This is a Request for Quote (RFQ) for a Stewardship Contracting project titled Los Pinos Designated Xerophytic Pine (DxP) Integrated Resource Stewardship Contract (IRSC) issued by the USDA Forest Service Pagosa Ranger District, San Juan National Forest in Colorado.

The solicitation seeks a single firm fixed-price contract to perform forest health and stewardship work from the award date through November 30, 2028. Mandatory work includes cutting and removing included timber (498 acres non-pay item) and comprehensive road reconstruction across 11 sub-items totaling approximately 8.27 miles of roads and associated infrastructure improvements. Optional timber subject to agreement removal (Aspen Nonsaw and Biomass) may be included at the contractor's discretion. The primary service code is F014 (Natural Resources/Conservation - Tree Thinning). Quoters must submit signed offers electronically to D_QUOT.tsjckqz1bgj2ukja@u.box.com and chad.bullock@usda.gov by August 20, 2026 at 1:00 p.m. MDT, with a mandatory site visit on July 30, 2026. All work must commence within 10 calendar days of receiving Notice to Proceed and be completed by November 30, 2028. A bid guarantee equal to 20 percent of construction item totals is required, and performance/payment bonds at 100 percent of road reconstruction values are mandatory. Evaluation criteria include Technical Approach (40 percent), Relevant Past Performance (20 percent), Benefit to Local Community (20 percent), and Price (20 percent). The solicitation is unrestricted and includes Davis-Bacon wage requirements for all construction work, Service Contract Act wage determination #2015-5435, and numerous federal compliance requirements including Buy American construction materials provisions, small business considerations, and anti-discrimination certifications.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUMIS CHECKED

CODE 18a. PAYMENT WILL BE MADE BY

CODE

FACILITYCODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

OFFEROR

363N

WASHINGTON DC 20250-1138

MS-1138

1400 INDEPENDENCE AVE SW

USDA-FS STEWARDSHIP CONTRACTING BR

8233 CODE 16. ADMINISTERED BYCODE

X

X

X

113310

SIZE STANDARD:

100.00 % FOR:SET ASIDE:UNRESTRICTED OR363N

REQUEST FOR

PROPOSAL

(RFP)

INVITATION

FOR BID (IFB)

10. THIS ACQUISITION ISCODE

REQUEST FOR

QUOTE (RFQ)

14. METHOD OF SOLICITATION

13b. RATING

NORTH AMERICAN INDUSTRY

CLASSIFICATION STANDARD

(NAICS):

SMALL BUSINESS

08/20/2026 1400 MD

07/20/2026

307-321-3901KEITH BRUGGER

(No collect calls)

INFORMATION CALL:

FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME

4. ORDER NUMBER3. AWARD/ 6. SOLICITATION

12363N26Q4124

5. SOLICITATION NUMBER

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF

1 3 1168765OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

TELEPHONE NO.

17a. CONTRACTOR/

PAGOSA SPRINGS CO 81147

180 SECOND PAGOSA ST

PAGOSA RANGER DISTRICT

USDA FOREST SERVICE

15. DELIVER TO

WASHINGTON DC 20250-1138

MS-1138

1400 INDEPENDENCE AVE SW

9. ISSUED BY

7.

2. CONTRACT NO.

EFFECTIVE DATE

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

ISSUE DATE

DELIVERY FOR FREE ON BOARD

(FOB) DESTINATION UNLESS

BLOCK IS MARKED

11.

SEE SCHEDULEX

12. DISCOUNT TERMS THIS CONTRACT IS A RATED

ORDER UNDER THE DEFENSE

PRIORITIES AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

13a.

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

8(A)

USDA-FS STEWARDSHIP CONTRACTING BR

WOMEN-OWNED SMALL

BUSINESS (WOSB)

ECONOMICALLY DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

Los Pinos DxP IRSC Pagosa Ranger District San Juan National Forest

Email signed SF 1449, price quotes using the Schedule of Items, and Technical Proposal to D__QUOT.tsjckqz1bgj2ukja@u.box.com and chad.bullock@usda.gov. Follow instructions in FAR 52.212-1 Instructions to Offerors.

Period of Performance: Award Date to 11/30/2028 Delivery: 11/30/2028

(Use Reverse and/or Attach Additional Sheets as Necessary)

HEREIN, IS ACCEPTED AS TO ITEMS:

X

XX

DATED

CHAD A. BULLOCK

. YOUR OFFER ON SOLICITATION (BLOCK 5),

INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ARE

ARE

31c. DATE SIGNED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

26. TOTAL AWARD AMOUNT (For Government Use Only)

OFFER

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

ARE NOT ATTACHED.

