The document is a bid tabulation (00013249_bid tab.xlsx) from the Oregon Department of Transportation (ODOT) for an Interstate 5 Exit 238 Ramp Paving project in Region 2. The Request for Bid (RFB) No. S-73000-00013249 was issued on 4/7/25, with bids due on 4/7/2025 at 2:00 pm, and involves comprehensive road infrastructure work. The project includes mobilization, temporary work zone traffic control, pollution control, cold plane pavement removal (22,731 square yards), asphalt paving with Level 3, 1/2" Dense ACP Mixture (3,836 tons), and various pavement marking and legend applications. Five bidders submitted proposals: North Santiam Paving Co, Knife River Corporation - Northwest, Roy Houck Construction LLC, Brix Paving Northwest Inc, and Riverbend Construction.
The bid tabulation reveals unit pricing for each project component, with total bid prices ranging from $408,268.20 to $505,505.00. The lowest bid was submitted by North Santiam Paving Co at $408,268.20, while the highest bid came from Riverbend Construction at $505,505.00. The project involves specific road maintenance tasks including pavement removal, asphalt overlay, and repainting road markings, with detailed unit pricing for each element. The procurement is restricted to existing ODOT price agreement holders, indicating a pre-qualified contractor selection process. The project is scheduled for completion by June 30, 2025, and requires compliance with specific regulatory requirements including domestic preference provisions and prevailing wage regulations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exit 238 Paving Plans_Signed~1.pdf | ||
| REQ-DASOBO-00104240 TrelstadSP Notice.pdf | ||
| 00013249_RFB.xlsx | XLSX spreadsheet | |
| 00013249_RFB_3.26.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 4/7/25 | ||||||
| RFB No.: | S-73000-00013249 | BIDDER | |||||
| NAME: | North Santiam Paving Co | Knife River Corporation - Northwest | Roy Houck Construction LLC | Brix Paving Northwest Inc | Riverbend Construction | ||
| Bids due: | 4/7/2025 2:00 pm | ||||||
| Description: | I5 Exit 238 Ramp Paving |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $ 12,000.00 | $ 12,000.00 | $ 9,000.00 | $ 9,000.00 | $ 13,985.00 | $ 13,985.00 | $ 16,000.00 | $ 16,000.00 | $ 39,999.96 | $ 39,999.96 |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | $ 12,000.00 | $ 12,000.00 | $ 24,100.00 | $ 24,100.00 | $ 27,500.00 | $ 27,500.00 | $ 40,000.00 | $ 40,000.00 | $ 30,170.00 | $ 30,170.00 |
| 3 | Pollution Control Plan | 1 | LS | $ 100.00 | $ 100.00 | $ 30.00 | $ 30.00 | $ 100.00 | $ 100.00 | $ 100.00 | $ 100.00 | $ 100.00 | $ 100.00 |
| 4 | Cold Plane Pavement Removal, 3" Deep | 22,731 | SQYD | $ 1.80 | $ 40,915.80 | $ 2.58 | $ 58,645.98 | $ 3.22 | $ 73,193.82 | $ 2.00 | $ 45,462.00 | $ 4.00 | $ 90,924.00 |
| 5 | Level 3, 1/2" Dense ACP Mixture (PG64-22) | 3,836 | TON | $ 85.00 | $ 326,060.00 | $ 81.00 | $ 310,716.00 | $ 80.25 | $ 307,839.00 | $ 95.00 | $ 364,420.00 | $ 85.35 | $ 327,402.60 |
| 6 | Hi-Build Paint, Extruded or Sprayed, Surface | 28,396 | FOOT | $ 0.40 | $ 11,358.40 | $ 0.39 | $ 11,074.44 | $ 0.39 | $ 11,074.44 | $ 0.40 | $ 11,358.40 | $ 0.39 | $ 11,074.44 |
| 7 | Pavement Legend, Type AB, Arrows Elongated | 11 | EACH | $ 350.00 | $ 3,850.00 | $ 352.00 | $ 3,872.00 | $ 350.00 | $ 3,850.00 | $ 350.00 | $ 3,850.00 | $ 350.00 | $ 3,850.00 |
| 8 | Pavement Legend, Type AB, Wrong Way Arrow | 1 | EACH | $ 400.00 | $ 400.00 | $ 405.00 | $ 405.00 | $ 400.00 | $ 400.00 | $ 400.00 | $ 400.00 | $ 400.00 | $ 400.00 |
| 9 | Pavement Bar, Type AB | 132 | FOOT | $ 12.00 | $ 1,584.00 | $ 12.00 | $ 1,584.00 | $ 12.00 | $ 1,584.00 | $ 12.00 | $ 1,584.00 | $ 12.00 | $ 1,584.00 |
| $ 408,268.20 | $ 419,427.42 | $ 439,526.26 | $ 483,174.40 | $ 505,505.00 |