimating details).
F. MEP Systems
a. Taps for utilities, chilled, fire, and domestic water, sanitary sewer, and storm drainage.
b. Wet pipe sprinkler systems to satisfy NFPA – 13.
c. Plumbing to satisfy occupancy, code, and program requirements.
d. Plumbing to satisfy occupancy, code, and POR.
e. HVAC Distribution VAV’s and FCU’s to sheet metal duct with supply-side economizers and thermostatic controls.
f. Electrical criteria sized at 12 watts/SF.
g. Lighting allowances at $9.50/SF.
G. Low Voltage Systems
a. Fire Alarm, Voice Data, Electronic Safety, & Security.
4. Indoor Physical Fitness
A. Foundations
a. Drilled straight shaft piers assumed adequate at 18-inch diameter by 40-ft deep.
b. 8-inch Reinforced concrete slab w/integral Grade Beam.
B. Building Shell
a. Pre-Engineered Metal Building (Structure, Roof, Siding).
b. Mezzanine (2nd floor) typical structural steel framing.
c. Exterior Roll-Up Doors.
C. Exterior Wall
a. 6-inch Metal Stud w/Dens Glass; one side, with Type – X Gypsum Wall Board; two-sides and Batt Insulation in the stud-bay cavities.
b. Vapor Barrier, Flashings, Insulated Metal Panel – 75%, Cut-Stone Veneer
Wainscotting – 15%, Punched Window openings – 10% (for maximum natural light), Storefront Glazing at building entrance, Storefront Entrance Doors, Egress Doors at grade.
D. Roofing
a. Modified Bitumen roofing system with integral flashing to parapets, Preformed aluminum parapet caps.
E. Interior Finish
a. The interior finishes commensurate with a typical institutional Gymnasium.
i. Includes Rubberized Floor, VCT, LVT, Carpet Tile, Polished Concrete Floor, etc.
F. MEP Systems
a. Wet pipe sprinkler systems to satisfy NFPA – 13.
b. Plumbing to satisfy occupancy and code requirements.
c. Package Chillers to serve all campus buildings. Assume adequate cooling at 2,636
Tons.
d. Electrical Service Design sized at 13 watts/SF.
e. Lighting allowances at $7.00/SF.
G. Low Voltage Systems
a. Fire Alarm, Voice Data, Electronic Safety and Security.
12 | P a g e
5. Cafeteria
A. Foundations
a. Drilled straight shaft piers assumed adequate at 18-inch diameter by 40-ft deep.
b. 6-inch Reinforced concrete slab w/integral Grade Beam
B. Building Shell
a. Structural Steel Framing System (Columns, Beams, Bar joist and decking)
b. 10#’s/SF @ Floors
c. 8#’s/SF @ Roof
d. 1.5#’s/SF for Misc.
C. Exterior Wall
a. 6-inch Metal Stud w/Dens Glass; one side, with Type – X Gypsum Wall Board; two-sides and Batt Insulation in the stud-bay cavities.
b. Vapor Barrier, Flashings, Insulated Metal Panel – 75%, Cut-Stone Veneer Wainscotting –
15%, Punched Window openings – 10% (for maximum natural light), Storefront Glazing at building entrance, Storefront Entrance Doors, Egress Doors at grade.
D. Roofing
a. Modified Bitumen roofing system with integral flashing to parapets
b. Preformed aluminum parapet caps
E. Interior Finish
a. The interior finishes commensurate with a typical institutional cafeteria and dining area.
i. Includes VCT, LVT, Carpet Tile, Polished Concrete Floor, etc.
F. MEP Systems
a. Wet pipe sprinkler systems to satisfy NFPA – 13.
b. Plumbing to satisfy occupancy and code requirements.
c. Package Chillers to serve all campus buildings. Assume adequate cooling at 2,636 Tons.
d. Electrical Service Design sized at 13 watts/SF.
e. Lighting allowances at $7.00/SF.
G. Low Voltage Systems
a. Fire Alarm, Voice Data, Electronic Safety, & Security
6. Classroom Building
A. Foundations
a. Drilled straight shaft piers assumed adequate at 18-inch diameter by 40-ft deep.
b. 6-inch Reinforced concrete slab-on-grade w/integral Grade Beam.
B. Building Shell
a. Structural Steel Framing System (Columns, Beams, Bar Joist, & Decking)
b. 10#’s/SF @ Floors
c. 8#’s/SF @ Roof
d. 1.5#’s/SF for Misc.
