00013247_bid tab.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
R2 Paving RFB - I5 Exit 228 Ramp Paving
Solicitation number
S-73000-00013247
Issued by
Lincoln County, Oregon

About this file

The provided document is a bid tabulation spreadsheet for the Oregon Department of Transportation's (ODOT) I5 Exit 228 Ramp Paving project under the Region 2 Paving Price Agreement series. The bid tabulation reveals six contractors' detailed pricing for eight specific bid items, including mobilization, temporary work zone traffic control, pollution control plan, pavement removal, asphalt mixture placement, thermoplastic marking, and pavement legends. The project involves 11,423 square yards of pavement removal at a 3-inch depth, 1,928 tons of Level 3 asphalt mixture placement, and 13,340 linear feet of thermoplastic marking. The bid submission deadline is April 3, 2024, at 2:00 PM, with a required project completion date of June 30, 2025.

The bid tabulation shows unit pricing variations among contractors, with total bid prices ranging from $282,488.25 (Knife River Corporation - Northwest) to $339,827.00 (Wildish Construction Co). The project requires night-time operations between 9 PM and 5:30 AM, strict ramp closure limitations, and compliance with domestic preference and prevailing wage regulations. While no specific budget is disclosed, the comprehensive infrastructure improvement involves detailed pavement treatment and marking work. The project is part of ODOT's ongoing regional transportation maintenance efforts, with engineering plans signed in February 2025, and will be executed through the OregonBuys platform with final work order effectiveness contingent upon ODOT's procurement authority signature.

View the file

Other files

File Type Posted
Exit 228 Paving Plans_Signed~3.pdf PDF
00013247_RFB.xlsx XLSX spreadsheet
Exit 233 Paving Plans_Signed~1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

S-73000-00013247 I5 Exit 228 Ramp Paving under PA series
BID TABULATIONKnife River Corporation - NorthwestBrix Paving Northwest IncRoy Houck Construction LLCNorth Santiam Paving CoRiverbend ConstructionWildish Construction Co
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Mobilization1LS$ 14,480.00$ 14,480.00$ 14,500.00$ 14,500.00$ 15,000.00$ 15,000.00$ 31,200.00$ 31,200.00$ 33,007.45$ 33,007.45$ 27,000.00$ 27,000.00
2Temporary Work Zone Traffic Control, Complete1LS$ 14,480.00$ 14,480.00$ 25,000.00$ 25,000.00$ 13,000.00$ 13,000.00$ 26,000.00$ 26,000.00$ 24,000.00$ 24,000.00$ 10,000.00$ 10,000.00
3Pollution Control Plan1LS$ 62.00$ 62.00$ 225.00$ 225.00$ 400.00$ 400.00$ 100.00$ 100.00$ 100.00$ 100.00$ 100.00$ 100.00
4Cold Plane Pavement Removal, 3" Deep11,423SQYD$ 3.40$ 38,838.20$ 2.00$ 22,846.00$ 4.10$ 46,834.30$ 4.00$ 45,692.00$ 4.35$ 49,690.05$ 5.00$ 57,115.00
5Level 3, 1/2" Dense ACP Mixture (PG64-22)1,928TON$ 83.85$ 161,662.80$ 95.00$ 183,160.00$ 90.55$ 174,580.40$ 85.00$ 163,880.00$ 89.45$ 172,459.60$ 100.00$ 192,800.00
6Thermoplastic, Extruded, Grooved, Non-Profiled13,340FOOT$ 3.50$ 46,690.00$ 3.60$ 48,024.00$ 3.40$ 45,356.00$ 3.40$ 45,356.00$ 3.85$ 51,359.00$ 3.50$ 46,690.00
7Pavement Legend, Type AB, Arrows Elongated6EACH$ 445.00$ 2,670.00$ 450.00$ 2,700.00$ 420.00$ 2,520.00$ 420.00$ 2,520.00$ 475.00$ 2,850.00$ 430.00$ 2,580.00
8Pavement Bar, Type AB253FOOT$ 14.25$ 3,605.25$ 14.00$ 3,542.00$ 13.50$ 3,415.50$ 14.00$ 3,542.00$ 15.30$ 3,870.90$ 14.00$ 3,542.00
TOTAL$ 282,488.25$ 299,997.00$ 301,106.20$ 318,290.00$ 337,337.00$ 339,827.00