00012712_Bid tab.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
ITB - US101 Culvert Repair Project MP73. 46-MP131. 65
Solicitation number
S-73000-00012712
Issued by
Tillamook County, Oregon

About this file

The document is a bid tabulation sheet for the US101 Culvert Repair Project issued by the Oregon Department of Transportation (ODOT), covering mileposts 73.45 to 131.65 in Tillamook and Lincoln Counties. The project involves comprehensive culvert rehabilitation, with four bidders (JR Carlon Corp, HP Civil Inc, Titan Utilities LLC, and Suulutaaq) providing unit pricing for 26 distinct line items. Key project elements include mobilization, work zone traffic control, portable message signs, pollution control, culvert pipe removal and installation, excavation, riprap placement, video inspection, and temporary water management facilities at multiple mileposts. The contract has a mandatory substantial completion date of September 15, 2025, with a final completion date of September 22, 2025.

The bid tabulation reveals significant price variation among bidders, with total bid amounts ranging from $412,328.00 (JR Carlon Corp) to $841,415.90 (Suulutaaq). Unit prices differ substantially across line items, particularly for critical tasks like culvert rehabilitation and water management facilities. The project requires specialized infrastructure expertise, focusing on environmental protection and stream restoration. While no specific funding sources are explicitly detailed, the contract includes provisions for domestic preference requirements mandating US-produced steel, iron, and manufactured products. Bidders must meet non-discrimination laws, provide drug-testing certifications, and submit a bid bond or certified check for 10% of their total bid amount, with evaluation criteria centered on identifying the lowest responsive and responsible bidder.

View the file

Other files

File Type Posted
00012712_Att B_Specifications.docx DOCX document
Broker of Record RFP.pdf PDF
Att C_Bid Pricing Form~47.xlsx XLSX spreadsheet
00012712_3.27_Q and A.docx DOCX document
00012712_Att A_Plans.pdf PDF
00012712_ITB.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

S-73000-000012712 US101 Culvert Repair Project MP73.45-MP131.65
BID TABULATIONJR Carlon CorpHP Civil IncTitan Utilities LLCSuulutaaq
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Mobilization1LS$20,000.00$ 20,000.00$ 65,456.14$ 65,456.14$ 75,000.00$ 75,000.00$63,500.00$ 63,500.00
2Temporary Work Zone Traffic Control, Complete1LS$ 20,044.80$ 20,044.80$ 125,000.00$ 125,000.00$ 95,000.00$ 95,000.00$ 26,500.00$ 26,500.00
3Portable Changeable Message Signs2EACH$ 1,750.00$ 3,500.00$ 4,000.00$ 8,000.00$ 6,000.00$ 12,000.00$ 8,000.00$ 16,000.00
4Pollution Control Plan1LS$ 750.00$ 750.00$ 500.00$ 500.00$ 12,500.00$ 12,500.00$ 1100.00$ 1,100.00
5Salvage and relay pipe 5 ft depth3FOOT$ 750.00$ 2,250.00$ 400.00$ 1,200.00$ 1,800.00$ 5,400.00$ 460.00$ 1,380.00
618" conc. culvert 5 ft depth15FOOT$ 257.78$ 3,866.70$ 1,000.00$ 15,000.00$ 450.00$ 6,750.00$ 137.00$ 2,055.00
7Remove extg. 2" pipe1LS$ 150.00$ 150.00$ 250.00$ 250.00$ 2,500.00$ 2,500.00$ 2100.00$ 2,100.00
8Remove 18" culvert pipe10FOOT$ 45.00$ 450.00$ 50.00$ 500.00$ 550.00$ 5,500.00$ 380.50$ 3,805.00
9Excavation32CU.YD$ 52.00$ 1,664.00$ 125.00$ 4,000.00$ 110.00$ 3,520.00$ 1,050.00$ 33,600.00
10Class 100 Riprap16CU.YD$ 200.00$ 3,200.00$ 250.00$ 4,000.00$ 90.00$ 1,440.00$ 255.00$ 4,080.00
11Install 36" culvert pipe, 10' Depth12FOOT$ 970.88$ 11,650.56$ 2,000.00$ 24,000.00$ 950.00$ 11,400.00$ 725.00$ 8,700.00
12Rehabilitate 18" culvert487FOOT$ 300.00$ 146,100.00$ 190.00$ 92,530.00$ 355.00$ 172,885.00$ 478.00$ 232,786.00
13Rehabilitate 30" culvert46FOOT$ 762.50$ 35,075.00$ 300.00$ 13,800.00$ 550.00$ 25,300.00$ 1,085.00$ 49,910.00
14Rehabilitate 36" culvert108FOOT$ 425.00$ 45,900.00$ 650.00$ 70,200.00$ 750.00$ 81,000.00$ 930.00$ 100,440.00
15Rehabilitate 48" culvert152FOOT$ 468.75$ 71,250.00$ 620.00$ 94,240.00$ 800.00$ 121,600.00$ 1,295.00$ 196,840.00
16Mainline Video Inspection1586FOOT$ 14.40$ 22,838.40$ 11.05$ 17,525.30$ 2.00$ 3,172.00$ 7.15$ 11,339.90
17Trench Resurfacing45SQYD$ 110.00$ 4,950.00$ 150.00$ 6,750.00$ 275.00$ 12,375.00$ 300.00$ 13,500.00
18Connect to exiting structure4EACH$ 150.00$ 600.00$ 2,000.00$ 8,000.00$ 3,500.00$ 14,000.00$ 925.00$ 3,700.00
19Precast conc. roughness blocks139EACH$ 80.86$ 11,239.54$ 90.00$ 12,510.00$ 200.00$ 27,800.00$ 236.00$ 32,804.00
20Temporary Water Management Facility MP73.461LS$ 859.00$ 859.00$ 17,500.00$ 17,500.00$ 10,000.00$ 10,000.00$ 6,950.00$ 6,950.00
21Temporary Water Management Facility MP74.951LS$ 1,210.00$ 1,210.00$ 17,500.00$ 17,500.00$ 10,000.00$ 10,000.00$ 7,300.00$ 7,300.00
22Temporary Water Management Facility MP75.191LS$ 610.00$ 610.00$ 17,500.00$ 17,500.00$ 10,000.00$ 10,000.00$ 6,700.00$ 6,700.00
23Temporary Water Management Facility MP89.371LS$ 558.00$ 558.00$ 17,500.00$ 17,500.00$ 10,000.00$ 10,000.00$ 6,600.00$ 6,600.00
24Temporary Water Management Facility MP79.811LS$ 1,412.00$ 1,412.00$ 17,500.00$ 17,500.00$ 10,000.00$ 10,000.00$ 7,150.00$ 7,150.00
25Culvert Drainage Markers, Type 18EACH$ 75.00$ 600.00$ 225.00$ 1,800.00$ 650.00$ 5,200.00$ 161.00$ 1,288.00
26Culvert Drainage Markers, Type 28EACH$ 200.00$ 1,600.00$ 225.00$ 1,800.00$ 650.00$ 5,200.00$ 161.00$ 1,288.00
TOTAL$ 412,328.00$ 654,561.44$ 749,542.00$ 841,415.90