The document is a bid tabulation sheet for the US101 Culvert Repair Project issued by the Oregon Department of Transportation (ODOT), covering mileposts 73.45 to 131.65 in Tillamook and Lincoln Counties. The project involves comprehensive culvert rehabilitation, with four bidders (JR Carlon Corp, HP Civil Inc, Titan Utilities LLC, and Suulutaaq) providing unit pricing for 26 distinct line items. Key project elements include mobilization, work zone traffic control, portable message signs, pollution control, culvert pipe removal and installation, excavation, riprap placement, video inspection, and temporary water management facilities at multiple mileposts. The contract has a mandatory substantial completion date of September 15, 2025, with a final completion date of September 22, 2025.
The bid tabulation reveals significant price variation among bidders, with total bid amounts ranging from $412,328.00 (JR Carlon Corp) to $841,415.90 (Suulutaaq). Unit prices differ substantially across line items, particularly for critical tasks like culvert rehabilitation and water management facilities. The project requires specialized infrastructure expertise, focusing on environmental protection and stream restoration. While no specific funding sources are explicitly detailed, the contract includes provisions for domestic preference requirements mandating US-produced steel, iron, and manufactured products. Bidders must meet non-discrimination laws, provide drug-testing certifications, and submit a bid bond or certified check for 10% of their total bid amount, with evaluation criteria centered on identifying the lowest responsive and responsible bidder.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00012712_Att B_Specifications.docx | DOCX document | |
| Broker of Record RFP.pdf | ||
| Att C_Bid Pricing Form~47.xlsx | XLSX spreadsheet | |
| 00012712_3.27_Q and A.docx | DOCX document | |
| 00012712_Att A_Plans.pdf | ||
| 00012712_ITB.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| S-73000-000012712 US101 Culvert Repair Project MP73.45-MP131.65 | |||||||
| BID TABULATION | JR Carlon Corp | HP Civil Inc | Titan Utilities LLC | Suulutaaq | |||
| Bid Item # | Description | Est | |||||
| QTY | UNIT | UNIT | |||||
| PRICE | TOTAL | ||||||
| PRICE | UNIT | ||||||
| PRICE | TOTAL | ||||||
| PRICE | UNIT | ||||||
| PRICE | TOTAL | ||||||
| PRICE | UNIT | ||||||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $20,000.00 | $ 20,000.00 | $ 65,456.14 | $ 65,456.14 | $ 75,000.00 | $ 75,000.00 | $63,500.00 | $ 63,500.00 |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | $ 20,044.80 | $ 20,044.80 | $ 125,000.00 | $ 125,000.00 | $ 95,000.00 | $ 95,000.00 | $ 26,500.00 | $ 26,500.00 |
| 3 | Portable Changeable Message Signs | 2 | EACH | $ 1,750.00 | $ 3,500.00 | $ 4,000.00 | $ 8,000.00 | $ 6,000.00 | $ 12,000.00 | $ 8,000.00 | $ 16,000.00 |
| 4 | Pollution Control Plan | 1 | LS | $ 750.00 | $ 750.00 | $ 500.00 | $ 500.00 | $ 12,500.00 | $ 12,500.00 | $ 1100.00 | $ 1,100.00 |
| 5 | Salvage and relay pipe 5 ft depth | 3 | FOOT | $ 750.00 | $ 2,250.00 | $ 400.00 | $ 1,200.00 | $ 1,800.00 | $ 5,400.00 | $ 460.00 | $ 1,380.00 |