ARE NOT ATTACHED.

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

30b. NAME AND TITLE OF SIGNER (Type or print)

30a. SIGNATURE OF OFFEROR/CONTRACTOR

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

25. ACCOUNTING AND APPROPRIATION DATA

29. AWARD OF CONTRACT: REFERENCE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER

37. CHECK NUMBER

FINALPARTIAL

36. PAYMENT

FINALPARTIAL

35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER33. SHIP NUMBER

COMPLETE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)

42b. RECEIVED AT (Location)

42a. RECEIVED BY (Print)

41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

STANDARD FORM 1449 (REV. 11/2021) BACK

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

Mark For:

USDA-FS STEWARDSHIP CONTRACTING BR

1400 INDEPENDENCE AVE SW

MS-1138

WASHINGTON DC 20250-1138

Period of Performance: 08/27/2026 to 11/30/2028

0001 The objectives of the Los Pinos DxP project are to increase forest health and vigor, and reduce stand densities and crown continuity in order to reduce the threat of crown fires by accomplishing the following:

Schedule of Items:

1) Cut and Remove Included Timber - Non-pay item

2) Road Reconstruction (Sub items a to k)

Product/Service Code: F014

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- TREE THINNING

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice

Processing Platform (IPP), https://www.ipp.gov.

If the contractor lacks an IPP account, USDA will automatically initiate the enrollment process with Treasury using the contractor's SAM.gov

Accounts Receivable POC as the IPP account holder. Once the enrollment process is complete, the IPP account holder will receive notification and can being invoicing. More information about

Continued ...

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

3 2 of

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12363N26Q4124

IPP can be found at: https://www.ipp.gov

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

1. SCHEDULE OF ITEMS

MANDATORY WORK ACTIVITIES:

ITEM

NO.

DESCRIPTION OF

MANDATORY WORK ACTIVITIES UNIT

ESTIMATED

QUANTITY

UNIT

PRICE TOTAL PRICE

1 Cut and Remove Included Timber Acre 498 N/A N/A

2 Road Reconstruction

a) Mobilization Lump Sum 1

b) Clearing and Grubbing Mile 0.16

a) Excavation and Embankment - Coal Creek Parking Grading

Lump Sum 1

b) Roadway Obliteration Mile 0.13

c) Linear Grading - Compaction Method (b)Reroute Mile 0.16

d) Roadway Obliteration Mile 0.13

e) Linear Grading - Compaction Method (b)Reroute Mile 0.16

f) Untreated Aggregate Courses - Surface

Course Commercial Source, Compaction Method (b)

Ton 7005

g) Road Reconditioning - Aggregate Surface Mile 3.64

h) Road Reconditioning - Native Surface Mile 4.10

i) Culverts and Drains Linear Foot 20

j) FS Heavy Duty Double Closure Gate Lump Sum 1

k) Temporary Traffic Control Lump Sum 1

Total All Mandatory Service Items $_________

12363N26Q4124 Los Pinos DxP IRSC

San Juan National Forest Page 4 of 63

TIMBER/PRODUCT REMOVAL PRICE SCHEDULE:

TIMBER SUBJECT TO AGREEMENT PRICE SCHEDULE:

SCHEDULE NOTES

Note 1: These schedules are for pricing/payment purposes. Refer to 52.212-1, Instructions to Offerors for technical proposal requirements. Evaluation criteria used by the Forest Service for proposals is located in 52.212-2 of this solicitation.

Note: Enter a quantity and Offer (Flat) in the Timber Subject to Agreement Removal Price Schedule if Timber Subject to Agreement (TSA) is being requested in the Technical Proposal. No entry indicates no desire to remove TSA.

Note: Small Business Set-aside procurements do not have the same restrictions as SBA set aside timber sales in regards to the size of businesses that can receive or purchase to manufacture the included timber.

Note: A bid guarantee is required in an amount equal to 20% of the total price offered for the Construction Items only. BID BONDS MUST BE PROVIDED WITH THE INITIAL OFFER. See FAR 52.228-1 Bid Guarantee (SEP 1996).

There is no longer an estimated price magnitude for construction provided in the FAR.

Payment and performance bonds are required for construction projects greater than $150,000 and shall be provided within 10 business days of award for construction (construction items 3 through 35 and associated subitems). Bonds shall be 100% of the total value of the road reconstruction items (see FAR 52.228-15 Performance and Payment Bonds -- (JUN 2020). Bonding costs shall be included in the prices quoted for Mobilization. No separate payment for bond premiums shall be made.

