00016164 Bid Results.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- US101 MP352. 6 - Lone Ranch Slide
- Solicitation number
- S-73000-00016164
- Issued by
- Crook County, Oregon
About this file
This is a bid results tabulation for an Invitation to Bid (ITB) issued by the Oregon Department of Transportation (ODOT) for the US 101 MP 352.6 Lone Ranch Slide construction project located in Brookings, Oregon. The project scope encompasses excavation and disposal of landslide material, removal and reconstruction of existing rock inlay, placement of stone embankment, installation of subsurface drainage systems, and implementation of temporary work zone traffic control. The procurement solicitation, identified as ITB No. S-73000-00016164, closed on March 17, 2026, at 2:00 PM with nine contractors submitting bids. Estimated project quantities include 160 hours of flagging labor, 1,050 tons of stone embankment, 50 square yards of drainage geotextile, and 275 linear feet of 8-inch diameter drain pipe. The contract requires substantial completion by May 8, 2026, with final completion by May 15, 2026, and is subject to prevailing wage requirements and liquidated damages of $300 per calendar day for failure to meet the substantial completion deadline.
The nine bidders competing for the project were Tidewater Contractors, Inc.; LaDuke Construction, LLC; K&B Quality Excavating, LLC; McLennan Excavation; Whitaker Construction Company; Elite Excavation LLC; Tripeak Contractors Inc; DIRTECH NW LLC; and Granite Construction Company. Total project cost bids ranged from $74,985.00 submitted by Tidewater Contractors, Inc. (the lowest bid) to $214,000.00 submitted by Granite Construction Company. Bid security equal to 10 percent of the total bid amount was required, and first-tier subcontractors with values equal to or exceeding 5 percent of the project bid or $350,000 regardless of percentage required disclosure within two working hours after bid closing. Award would be made to the responsible bidder submitting the lowest responsive bid price, with Oregon preference and reciprocal preference adjustments applied as applicable, and ODOT was required to post its intent to award within five business days after the bid opening date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATT A - Special Provisions and Specifications_MP352.6~2.pdf | ||
| ATT B - Plans_MP352.6~1.pdf | ||
| ATT C Bid Pricing Form_~4.xlsx | XLSX spreadsheet | |
| 00016164 Invitation to Bid.docx | DOCX document | |
| Existing Utility line additional Information.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 3/17/26 | ||||||||||||
| ITB No. | S-73000-00016164 | BIDDER | |||||||||||
| NAME: | Tidewater Contractors, Inc | LaDuke Construction, LLC | K&B Quality Excavating, LLC | McLennan Excavation | Whitaker Construction Company | Elite Excavation LLC | Tripeak Contractors Inc | DIRTECH NW LLC | Granite Construction Company | ||||
| Bid Closing: | 3/17/2026 @ 2:00 PM | CITY/STATE: | Brookings, OR | Central Point, OR | Blodgett, OR | Brookings, OR | Brigham City, UT | Klamath Falls, OR | Canby, OR | Oregon City, OR | Hermiston, OR | ||
| Description: | Us 101 MP 352.6 Lone Ranch Slide | CCB# | 29995 | 193168 | 202260 | 195758 | 201797 | 236407 | 241017 | 220561 | 101195 | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $5,000.00 | $5,000.00 | $11,300.00 | $11,300.00 | $14,000.00 | $14,000.00 | $16,400.00 | $16,400.00 | $22,000.00 | $22,000.00 | $8,854.00 | $8,854.00 | $35,000.00 | $35,000.00 | $21,000.00 | $21,000.00 | $20,500.00 | $20,500.00 |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | $16,000.00 | $16,000.00 | $4,000.00 | $4,000.00 | $7,500.00 | $7,500.00 | $7,500.00 | $7,500.00 | $6,100.00 | $6,100.00 | $9,750.00 | $9,750.00 | $13,000.00 | $13,000.00 | $10,500.00 | $10,500.00 | $18,000.00 | $18,000.00 |
| 3 | Flaggers | 160 | HR | $1.00 | $160.00 | $80.00 | $12,800.00 | $90.00 | $14,400.00 | $120.00 | $19,200.00 | $80.00 | $12,800.00 | $140.62 | $22,499.20 | $120.00 | $19,200.00 | $82.00 | $13,120.00 | $100.00 | $16,000.00 |
| 4 | Erosion Control | 1 | LS | $750.00 | $750.00 | $3,000.00 | $3,000.00 | $1,500.00 | $1,500.00 | $7,000.00 | $7,000.00 | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | $5,000.00 | $5,000.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 5 | Pollution Control Plan | 1 | LS | $250.00 | $250.00 | $1,200.00 | $1,200.00 | $1,500.00 | $1,500.00 | $6,000.00 | $6,000.00 | $2,900.00 | $2,900.00 | $1,000.00 | $1,000.00 | $5,000.00 | $5,000.00 | $2,000.00 | $2,000.00 | $500.00 | $500.00 |
| 6 | General Excavation | 1 | LS | $17,000.00 | $17,000.00 | $14,900.00 | $14,900.00 | $51,950.00 | $51,950.00 | $56,000.00 | $56,000.00 | $30,300.00 | $30,300.00 | $68,000.00 | $68,000.00 | $55,000.00 | $55,000.00 | $58,800.00 | $58,800.00 | $75,000.00 | $75,000.00 |
| 7 | Stone Embankment | 1050 | TONS | $27.00 | $28,350.00 | $54.00 | $56,700.00 | $62.00 | $65,100.00 | $58.00 | $60,900.00 | $77.00 | $80,850.00 | $66.00 | $69,300.00 | $50.00 | $52,500.00 | $59.00 | $61,950.00 | $65.00 | $68,250.00 |
| 8 | Drainage Geotextile, Type 2 | 50 | SQYD | $1.00 | $50.00 | $6.00 | $300.00 | $10.00 | $500.00 | $25.00 | $1,250.00 | $47.00 | $2,350.00 | $38.86 | $1,943.00 | $10.00 | $500.00 | $15.00 | $750.00 | $10.00 | $500.00 |
| 9 | 8 Inch Drain Pipe | 275 | FT | $27.00 | $7,425.00 | $54.54 | $14,998.50 | $35.00 | $9,625.00 | $10.00 | $2,750.00 | $68.00 | $18,700.00 | $13.10 | $3,602.50 | $12.00 | $3,300.00 | $80.00 | $22,000.00 | $50.00 | $13,750.00 |
| TOTAL PROJECT COST | $74,985.00 | $119,198.50 | $166,075.00 | $177,000.00 | $177,500.00 | $185,948.70 | $188,500.00 | $191,620.00 | $214,000.00 |