C. Exterior Wall
a. 6-inch Metal Stud w/Dens Glass; one side, with Type – X Gypsum Wall Board; two-sides and Batt Insulation in the stud-bay cavities.
b. Vapor Barrier, Flashings, Masonry Veneer - 80%, Cut-Stone Veneer – 10%, Punched
Window openings – 10% (for maximum natural light), Egress Doors
D. Roofing
a. Modified Bitumen roofing system with integral flashing to parapets.
b. Preformed aluminum parapet caps.
E. Interior Finish
a. The interior finishes commensurate with the typical institutional classroom building.
13 | P a g e
i. Includes VCT, LVT, Carpet Tile, Polished Concrete Floor, etc.
b. Walls between classrooms will have added soundproofing.
F. MEP Systems
a. Taps for Utilities, Chilled, Fire, and Domestic Water, Sanitary Sewer, and storm drainage.
b. Wet pipe sprinkler systems to satisfy NFPA – 13.
c. Plumbing to satisfy occupancy, code, and program requirements.
d. HVAC Distribution VAV’s and FCU’s to sheet metal duct with supply-side economizers and thermostatic controls.
e. Electrical criteria sized at 13 watts/SF.
f. Lighting allowances at $9.50/SF.
G. Low Voltage Systems
a. Fire Alarm, Voice Data, Electronic Safety, & Security.
7. Recruit Dormitories
A. Foundations
a. Drilled straight shaft piers assumed adequate at 18-inch diameter by 40-ft deep.
b. 6-inch Reinforced concrete slab-on-grade w/integral Grade Beam.
B. Building Shell
a. Structural Steel Framing System (Columns, Beams, Bar joist and decking).
b. 10#’s/SF @ Floors.
c. 8#’s/SF @ Roof.
d. 1.5#’s/SF for Misc.
e. 4-inch concrete topping at metal deck floor pan.
f. 3-inch concrete topping at metal deck roof pan
C. Exterior Wall
a. 6-inch Metal Stud w/Dens Glass; one side, with Type – X Gypsum Wall Board; two-sides and Batt Insulation in the stud-bay cavities.
b. Vapor Barrier, Flashings, 3- Coat Stucco - 80%, Cut-Stone Veneer – 10%, Punched
Window openings – 10% (for maximum natural light), Egress Doors.
D. Roofing
a. Modified Bitumen roofing system with integral flashing to parapets.
b. Preformed aluminum parapet caps.
E. Interior Finish
a. The interior finishes commensurate with a typical institutional dormitory.
i. Includes VCT, LVT, Carpet Tile, Polished Concrete Floor, etc.
F. MEP Systems
a. Taps for utilities, Chilled Water, Fire Water, Domestic Water, Sanitary Sewer, and storm drainage.
b. Wet pipe sprinkler systems to satisfy NFPA – 13.
c. Plumbing to satisfy occupancy, code, and POR.
d. HVAC Distribution VAV’s and FCU’s to sheet metal duct with supply-side economizers and thermostatic controls.
e. Electrical criteria sized at 15 watts/SF.
f. Lighting allowances at $9.50/SF.
G. Low Voltage Systems
a. Fire Alarm, Voice Data, Electronic Safety, & Security.
14 | P a g e
5.6 Program Buildings & Site Elements
Phase I (Currently Funded)
Refer to Site Test Fit in Section 6.6 for building and site element’s locations.
1. Administration Building
A. This is a 3-story building that houses 22 offices, a 20-person squad room, 2 conference rooms, and a 1,000-seat auditorium. It is the main building of this part of campus. It should be connected to or in very close proximity to the Classroom Building. The scope was increased to build out 3rd floor structural capacity and to build out the 3rd floor
Shell Space.
2. Classroom Building
A. This is a 1-story or 2-story building that houses 9 classrooms: 1: 200-seat classroom, 2:
150-seat classrooms, 3: 60-seat classrooms, and 3: 30-seat classrooms. It should be connected to or in very close proximity to the Administrative Building.
3. Dorms for Recruits
A. This is a series of 5: 2-story buildings that houses 500 recruits. Approximately 400 will be for men’s dorms and 100 for women’s dorms. It is assumed that each floor plate will house 50 people. The bedroom will be barrack-style, open floor plan with centralized toilets and showers. Each floor plate will include one counselor room, one isolation room, a laundry room, and a day room. Dorm configuration could be altered to include
180 recruits in one building.
4. Cafeteria
A. The cafeteria is to have a kitchen, dining area, and staff support area. The anticipated volume is 250 people eating in three shifts for a total of 750 people. There is a 50-person VIP conference / dining area. The kitchen is also sized to handle catering to the existing TXDPS Firearms Training Building.
5. Indoor Physical Fitness
A. This 2-story building has two main parts: (1) Inside Gym, Fitness and Wellness Unit and
(2) Arrest and Control Tactics – Indoor. This structure will be a one-story indoor conditioned space.
