Summary of Exhibit 3 - Specifications for ESB - US 395 Tree Trimming

This specification document is issued by the Oregon Department of Transportation (ODOT) for a tree trimming and vegetation removal project along US 395 between Mileposts 1.73 (Portal Lane) and 2.47 (Nelson Road). The scope of work requires contractors to furnish and maintain temporary work zone traffic control, fall trees, trim tree canopy, remove brush and vegetation, chip material, and treat hardwood tree trunks with herbicide. Specific clearing requirements include removing all dead or visibly dying trees, trees with diameter at breast height (dbh) equal to or less than six inches, and all limbs and brush within 30 feet horizontal distance from the edge of pavement and 35 feet vertical clearance. Tree stumps must be cut flush or within two inches of the ground surface in the Clear Zone and no higher than four inches above ground surface outside the Clear Zone. All debris, felled trees, foliage, downed trees, brush, and vegetative materials with diameter greater than one inch must be removed from the work area and either chipped on-site or hauled to approved disposal sites. The project is subject to the 2024 Oregon Standard Specifications for Construction, with modifications detailed in the specification document, and ODOT's Temporary Traffic Control Handbook for Operations of Three Days or Less. Migratory bird nesting habitat protection is required, with no vegetation clearing permitted from March 1 through September 1 without written approval, and contractors must provide 10 calendar days' notice before starting activities that could harm nesting birds.

Payment for this project will be made as a lump sum under the item "Tree Removal, Brushing & Cleanup," with the contractor bearing all costs for equipment, labor, materials, supervision, and transportation necessary to complete the work. All cleared material and debris become the contractor's property and may be disposed of through chipping or hauling, with chips spread uniformly in loose layers not exceeding three inches. Herbicide treatment of hardwood tree stumps must use Polaris AC or an approved equivalent, applied as an undiluted concentrate to the outer 1.5 inches of the stump circumference with dye added according to manufacturer specifications, and cannot occur within six hours of rain or near water bodies. The contractor assumes full responsibility and liability for all damages, injuries, and property harm resulting from contract execution and must repair any damage to ODOT or third-party property at its sole expense. The project manager is Teresa Bock, and all work is subject to inspection by the designated ODOT representative, with payment withheld for non-compliant work until deficiencies are corrected at the contractor's expense.

View the file

Other files

File Type Posted
00016451 ESB RFCQ 279B.docx DOCX document
00016451 Exhibit 3 Specifications Revised.docx DOCX document
00016451 Addendum2.docx DOCX document
00016451 ESB Sample Contract 279B.docx DOCX document
00016451 Exhibit 4 Supporting Docs.pdf PDF
00016451 Exhibit 5 Vicinity Map.pdf PDF
00016451 Addendum 1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 3 - SPECIFICATIONS

SPECIAL PROVISONS & SPECIFICATIONS FOR

ESB - US 395 Tree Trimming 2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION: The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications that apply to this Request for Competitive Quotes and resulting Contract.

Some sections of the technical specifications are identified and modified below. Sections of the technical specifications not identified below remain applicable to the Contract according to their original terms. Part 00100 of the Standard Specifications (General Conditions) is not applicable to the Contract; however, if a technical specification (Parts 200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the technical specification. The Standard Specifications are available online:

http://www.oregon.gov/ODOT/HWY/SPECS/Pages/standard_specifications.aspx

SCOPE

The work to be completed under this Contract consists of the following, located along us 395, between MP 1.73 (Portal LN) to 2.47 (Nelson RD):

1. Furnish and maintain temporary work zone traffic control.

2. Furnish material, equipment, and labor to fall trees, trim tree canopy, remove brush and vegetation, chip material and treat hardwood tree trunks with herbicide. Remove or chip foliage and debris deposited from felled trees and tree limbs and larger brush, and as directed.

3. Perform additional and incidental work as called for by the plans and specifications.

PROJECT INFORMATION

Project Manager:

Teresa Bock Teresa.m.bock@odot.oregon.gov 541-709-8660

APPLICABLE STANDARD SPECIFICATIONS & SPECIAL PROVISIONS

Silence of Specifications: The apparent silence of the specifications as to any detail, or the apparent omission of a detailed description concerning any point, shall be regarded as meaning that the highest value commercial practices are to prevail and that only materials and workmanship of first quality are to be used.

Where neither the Special Provisions nor the bid schedule indicate separate payment for the work to be completed under this Contract, perform the work as incidental for which no separate measurement or payment will be made.

SECTION 00210 – MOBILIZATION

Comply with Section 00210 of the Standard Specifications modified as follows:

Construction

00210.40 Mobilization – delete the last bullet of the bullet list. Obtaining and maintaining access to Doc Express®, and using Doc Express® to submit documents will not be required on this project.