SPECIES PRODUCT ESTIMATED

QUANTITY

UNIT OF

MEASURE

MINIMUM

ACCEPTABLE

OFFER

OFFER

(FLAT)

TOTAL

OFFER

Live Ponderosa Pine and Douglas-

Fir Sawtimber 1,328 CCF $0.25

N/A N/A Live White Fir and

Other Conifers Sawtimber 632 CCF $0.25 N/A N/A

Minimum Acceptable Offer – All Products $490

Total – All Included Products 1/ $_________ 1/ Total Value Offering: Forest Service to determine proportionate rates for Species and Products

SPECIES PRODUCT ESTIMATED

QUANTITY

UNIT OF

MEASURE

MINIMUM

ACCEPTABLE

OFFER

OFFER

(FLAT)

Aspen Nonsaw

CCF $0.25 $_________

All Biomass CCF $0.01 $_________

12363N26Q4124

San Juan National Forest Page 5 of 63

Construction wage rate requirements (Davis-Bacon wage determination) applies to all construction (road reconstruction) work items.

A site visit will be held on July 30th, 2026 to view the project areas and discuss the end results of the project, and to facilitate dialogue on contractual requirements that are anticipated in the contract, and discuss or consider any operational limitations foreseen by attendees. Contact Adam Tlachac to confirm if you will be attending by July 29th at adam.tlachac@usda.gov. The meeting will take place at 9:00 a.m. MDT at the Pagosa Ranger District, 180 Pagosa Street, Pagosa Springs CO 81147.

PERIOD OF PERFORMANCE IS FROM DATE OF AWARD THROUGH NOVEMBER 30, 2028.

2. LAND MANAGEMENT ACTIVITIES.

The Forest Service is executing this procurement under the stewardship contracting authority provided under Section 8205 of Public Law 113-79, the Agricultural Act of 2014 as amended under Section 204 & 207 of the Consolidated Appropriations Act (Omnibus Bill 2018). Stewardship authority grants the Forest Service Chief or designee the authority to aggregate contractual requirements into stewardship projects and solicit those requirements.

Performance of land management activities shall be in accordance with Project Description and Work Specifications. Payment for Land Management Work Activities in Schedule of Items will be made in Stewardship Credits and Appropriated Funds.

All Base Work Activities (Mandatory) shall be performed. Optional activities are listed in order of planned priority.

Award may be made for optional items in any order that the Contracting Officer determines is in the best interest of the Government.

3. FAR 52.212-4 CONTRACT TERMS AND CONDITIONS - COMMERCIAL PRODUCTS AND COMMERCIAL

SERVICES (NOV 2025)

a) Definitions. The clause at Federal Acquisition Regulation (FAR) 52.202-1, Definitions, is incorporated by reference.

(b) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post acceptance rights—

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(c) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

12363N26Q4124 Los Pinos DxP IRSC

San Juan National Forest Page 6 of 63 mailto:adam.tlachac@usda.gov

(d) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(e) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal, or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause FAR 52.233-1, Disputes, which is incorporated in this contract by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence. Examples of occurrences include acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. When an excusable delay occurs, the Contractor shall—

(1) Notify the Contracting Officer in writing as soon as possible;

(2) Remedy the delay as quickly as possible; and

(3) Notify the Contracting Officer when the occurrence is over.

(g) Invoice. The Government will handle invoices according to the Prompt Payment Act (31 U.S.C. 3903) and 5 CFR part 1315. The Contractor shall submit invoices to the address designated in the contract to receive invoices. An invoice must include the information required by 5 CFR part 1315.9(b).

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees, and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark, or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment—

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.

(3) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(4) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—

12363N26Q4124 Los Pinos DxP IRSC

San Juan National Forest Page 7 of 63 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903&num=0&edition=prelim

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(5) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by if–

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

12363N26Q4124

San Juan National Forest Page 8 of 63

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures for interest credits prescribed in FAR part 32 in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon—

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance.

The Government will send a cure notice to the Contractor, unless the reason for the termination is late delivery.

In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Government-financed air transportation; and 41 U.S.C. chapter 21 relating to procurement integrity.

12363N26Q4124

San Juan National Forest Page 9 of 63

(r) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services;

(2) The Disputes, Payments, Invoice, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;

(3) Other contract clauses incorporated in the solicitation or contract;

(4) Addenda to this solicitation or contract;

(5) Solicitation provisions incorporated in the solicitation;

(6) Other paragraphs of this clause;

(7) Other documents, exhibits, and attachments; and

(8) The specification.