6. Outdoor Physical Fitness (Track & Field)
A. This is for outdoor exercises and includes a full-size football field with 5-yard striping, without goal posts, and using synthetic turf. This includes a 5-lane, ¼-mile, running track.
7. Central Utility Plant
A. This 1-story building is sized to accommodate support of a Phase I build out utility loop for the campus, including chilled water, hot water, electrical distribution, and one central backup generator. Package chillers are to serve all buildings. Assumption is adequate cooling at 2,636 tons. The scope was increased to add a Docking Station for a portable generator to serve as a backup.
8. Maintenance / Warehouse Building
A. Combined with the Central Utility Plant.
9. Water Tower
A. The Water Tower (2M gallon) is for Fire Suppression.
15 | P a g e
10. Water & Pump Station
A. Located next to the water tower, the main water service will be routed to this location.
11. Outdoor Physical Fitness Pavilion
A. This structure will be an open-air pavilion. The activities here are for the Fitness and
Wellness Unit (FWU) and Arrest Control Tactics (ACT).
12. Perimeter Fence for New Site
A. The existing fence will be extended to the new site. The existing fence is an 8-ft high chain link.
13. 1.5-Mile Fitness Trail
A. Cardio course, containing 30% grade at various locations, utilizing the existing topography.
14. 800-Stall Parking Lot
A. Dedicated surface parking lot of 500 stalls for the recruit dorms, as well as a dedicated surface parking lot of 300 stalls to serve the Administration Building, Classroom Building, and Cafeteria.
15. Detention Basin & Water Quality Basin
A. These basins are to be in the remote north part of the campus.
16. Bullet Traps (at Existing Site)
A. To avoid delays in the safe use of the ranges for firearms training, it is proposed that each of the following ranges be outfitted with stand-alone bullet traps constructed in front of each backstop: Tactical, 60 Point, Multi-Purpose, and Rifle. This will provide a double layer of protection behind each range and allow for the capture of lead and brass for easy collection with no accumulation within the berms. In addition, these bullet traps will decrease the ricochet potential and round escape beyond the range area.
17. Mobile Targeting System (at Existing Site)
A. In conjunction with the proposed bullet traps, a moving targeting system can be designed to accommodate target movement left, right, and turning, and can be specific to each range. Mobile targeting systems can be ground-mounted, or overhead-supported. This will allow for more effective weapons training, especially from a tactical training perspective.
18. Wastewater Treatment Plant (WWTP)
A. This structure is to be in the north part of the campus, to be remote from the active part of campus. The WWTP to be protected by a PEMB (Pre-Engineered Metal Building).
Phase II (Not in Project & Not Yet Funded)
19. In-Service Personnel Dorms
A. This is a series of 4: 2-story buildings that house 200 people. It is assumed that each floor plate will house 25 people. The bedroom style will be a combination of 100 single rooms and 50 double rooms with centralized toilets and showers. Each floor plate will also include a laundry and a day room. The building will have approximately 80% 3-Coat
Stucco, 10% Cut-Stone Veneer, and 10% Punched Window Openings. The roof will be
Modified Bitumen. The In-Service Dorms have room to expand 100% on site.
16 | P a g e
20. Parking Garage
A. This 2-story parking garage will house 400 stalls, 200 of which are dedicated to the In-
Service Dorms. The assumption is precast concrete.
21. Maintenance / Warehouse Building
A. This building from Phase I is combined with the CUP.
22. Central Utility Plant
A. This building from Phase I can expand 100% as needed for additional campus growth.
Phase III (Not in Project & Not Yet Funded)
23. Indoor Aquatics
A. This Olympic-sized pool will have supporting elements and climate control for 24/7/365 operation.
17 | P a g e
Section VI: Site Planning
6.1 Site Location Maps
Figure 1. Existing Site & New Site Location Map
18 | P a g e
Figure 2. Map of New Site
19 | P a g e
6.2 Existing Site Conditions
Site Suitability
The new 135.58-acre site has room for all program elements and future expansion. There is a
Freshwater Wetland (creek) through the southern one third of the new site. There is a 50-ft easement for a crude oil pipeline running diagonally east-west through the new site. The 100- and 500-year floodplains make the far northern portion of the site non-usable for any grade manipulation. The new site is assumed to be able to be balanced because of grades that are relatively gentle.
6.3 Parking Requirements
Phase I Parking is 800 stalls in surface lots. This includes 500 stalls for Recruit Dorms and 300 stalls for general parking for the staff and visitors to the campus. The CUP will have dedicated surface parking of
10 for staff. Per 2012 Texas Accessibility Standards, 17 stalls must be accessible parking spaces.