Payment

00210.90 Payment – delete the last sentence in this Subsection.

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

Comply with Section 00220 of the Standard Specifications.

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

Comply with Section 00221 of the Standard Specifications modified as follows:

00221.00 Scope - Add the following:

Provide work zone traffic control measures conforming to The Oregon Department of Transportation’s Temporary Traffic Control Handbook for Operations of Three Days OR Less, December 2011. Copies of this handbook can be accessed via the internet under “Publications” on the Traffic Engineering and Operations Section web site (Highway Division, Oregon Department of Transportation) at:

2026 ODOT TEMPORARY TRAFFIC CONTROL HANDBOOK (OTTCH)

SECTION 00290 - ENVIRONMENTAL PROTECTION

Comply with Section 00290 of the Standard Specifications. modified as follows:

00290.36(a) Migratory Birds ‑ Add the following to the end of this Subsection:

(1) Bird Management - Bird management activities to comply with the Migratory Bird Treaty Act (16 U.S.C. 703 712) will be performed by the Agency. Ensure that the Agency and its permitted agents have access to the project area, as needed to prevent migratory bird nesting. Nesting prevention may include daily bird harassment and the installation and maintenance of devices that exclude birds.

Do not disturb migratory bird nesting habitats (shrubs, trees, and structures), or clear vegetation from March 1 to September 1 of each calendar year without prior written approval from the Engineer. Notify the Engineer, in writing, a minimum of 10 Calendar Days prior to starting activities that could harm nesting birds.

Measurement

00290.80 Measurement - Replace this Subsection, except for the Subsection number and title, with the following:

No measurement of quantities will be made for work performed under this Section.

Payment

00290.90 Payment - Replace this Subsection, except for the Subsection number and title, with the following:

No separate or additional payment will be made for work performed under this Section. Payment is considered incidental to the work described and required under Section 00744.

SECTION 00320 – CLEARING AND GRUBBING

Comply with Section 00320 of the Standard Specifications modified as follows:

Description

00320.00 Scope – Replace this Subsection, except for the Subsection number and title, with the following:

This work consists of removing and disposing of trees and other vegetation within a specified area or as otherwise directed. This work also consists of treating hardwood tree stumps with herbicide.

00320.01 Areas of Work – Replace this Subsection, except for the Subsection number and title, with the following:

All tree cutting, vegetation removal, and tree canopy trimming work will take place within existing highway right of way between the designated work area limit areas. The work area limit areas will be marked in the field.

Contractor shall cut and remove:

· All dead or visibly dying trees

· All trees with dbh equal to or less than 6 inches

· All limbs and brush

Tree cutting, vegetation removal, and tree canopy trimming shall be completed within the working limits of 35 feet vertical clearance and 30 feet horizontal distance from the edge of pavement or restricted by right of way. Tree canopy trimming requires cutting to the tree trunk and should be done according to accepted industry standards for pruning. This may require cutting outside of the horizontal distance specified. Do not cut or trim trees that fall outside of ODOT right of way. Clearing limits may be modified, but shall not be less than the 30 feet from edge of pavement unless in conflict with right of way limits and fence lines, or as otherwise directed. Edge of Clearing limits shall be uniform along cut line and through transitions.

00320.02 Definitions:

(a) Clearing - Replace this Subsection, except for the Subsection number and title, with the following:

Clearing consists of:

· Preserving trees and other vegetation designated to remain in place.

· Cutting and removing vegetation, brush, and trees.

· Removing downed trees and other vegetative materials.

· Temporarily stockpiling removed materials within designated areas approved by ODOT outside of the Clear Zone.

(b) Grubbing - Delete this Subsection.

Materials

Add the following Subsection:

00320.10 Herbicide - Furnish Polaris AC herbicide or approved equal.

Construction

00320.40 Clearing Operations:

(a) Clearing Trees and Other Vegetation - Replace this Subsection, except for the Subsection number and title, with the following:

Cut trees and brush so they fall into the areas specified to be cleared. The building of access roads will not be required or permitted.

Cut off tree stumps:

· Flush or within 2 inches of the ground surface if within the Clear Zone, as defined in Subsection 00320.02(c).

· No higher than 4 inches above the ground surface if cut outside of the Clear Zone and the Clearing limits.

When cutting tree branches for canopy trimming to the 35 feet vertical and 30 feet horizontal distance requirement and within right of way, cut remainder of the limb off to face of the tree at no additional cost.

Remove all evidence of Clearing matter and debris within the Clear Zone, as defined in Section 00320.02 (c). All cleared matter and debris shall be removed from the Clear Zone and hauled away or chipped on site unless otherwise directed by the ODOT Project Manager or designated representative. This work includes removal of the following unless otherwise directed:

· Felled trees and foliage from felled trees.