(s) Unauthorized obligations.

(1) Except as stated in paragraph (s)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti- Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government-authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (s)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(t) Comptroller General examination of record. This paragraph applies if this contract was awarded using other than sealed bid procedures and is in excess of the simplified acquisition threshold on the date of award of this contract.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices, at all reasonable times, the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR part 4, longer period required by statute, or periods specified in

12363N26Q4124

San Juan National Forest Page 10 of 63 other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement.

Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This clause does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(u) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of clause)

FAR 52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025)

This is a commercial construction acquisition that applies to construction items 3 through 35 and associated subitems. FAR 52.212-4 is amended as follows:

(b) Inspection/Acceptance. Inspection and Acceptance will be conducted in accordance with FAR 52.246-12, Inspection of Construction (Aug 1996).

(d) Changes. Changes will be handled in accordance with the following FAR clause(s): FAR 52.243-4, Changes (Nov 2025).

ADDENDUM TO FAR 52.212-4

4. SCOPE OF CONTRACT

(a) Description of Work- The objectives of this project are to address concerns about forest health and fuel loading, and to improve road condition and decrease erosion associated with road infrastructure by accomplishing the following:

a. Thinning and group selection cuts and timber removal in mixed conifer stands

b. Reconditioning aggregate and native roadways and performing associated maintenance and upgrades to drainage structures and closure gates

c. Rerouting a small segment of system road

d. Regrading and surfacing the Coal Creek trail parking area

(a) Resulting Contract – Any resultant contract will be a firm fixed price commercial services contract with requirements for timber.

(b) Project Location- Township 36 N, Range 1 W, Sections 22, 27, 28, 33, 34, 35, and 36; New Mexico Principal Meridian; Archuleta County, Colorado.

5. ADMINSTRATIVE CHANGES

Notwithstanding 52.212-4 (d), the Government reserves the right to issue unilateral modifications to this contract, provided that such modifications do not affect the contract’s cost, delivery schedule, or scope of work. Examples of permissible unilateral modifications include, but are not limited to, administrative changes, changes to paying office information, corrections of typographical errors, and updates to points of contact. Such unilateral

12363N26Q4124

San Juan National Forest Page 11 of 63 modifications shall be effective upon issuance by the Contracting Officer and shall not require contractor concurrence.

6. SPECIFICATIONS

General specifications for each Contract Activity individually described by an item number in the Schedule of Service Items can be found in Appendix A. Specifications for timber removal can be found in Appendix B and associated road plans and specifications in Appendix C for Stewardship related projects. Incidental construction or reconstruction specified road work plans, drawings, exhibits, and specifications can be found in Appendix D.

7. CONTRACTOR QUALITY CONTROL INSPECTION SYSTEM

The Contractor shall identify the quality control inspection system it will use to ensure that contract specifications will be achieved. At no time shall the contractor rely upon Government inspections to provide notification of unsatisfactory performance. The Contractor shall produce written inspection records in a format and at times and places satisfactory to the Contracting Officer. Inspection records shall be made available upon request of the Contracting Officer and be maintained until the date of contract closure. The Contracting Officer may observe the Contractor's inspection at any time and shall otherwise have unlimited access to the inspection data.

8. ACCEPTANCE

The Forest Service shall perform an inspection upon Contractor’s written request and assurance that work has been completed. Requests shall be for a reasonable portion of work. Acceptance may be made for all or portions of work.

9. GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN

Quality assurance plans specific to individual items will be found in Appendix A.

10. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after receipt of Notice to Proceed for specified work items, (b) prosecute the work diligently, and (c) complete all work no later than November 30, 2028. The time stated for completion shall include final cleanup of the premises.

11. PERIOD OF PERFORMANCE

The period of performance of this contract is from date of award through November 30, 2028.

12. CONTRACT OPERATIONS SCHEDULE

Under this contract, “Contractor’s Operations” shall include activities of or use of equipment of Contractor, Contractor’s employees, agents, Subcontractors, or their employees or agents, acting in the course of their employment in operations hereunder on National Forest lands or within Forest Service protection boundary (unless acting under the immediate supervision of Forest Service).

Contractor’s Operations shall be conducted in a workmanlike and orderly manner. The timing of required Forest Service designation of work on the ground and the performance of other Forest Service work shall not be such as to cause unnecessary delay to Contractor.

Contractor shall, before commencing operations, provide in writing an annual Operating Schedule of anticipated major activities and needs for logging Included Timber and completing stewardship projects, such as logging, road maintenance, and construction. Upon reasonable notice to Forest Service, such a schedule shall be subject to modifications necessitated by weather, markets, or other unpredictable circumstances.