Phase II Parking is 400 stalls in a two-level parking garage. This will serve the added 200 stalls for the
Phase II In-Service Dorms and increased capacity for general parking for the staff and visitors to the campus. The total number of stalls for total build out is 1,210. Per 2012 Texas Accessibility Standards, 23 stalls must be accessible parking spaces.
Fire Access to all buildings can be via the perimeter road and designated fire lanes. The cafeteria will have a loading dock for loading and unloading supplies. The Administration Building will have a drop-off lane in front of the building.
6.4 Site Investigations
Existing Conditions
The proposed development encompasses a 135.58-acre site recently acquired by the TXDPS located on
CR-240 in Florence, TX. The site includes existing structures, existing drives, streams, and man-made stock ponds as well as a 50-ft pipeline easement, 0.04-Acre drainage easement and 0.038-acre right-of-way dedication for CR-240 expansion. The existing main point of egress and ingress is CR-240 on the southeast boundary. South Salado Creek is adjacent to the northeast boundary.
Investigations Previously Performed
• TFC TXDPS Site Assessment, Environmental Technical Memorandum, dated March 2024, prepared for TFC and Cobb, Fendley, & Associates, Inc., prepared by Stantec Consulting Services Inc.
– To be sent under separate cover.
• Cobb Findley Topo Survey dated April 9, 2024
– To be sent under separate cover.
• Tree Survey dated April 30, 2024.
– To be sent under separate cover.
Cultural Resources Constraints / Archeological Survey & THC Notice
There is no structure on site that is 50 years of age or older that is of any historic significance. The adjacent property has a cemetery that has a 75-ft buffer offset per THC.
Environmental Site Assessment
Refer to Stantec document dated March 8, 2024, “TFC TXDPS Site Assessment, Environmental Technical
Memorandum.”
20 | P a g e
Floodplain / Wetlands Determination
A portion of this site is located within the FEMA 500-year floodplain (Zone AE) and FEMA 100-year floodplain (Zone A). Firm Panel No. 48491C0100E, Williamson County, TX, and incorporated areas
(Effective Date September 26, 2008).
Traffic Impact Analysis
This site will have approximately 425 trips on Friday afternoon and 425 trips on Sunday afternoons as users of the facility leave and arrive. Typical daily trips will consist of office and maintenance workers during the day-to-day operation of the facility. Williamson County does not have TIA requirements and due to the relatively low number of trips, a TIA will not be expected.
6.5 Availability & Location of Utilities
Figure 3. Existing Site Utilities Map
21 | P a g e
Domestic Water
Based on data provided of the proposed expansion, we anticipate a total domestic water peak daily demand of approximately 660 GPM to service these facilities. Water service is possible for this expansion by proposing a 16-inch PVC water line. The City of Georgetown will operate the line once constructed. The anticipated alignment of this waterline is depicted in the image below.
Figure No. 4. Anticipated Water Line
The 16-inch waterline will connect to an existing Georgetown water main at Ronald Regan Blvd and CR
245. The total length of the waterline is estimated to be 32,300 LF. The waterline shall not be located inside of the public right-of-way (except at roadway crossings) and shall be in the easements. The
Opinion of Probable Cost of this offsite 16-inch waterline is provided in Appendix C.
22 | P a g e
Fire Water / Water Tank / Tower
The proposed 16-inch waterline depicted above will also service this property’s fire demand. Due to the single 16-inch line service to the property (not located on a ‘loop’), a redundant water supply will be proposed. This will be provided by a +/-2-million-gallon ground storage tank or tower. This storage tank and the 16-inch waterline will connect to a 12-inch waterline routed through the site serving the hydrants and building sprinkler systems. All potable water tanks are required to be 500 ft from any packaged WWTP. TCEQ requires the water tank area to be fenced with an access road inside the fence.
An acre is assumed for a water tank site. Co-location of the water tank, pump station and fencing together is assumed.
Chilled Water
Assuming all buildings will be served with chilled water. For future consideration of phases assume installation of chilled water loop, for ease of expandability.
Sanitary Sewer
The existing facility currently manages wastewater using septic systems. It is assumed there are three
5,000 GPD systems installed which collect approximately 60 LUEs that come from the existing facility. To support expansion of the facility, additional wastewater capacity will be required.
Based on data provided of the proposed expansion, a total wastewater demand of approximately 391
LUE to service these facilities is needed at full build out. To meet this demand, a packaged WWTP is necessary. The packaged WWTP could be configured for surface water discharge or a Texas Land
Application Permit (TLAP).
To meet growing wastewater demands triggered by the facility expansion, perusing a Texas Pollutant
Discharge Elimination System (TPDES) permit is recommended through the TCEQ and constructing a
WWTP on site.