· Downed trees and vegetative materials.

· Brush and all other vegetative materials. Sticks and branches from felled trees or branch trimmings with diameters greater than 1” diameter.

· Roadway and roadway Clear Zone shall be cleaned of debris before opening the travel lane to traffic.

· All vegetative matter cut for the purposes of this contract that is of more than 1” diameter and located outside of the designated Clear Zone on slopes of less than 2H:1V incline, shall be removed from the slope and chipped or hauled away unless otherwise directed by ODOT.

· All material from cutting operations shall be disposed of at approved disposal sites or chipped. Materials from cutting/chipping operations shall be removed from ditch lines and slopes in areas where materials may have the potential to migrate into the ditch line or culverts.

00320.41 Grubbing Operations – Delete this Subsection.

00320.42 Disposal of Matter - Replace this Subsection, except for the Subsection number and title, with the following:

All matter and debris accumulated from cutting operations, including marketable trees, become the Contractor's property. Dispose of this matter and debris by one or more of the following methods:

· Chipping - Woody matter may be disposed of by chipping and spreading the chips uniformly over selected areas along the roadway, as directed, in loose layers not more than 3 inches in any dimension.

· Hauling – Woody matter may be hauled away to proper approved disposal sites of the contractors choosing according to 00290.20. Hauled material shall not be deposited on highway right of way except as stated in these specifications.

Add the following Subsection:

00320.44 Herbicide Treatment - All hardwood tree stumps shall be treated with Polaris AC (or approved equal) applied to the outer 1.5” inch of the stem or stump circumference; the outer portion of the cut surface including the cambium until thoroughly wet but not to the point of runoff. Treat the entire surface should the stem size be small. Stumps shall be treated according to the manufacturer’s recommendations as soon as possible after the tree has been cut.

Herbicide shall be utilized and applied as an undiluted concentrate in accordance to the manufacturer’s label guidelines for stump treatment. Dye shall be added to all herbicide mixes following the dye manufacturer’s recommended application rates.

No chemical treatment shall take place within 6 hours of rain showers and within any lake, pond, wetland, roadside ditch, irrigation ditch, river, creek, or any waterway with flowing water.

Measurement

00320.80 Measurement - Work covered under this Section will be measured for payment by the following method:

· Lump Sum - Under this method, no measurement will be made. The Contractor is expected to perform all work by the completion date for the lump sum amount.

Payment

00320.90 Payment - Replace this Subsection, except for the Subsection number and title, with the following:

Payment for the Clearing, disposal, cleanup and other work specified to be performed will be made at the Lump Sum amount under item "Tree Removal, Brushing & Cleanup".

Payment will be payment in full for furnishing all equipment, labor, and incidentals necessary to complete the work as specified.

No separate or additional payment will be made for brushing and cleanup required to access and complete the work as specified.

When the Contract Schedule of Items does not indicate payment for work performed under this Section, no separate or additional payment will be made. Payment will be included in payment made for the appropriate items under which this work is required.

MISCELLANEOUS

· Contractor shall make every effort to create and build goodwill and healthy public relations with adjacent land owners and the traveling public.

· Contractor shall be responsible for all parts of the work area and the removal of all debris and surplus material, so as to leave the area in as good a condition as when the work commenced.

· Contractor shall furnish all necessary supervision, labor, equipment, tools, and transportation, and other resources for removal of trees and vegetation.

· All work performed by the Contractor will be subject to inspection by the designated ODOT representative, and payment will be withheld for any work not complying with the referenced specifications until the deficiencies are corrected. Deficiencies shall be corrected at the sole expense of the Contractor.

LIABILITY

Contractor shall assume the entire responsibility and liability for all damages or injuries of any kind or nature whatsoever to all persons, whether its employees or otherwise, and to all property growing out of or resulting from the execution of the work provided for in this Contract or occurring in connection therewith. Contractor agrees to defend, indemnify, and hold harmless ODOT, its agents, employees, and insurers from and against any and all losses and expenses, including court costs and attorney's fees, damages or injuries growing out of or resulting from or occurring in connection with the execution of the work herein provided for; provided, however, that Contractor will not be held liable for loss of life or injury or damage to person or property due to the sole negligence of ODOT, its agents, or its employees.

If any damage is done to ODOT property (i.e. roadway, fence, signs, guardrail, etc.), or the property of others by Contractor, its employees, or agents during the term of this Contract, Contractor will repair and restore at its sole cost any such property and correct any damages inflicted thereto, returning it to as good a condition as the property was in before being damaged, in a manner satisfactory to the owner(s) of the property for the damage suffered.