| 6 | 18" conc. culvert 5 ft depth | 15 | FOOT | $ 257.78 | $ 3,866.70 | $ 1,000.00 | $ 15,000.00 | $ 450.00 | $ 6,750.00 | $ 137.00 | $ 2,055.00 |
| 7 | Remove extg. 2" pipe | 1 | LS | $ 150.00 | $ 150.00 | $ 250.00 | $ 250.00 | $ 2,500.00 | $ 2,500.00 | $ 2100.00 | $ 2,100.00 |
| 8 | Remove 18" culvert pipe | 10 | FOOT | $ 45.00 | $ 450.00 | $ 50.00 | $ 500.00 | $ 550.00 | $ 5,500.00 | $ 380.50 | $ 3,805.00 |
| 9 | Excavation | 32 | CU.YD | $ 52.00 | $ 1,664.00 | $ 125.00 | $ 4,000.00 | $ 110.00 | $ 3,520.00 | $ 1,050.00 | $ 33,600.00 |
| 10 | Class 100 Riprap | 16 | CU.YD | $ 200.00 | $ 3,200.00 | $ 250.00 | $ 4,000.00 | $ 90.00 | $ 1,440.00 | $ 255.00 | $ 4,080.00 |
| 11 | Install 36" culvert pipe, 10' Depth | 12 | FOOT | $ 970.88 | $ 11,650.56 | $ 2,000.00 | $ 24,000.00 | $ 950.00 | $ 11,400.00 | $ 725.00 | $ 8,700.00 |
| 12 | Rehabilitate 18" culvert | 487 | FOOT | $ 300.00 | $ 146,100.00 | $ 190.00 | $ 92,530.00 | $ 355.00 | $ 172,885.00 | $ 478.00 | $ 232,786.00 |
| 13 | Rehabilitate 30" culvert | 46 | FOOT | $ 762.50 | $ 35,075.00 | $ 300.00 | $ 13,800.00 | $ 550.00 | $ 25,300.00 | $ 1,085.00 | $ 49,910.00 |
| 14 | Rehabilitate 36" culvert | 108 | FOOT | $ 425.00 | $ 45,900.00 | $ 650.00 | $ 70,200.00 | $ 750.00 | $ 81,000.00 | $ 930.00 | $ 100,440.00 |
| 15 | Rehabilitate 48" culvert | 152 | FOOT | $ 468.75 | $ 71,250.00 | $ 620.00 | $ 94,240.00 | $ 800.00 | $ 121,600.00 | $ 1,295.00 | $ 196,840.00 |
| 16 | Mainline Video Inspection | 1586 | FOOT | $ 14.40 | $ 22,838.40 | $ 11.05 | $ 17,525.30 | $ 2.00 | $ 3,172.00 | $ 7.15 | $ 11,339.90 |
| 17 | Trench Resurfacing | 45 | SQYD | $ 110.00 | $ 4,950.00 | $ 150.00 | $ 6,750.00 | $ 275.00 | $ 12,375.00 | $ 300.00 | $ 13,500.00 |
| 18 | Connect to exiting structure | 4 | EACH | $ 150.00 | $ 600.00 | $ 2,000.00 | $ 8,000.00 | $ 3,500.00 | $ 14,000.00 | $ 925.00 | $ 3,700.00 |
| 19 | Precast conc. roughness blocks | 139 | EACH | $ 80.86 | $ 11,239.54 | $ 90.00 | $ 12,510.00 | $ 200.00 | $ 27,800.00 | $ 236.00 | $ 32,804.00 |
| 20 | Temporary Water Management Facility MP73.46 | 1 | LS | $ 859.00 | $ 859.00 | $ 17,500.00 | $ 17,500.00 | $ 10,000.00 | $ 10,000.00 | $ 6,950.00 | $ 6,950.00 |
| 21 | Temporary Water Management Facility MP74.95 | 1 | LS | $ 1,210.00 | $ 1,210.00 | $ 17,500.00 | $ 17,500.00 | $ 10,000.00 | $ 10,000.00 | $ 7,300.00 | $ 7,300.00 |
| 22 | Temporary Water Management Facility MP75.19 | 1 | LS | $ 610.00 | $ 610.00 | $ 17,500.00 | $ 17,500.00 | $ 10,000.00 | $ 10,000.00 | $ 6,700.00 | $ 6,700.00 |
| 23 | Temporary Water Management Facility MP89.37 | 1 | LS | $ 558.00 | $ 558.00 | $ 17,500.00 | $ 17,500.00 | $ 10,000.00 | $ 10,000.00 | $ 6,600.00 | $ 6,600.00 |
| 24 | Temporary Water Management Facility MP79.81 | 1 | LS | $ 1,412.00 | $ 1,412.00 | $ 17,500.00 | $ 17,500.00 | $ 10,000.00 | $ 10,000.00 | $ 7,150.00 | $ 7,150.00 |
| 25 | Culvert Drainage Markers, Type 1 | 8 | EACH | $ 75.00 | $ 600.00 | $ 225.00 | $ 1,800.00 | $ 650.00 | $ 5,200.00 | $ 161.00 | $ 1,288.00 |
| 26 | Culvert Drainage Markers, Type 2 | 8 | EACH | $ 200.00 | $ 1,600.00 | $ 225.00 | $ 1,800.00 | $ 650.00 | $ 5,200.00 | $ 161.00 | $ 1,288.00 |
| TOTAL | $ 412,328.00 | $ 654,561.44 | $ 749,542.00 | $ 841,415.90 |