A Preliminary Application to TCEQ was submitted in April of 2024 describing the proposed discharge location. TCEQ reviewed the preliminary application and granted preliminary acceptance of the discharge point. A full TPDES permit application is required to be submitted to obtain either a discharge permit or TLAP permit from TCEQ before the WWTP can be approved for construction. The WWTP is required to be 500 ft from any potable water tank and 250 ft from any potable water well.
Storm Sewer
Existing Drainage
According to the available GIS topography, stormwater runoff passing through the site will flow to two points of analysis that drain to South Salado Creek. A natural ridge exists in the center of the site. 92.55 acres flows north through a man-made stock pond and into Point of Analysis A, a channel located on the southeast corner of the property. 43.03 acres flows north to Point of Analysis B, a natural low point on the north boundary of the property adjacent to South Salado Creek. According to the available GIS topography, approximately 16.25 acres of offsite flow enters the site from the southwest boundary of the property. All existing drainage flows to South Salado Creek.
Proposed Drainage
Under the proposed conditions, the necessary drainage, detention, and water quality infrastructure will be provided to service the entire 135.58-acre site. Drainage design includes one water quality and one detention pond. 16.25 acres of off-site drainage from the south will be conveyed across the proposed drainage system downstream of the water quality and detention ponds.
23 | P a g e
Detention & Water Quality
This site is located over the Edwards Aquifer Contributing Zone, which triggers the need for Water
Quality Treatment. A plus/minus 30,000-SF Water quality pond and a plus/minus 75,000-SF detention pond will be proposed with this development to treat and detain the stormwater runoff from the TXDPS
Training Facility. The water quality pond design will be partial biofiltration basins designed to treat the proposed impervious cover as well as future development. The detention and water quality ponds will be located at the north property boundary.
Proposed ponds will be required to be designed to release post-development rainfall runoff at a rate that is less than or equal to the pre-developed flows in 2-, 10-, 25-, and 100-year storm events per
Williamson County.
Natural Gas
Natural Gas lines are not located in the immediate area. Atmos has a line located 12 miles away and
Texas Gas has a line 8 miles away. Therefore, gas service will be provided by on-site tank(s) which will be refilled on a regular basis. Gas lines from these tanks will be provided to necessary buildings where appropriate. We assume the buildings that require gas are the following:
• Barrack (Heating Water for Showers)
• Cafeteria (Cooking & Cleaning)
• Administration Building
Electricity
TXDPS site is in Pedernales Electric Co-op (PEC) service area and will be serviced by the Liberty Hill office.
Once the site plan approval has been prepared, PEC will begin their design of the required improvements.
Telecommunications / Data
Assumption is this service can be brought to the site.
Distributed Antennae System
Assume this service might be required to boost cellular signal on site and in larger buildings and parking garages to handle the number of users. This is not priced into the model.
Water Treatment & Pump Station
Assuming half an acre in size and assuming TXDPS is not treating raw groundwater. If TXDPS is planning on using well water, assume to add 0.25- to 0.5-acre to allow space for the treatment equipment. In addition to the treatment units TXDPS will need to plan to dispose of the treatment by products (iron & water). Typically, this is land applied and allowed to absorb/evaporate. The maximum allowable agronomic rate for land application of water treatment plant residuals is 40 dry tons/acre/year. Actual application rates will need to be determined by agronomic soil analysis and calculations of water treatment residuals flow rate, annual volume and nutrient and pollutant concentrations.
Central Utility Plan / Maintenance / Warehouse Building
Assumption is 15K SF is needed for Phase I and can double in size for Phase II.
Wastewater Treatment Plant
Setback requirement is 150 ft from the WWTP and the next closest structure. The wells cannot be within
500 ft of the WWTP or land application irrigation field. Potable water storage tanks and other assets have similar setbacks to WWTPs and disposal areas.
