This is a bid tabulation spreadsheet for the Oregon Department of Transportation (ODOT) District 5 Sanding Rock 2024 project in Lane County. The document shows bid results from four contractors: Wildish Building Material Co., Knife River, Siegmund Excavation and Construction, and North Santiam Paving Co. The project involves furnishing 10,000 tons of sanding material, with an additional component for hauling and stockpiling the same quantity.
The bid pricing reveals Wildish Building Material Co. as the lowest bidder with a total bid of $398,800.00, followed by Knife River at $647,000.00, Siegmund Excavation and Construction at $765,000.00, and North Santiam Paving Co. at $958,000.00. Wildish Building Material Co. quoted $33.42 per ton for furnishing the material and $6.46 per ton for hauling and stockpiling, while the highest bidder, North Santiam Paving Co., quoted $45.00 and $50.80 per ton respectively for the same services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit 3_PO Terms and Conditions~5.pdf | ||
| 00011462_RFCQ.doc | DOC document | |
| SSDetReq Oregon ASK Ex~1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| District 5 Sanding Rock 2024 (Re-bid) S-73000-00012213 | |||||||
| BID TABULATION | Wildish Building Material Co. | Knife River | Siegmund Excavation and Construction | North Santiam Paving Co. | |||
| Bid Item # | Description | Est | |||||
| QTY | UNIT | UNIT | |||||
| PRICE | TOTAL | ||||||
| PRICE | UNIT | ||||||
| PRICE | TOTAL | ||||||
| PRICE | UNIT | ||||||
| PRICE | TOTAL | ||||||
| PRICE | UNIT | ||||||
| PRICE | TOTAL |
PRICE
| 1 | Furnish Sanding Material | 10000 | Ton | $ 33.42 | $ 334,200.00 | $ 24.85 | $ 248,500.00 | $ 34.50 | $ 345,000.00 | $ 45.00 | $ 450,000.00 |
| 2 | Sanding Material, Haul and Stockpile | 10000 | Ton | $ 6.46 | $ 64,600.00 | $ 39.85 | $ 398,500.00 | $ 42.00 | $ 420,000.00 | $ 50.80 | $ 508,000.00 |
| TOTAL | $ 398,800.00 | $ 647,000.00 | $ 765,000.00 | $ 958,000.00 |