24 | P a g e
6.6 Site Test Fit
Figure 5. Site Test Fit
25 | P a g e
Section VII: Space Program
1 – Administration Building
Item Description Unit Area # Spaces Total Area
Offices 120 22 2,664
Reception 2,244 1 2,244
Squad Room 56 20 1,120
Administration Staff 56 7 392
Conference Room 25 40 1,000
Conference Room 25 20 500
Restrooms** (4 Toilets Each) 760 1 760
Break Room 1,500 1 1,500
Storage 500 1 500
Print / Copy 200 1 200
Auditorium
1,000-Seat Graduation 3x Year 24 1000 24,000
15-Table Stage 1,800 2 3,600
A/V Equipment & Storage 3,000 2 6,000
Uniform Storage 6,000 1 6,000
Recruit Gun Vault (960 People)**** 960 1 960
Restrooms * (8 Toilets Each) 520 2 1,040
Sub-Total 52,480
Gross 35% *** 28,258
Total Gross Square Feet 80,738
Notes
* 8 men’s and 8 women’s toilets, during SD the DPS team will decide on one or many locations
** 4 men’s and 4 women’s toilets, during SD the DPS team will decide on one or many locations
*** Includes horizontal and vertical circulation and includes mechanical and electrical rooms
**** During SD the DPS team will decide on one or many locations
26 | P a g e
2 – Classroom Building
Item Description Unit Area # Spaces Total Area
Classroom (200) *
(30-SF per Student) 6,000 1 6,000
Classroom (150) *
(30-SF per Student) 4,500 2 9,000
Classroom (60) *
(28-SF per Student) 1,680 3 5,040
Classroom (30) *
(28-SF per Student) 840 3 2,520
Storage (for all 9 Classrooms) 1,000 1 1,000
Restrooms ***
(9 Toilets Each) 585 2 1,170
Vending / Break 500 2 1,000
Janitor / Storage 90 2 180
IT Main Distribution Room (MDR) 250 1 250
IT Intermediate Distribution Room (IDR) 100 2 200
General Building Storage 200 1 200
Building Maintenance Storage 200 1 200
Janitorial Equipment Storage 200 1 200
Sub-Total 26,960
Gross 35% *** 14,517
Total Gross Square Feet **** 41,477
Notes
* Assuming 9 of 17 Training Sergeants are Teaching
** Includes Mechanical and Electrical Rooms
** Includes Horizontal and Vertical Circulation
*** Assumes 775 Occupants in Building
**** DPS team will confirm with AE if the building is one or two story.
27 | P a g e
3 – Recruit Dormitory (500-Bed)
Item Description Unit Area # Spaces Total Area
Male Recruit Dormitory
Male Bay (50 Beds / Floor)
(400 Beds Total | 8 Floors | 4 Buildings) 93 400 37,000
Counselor Suite (1 Single Room) 262 8 2,096
Isolation Room 262 8 2,096
Community Bath & Toilet Male * 837 8 6,696
Laundry 181 8 1,448
Linen Storage 100 8 800
Janitor 100 8 800
Day Room 900 8 7,200
Female Recruit Dormitory (80 / 20) M/W
Female Bay (50 Beds / Floor)
(100 Beds Total | 2 Floors | 1 Building) 93 100 9,300
Counselor Suite 262 2 524
Community Bath & Toilet Female 837 2 1,674
Isolation Room 262 2 524
Laundry 181 2 362
Linen Storage 100 2 200
Janitor 100 2 200
Day Room 900 2 1,800
Sub-Total 14,584
Gross 32% *** 6,863
Total Gross Square Feet 21,447
Total Recruit Dormitory 106,941
Notes
* Community Bath and Toilet Assumes 1 Toilet/Shower per 6 People, Assume 140-SF per Person
*** Includes Mechanical and Electrical Rooms
*** Includes Horizontal and Vertical Circulation
28 | P a g e
4 – Cafeteria
Item Description Unit Area # Spaces Total Area
Staff Areas
Reception / Lobby 500 1 500
Staff Breakroom 250 1 250
Restroom 64 2 128
Work / Copy / Supply 100 1 100
Food Service Worker (1) 144 1 144
Manager (1) 144 1 144
Kitchen – Sized to Serve 600 (150 x 4)
Storage Bulk Dry Goods 600 1 600
Storage Bulk Refrigeration 650 1 650
Storage Bulk Freezer 650 1 650
Storage Bulk Cleaners, Soap, etc. 300 1 300
Kitchen Produce Preparation 450 1 450
Kitchen Bakery Preparation 350 1 350
Kitchen Cooking & Baking Equipment 700 1 700
Hot / Cold Staging Area 200 1 200
Ready Area 800 1 800
Dishwashing 250 1 250
Equipment Storage Room 850 1 850
Equipment Maintenance 500 1 500
Locker Room (10) 100 1 100
Warming Carts Staging Area ** 400 1 400
Warming Carts Wash Area ** 200 1 200
Warming Carts Storage Area ** 200 1 200
Support Spaces
Custodial Storage / Equipment 300 1 300
Receiving / Loading Dock 1,000 1 1,000
Dining Hall
Dining Area – Sized for 250 People
(250 People in 3 Shifts = 750 Total) 5,000 1 5,000
VIP Conference / Dining (50) 1,500 1 1,500
Storage 1,200 1 1,200
Restrooms **** (9 Toilets Each) 585 2 1,170
Sub-Total 18,636
Gross 30% *** 7,987
Total Gross Square Feet 26,623
Notes
** Warming Carts to Serve Existing Training Academy Building
*** Includes Mechanical and Electrical Rooms
*** Includes Horizontal and Vertical Circulation
**** Assuming 750-Occupant Load
29 | P a g e
5 – Indoor Physical Fitness
Item Description Unit Area # Spaces Total Area
Inside Gym – Fitness & Wellness Unit (Priced Separately)
Manager 100 1 100
Sergeant 100 1 100
Education Specialist 100 1 100
Training Specialist 100 1 100
Statistician 100 1 100
Staff Break Room 400 1 400
Conference Room – 25 375 1 375
Fitness & Wellness Trooper Squad Room 56 10 560
Medical Office 120 2 240
Physical Therapy Room 1,000 1 1,000
Examination Room 120 2 240
Weight Room 9,400 1 9,400
Indoor Training 4,700 1 4,700
Storage 400 1 400
Staff Locker / Showers / Changing Room / Restrooms (8M, 8W) * 3,750 1 3,750
Sub-Total 21,565
Gross 35% 11,612
Total Gross Square Feet 33,177
5 – Indoor Physical Fitness
Item Description Unit Area # Spaces Total Area
Arrest & Control Tactics (Priced Separately)
Office – Lieutenant 100 1 100
Office – Sergeant 100 2 200
Trooper Squad Room 56 10 560
Breakroom 750 1 750
Conference Room – 20 400 1 400
Training Room – 1 16,275 1 16,275
Training Room – 2 16,275 1 16,275
Training Room – 3 2,475 1 2,475
Training Room – 4 2,475 1 2,475
Training Room – 5 2,475 1 2,475
Training Room – 6 1,500 1 1,500
Staff Locker / Showers / Changing Room / Restrooms (8M, 8W) * 3,750 1 3,750
Storage 400 1 400
Sub-Total 47,635
Gross 35% 25,650
Total Gross Square Feet 106,462
* Staff and Non-Trainee Facilities will be provided in separate areas
30 | P a g e
7 – Central Utility Plant
Item Description Unit Area # Spaces Total Area
Central Utility Plant
Maintenance Work Area 830 1 830
HVAC Boiler Work 550 0 0
HVAC Boiler Storage / Equipment 500 0 0
Chilled Water 2,400 1 2,400
Plumbing Storage / Equipment 500 1 500
Paint Storage 100 0 0
Transformer Room 500 1 500
Main Electrical 600 1 600
Electrical Storage / Equipment 500 1 500
Main Computer / Data Center 250 1 250
Technician (2) 80 2 160
Equipment / Storage / Receive 160 1 160
Mechanical 140 1 140
Electrical 125 4 500
Main Telephone 100 1 100
Sprinkler 80 1 80
Sprinkler Pump Room 480 1 480
Sub-Total 7,200
Gross 20% 1,800
Total Gross Square Feet 9,000
Central Plant and Building Maintenance are Combined into One Building.
31 | P a g e
8 – Building Maintenance
Item Description Unit Area # Spaces Total Area
Building Maintenance
Administrative Assistant 56 2 112
Storage 90 1 90
Physical Plant Manager 120 1 120
Closet 42 1 42
Work / Copy 110 1 110
Locksmith Work 121 1 121
Blueprint / File Room 160 1 160
Supply 36 1 36
Vending / Breakroom (20) 560 1 560
Unisex Toilet 64 2 128
Building Engineer 140 1 140
General Storage 180 1 180
Building Material Storage 200 1 200
Housekeeping
Supervisor 120 1 120
Staff Work Area 432 1 432
Bulk Janitor Storage 860 1 860
Dry Cleaning Holding Area 240 1 240
Unisex Toilet 64 1 64
Work / Copy / File 100 1 100
General Storage 650
Sub-Total 4,465
Gross 20% 1,116
Total Gross Square Feet 5,581
Central Plant and Building Maintenance are Combined into One Building.
32 | P a g e
New Site Test Fit List
Phase I Site Element Site Footprint (SF)
1 Administration Building (2 Story) 80,738
2 Classroom Building (1 Story) 41,477
3 Recruit Dormitories (2 Story – Can Expand 100%) 106,941
4 Cafeteria (1 Story) 26,623
5 Indoor Physical Fitness (2 Story) 106,462
6 Outdoor Physical Fitness (Track & Field) 175,740
7 Central Utility Plant (1 Story) 9,000
8 Maintenance / Warehouse Building (Combined with #7) 5,581
9 Water Tower 15,625
10 Water Treatment & Pump Station 21,780
11 Outdoor Physical Fitness Pavilion 2 (1 Story) 20,000
12 Perimeter Fence
13 1.5-Mile Fitness Trail 79,200
14 800-Stall Parking Lot 280,000
15 Detention Basins 112,831
16 Bullet Traps (Existing Site)
17 Mobile Targeting System (Existing Site)
18 Waste Water Treatment Plant 108,500
Programmed Space Sub-Total 398,602
Site Elements Sub-Total 791,896
Total 1,190,498
Phase II Not Included in Budget *
19 In-Service Personnel Dormitory (2 Story – Can Expand 100%) 81,982
20 400-Stall Parking Garage (2 Story) 140,000
21 Maintenance / Warehouse Building (Combined with #22)
22 Central Utility Plant (Can Expand 100%)
Phase III Not Included in Budget *
23 Indoor Aquatics (50M Pool) 68,377
33 | P a g e
Section VIII: POR Certification & Sign Off
The representatives of the TXDPS agree that the POR contained here adequately identifies, describes, and documents the needs of the project. Approval of the POR indicates an understanding of the purpose and content described in this document.
8.1 User Group
James King Deputy Administrator
Printed Name User Coordinator, Title Signature Date
Kevin Sandberg TFC Senior Project Manager
Printed Name Title Signature Date
Jason Griffin Major
Printed Name Title Signature Date
Derek Prestridge Assistant Chief
Printed Name Title Signature Date
Shannon Hamby Captain
Printed Name Title Signature Date
34 | P a g e
Section IX: Appendices
Appendix A: Master Schedule
T X
D P
S T ra in in g A ca d e m y | B
.0
P ro g ra m o f R e q u ire m e n ts | Ju ly 2
, 2
| P a g e
SITEWORK +
PAVING
UTILITIES
CENTRAL UTILITY
PLANT/WHSE
ADMIN
BUILDING
INDOOR
PHYSICAL
FITNESS
CAFETERIA
CLASSROOM
BUILDING
RECRUIT DORMS
X 5
OUTDOOR
PHYSICAL
FITNESS AREA
PROJECT TOTAL
## UNIFORMAT
A 00 Temporary Controls 727,947$ 531,168$ 205,744$ 482,545$ 625,281$ 221,386$ 270,729$ 418,317$ 89,270$ 3,572,387$
A 01 Selective Demo. & Existing Conditions 186,484$ -$ -$ -$ -$ -$ -$ -$ -$ 186,484$
A 10 Concrete Foundations -$ -$ 446,041$ 1,758,958$ 1,839,689$ 1,246,398$ 739,916$ 2,311,838$ 337,436$ 8,680,276$
B 10 Superstructure -$ -$ 536,634$ 4,543,834$ 2,755,923$ 1,011,572$ 1,574,218$ 5,464,592$ 444,000$ 16,330,773$
B 11 Misc. Metals -$ -$ -$ 74,880$ 62,400$ -$ 99,840$ 74,580$ -$ 311,700$
B 20 Exterior Walls -$ -$ 136,572$ 1,429,725$ 521,335$ 572,247$ 531,290$ 488,457$ -$ 3,679,626$
B 30 Roofing and Moisture Protection -$ -$ 417,601$ 1,948,763$ 1,954,484$ 798,197$ 664,885$ 1,139,993$ 375,000$ 7,298,921$
C 10 Interior Construction -$ -$ 104,132$ 4,780,118$ 1,260,891$ 452,617$ 1,587,280$ 3,003,057$ -$ 11,188,095$
C 20 Interior Finishes & Specialties -$ -$ 149,319$ 2,300,918$ 1,938,670$ 508,034$ 903,923$ 1,521,060$ -$ 7,321,923$
D 10 Elevators -$ -$ -$ 134,100$ 102,500$ -$ 134,100$ -$ -$ 370,700$
D 20 Plumbing -$ -$ 290,203$ 3,629,895$ 3,973,528$ 1,696,145$ 2,139,824$ 3,850,139$ -$ 15,579,735$
D 30 HVAC -$ -$ 11,773,963$ 7,097,130$ 6,395,948$ 380,975$ 2,430,641$ 5,285,790$ -$ 33,364,447$
D 40 Fire Protection -$ -$ 35,724$ 500,702$ 299,957$ 65,227$ 171,481$ 353,707$ -$ 1,426,798$
D 50 Electrical and Lighting -$ -$ 611,467$ 5,916,714$ 3,611,108$ 1,001,198$ 2,243,711$ 4,250,210$ 168,675$ 17,803,083$
D 51 Communications & Security -$ -$ 69,260$ 1,029,410$ 505,695$ 126,459$ 352,555$ 507,970$ -$ 2,591,349$
D 52 Electronic Safety and Security -$ -$ 51,034$ 787,196$ 372,617$ 93,181$ 269,601$ 347,558$ 43,935$ 1,965,122$
D 60 Low Voltage -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
E 10 Equipment (ALLOWANCE) -$ -$ -$ 778,321$…
This is the start of the file's text. The full file is on GovTribe.