Contractor’s Operations may be conducted outside Normal Operating Season. “Normal Operating Season” is the period(s) beginning and ending on the dates stated below.

12363N26Q4124

San Juan National Forest Page 12 of 63

Timeframe Restriction Description

N/A N/A

13. SCHEDULES AND REPORTS

Contractor shall provide the following submittals as stated below unless otherwise mutually agreed upon. The Contractor shall update all submittals as needed, or as required by the CO, but in no case less than once per calendar year on a date specified by the Contracting Officer:

ITEM DESCRIPTION SUBMITTAL DUE

Proposed Operation Plan (Overall Schedule): The Contractor shall prepare and submit one electronic copy of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the estimated starting and completion dates of various phases of the work. The schedule shall comply with the contract time requirements in the contract.

With proposal for Mandatory Work and 30 days after optional work items are exercised

Schedule for Construction Items: The Contractor shall comply with the requirements of FAR 52.236-15 – Schedules for Construction Contracts. At prework meeting

Subcontractors: List of proposed subcontractors and their intended work. Sub-contractors must have Contracting Officer’s written approval prior to starting work on the project. Submit on Standard Form 1413 at prework at prework meeting.

With proposal

Traffic Control Plan. The Contractor shall prepare and submit a Traffic Control Plan detailing conformance with OSHA requirements, MUTCD requirements, and all other contract requirements, including, but not limited to the requirements included in the Appendices, if any.

At prework meeting

Safety Plan. The Contractor shall comply with the requirements of the solicitation’s safety clause for all activities under this contract.

With proposal

Quality Control Plan. Submit original with proposal. Any updates need to be provided for approval to the CO.

With proposal

Designation of Contractor personnel describing responsibilities and authorities At prework meeting

Annual Operating Plan. Contractor shall submit an annual plan listing units, roads and other information required in Appendix B.

Beginning of every operating season annually Fire Control Plan. Contractor shall submit plan in accordance with Fire Precautions and Control requirements.

At prework meetings

Soil Erosion and Water Pollution Control Plan. The Contractor shall prepare and submit an Erosion Control Plan detailing permanent and temporary control measures to minimize erosion and sedimentation during and after contract performance. Plan shall conform to all contract requirements, including but not limited to #31 “Erosion Prevention and Control”, and the requirements in the Appendices, if any.

At prework meetings

Aggregate Gradation and Quality. Test results certifying material meet specifications.

Shall be turned into COR a minimum of 7 days before placement for review and approval. Before Placement

Equipment Load Limitations List At prework meetings

All schedules and reports shall be submitted to the Contracting Officer, unless the Contracting Officer directs the Contractor to submit any schedules or reports directly to the Contracting Officer’s Representative.

12363N26Q4124 Los Pinos DxP IRSC

San Juan National Forest Page 13 of 63 https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52#FAR_52_236_15

14. STEWARDSHIP CREDITS

Stewardship Credits are credits that are earned and established when work listed in the Schedule of Items has been performed and accepted. Stewardship credits may be cash or non-monetary (product value) and shall be earned at the rate as shown in award documents. Earned non-monetary credits may be used to pay for timber value included in the Schedule of Items. Unless otherwise indicated in the Schedules, credits will be earned based upon Actual Quantities accomplished and accepted.

15. ESTABLISHMENT OF STEWARDSHIP CREDITS

Notwithstanding references to payments in “Payment” clauses or provisions of this contract, payment for Stewardship Activities will be made with Stewardship Credits as indicated in the award document.

Stewardship Credits will be established on a monthly basis as work is accepted. Stewardship credits will be established for the number of units of each activity that have been completed and accepted. Acceptance may be for all, or a reasonable portion of, any specific activity.

Invoices to establish cash credits (cash payment) are to be submitted electronically via the Invoice Processing Platform (IPP).

Invoices to establish non-monetary credit are to be submitted to the Contracting Officer Representative (COR) identified on award documents. These credits will be used to off-set the amount required to be paid for the forest products value when earned prior to the cutting of Included Timber.

16. PAYMENT

It is anticipated that funds will be exchanged in the performance of this contract because the value of the timber will not completely offset the value of the work to be performed. When payment is made to the contractor for work performed, it will be made in accordance with the specifications set forth under the payment methods provisions in Appendix A. When harvesting operations are underway, the value of work completed and timber removed will be documented monthly in the Forest Products Financial System which will produce a Statement of Accounts.

Payment terms for funded (cash credits) stewardship work will be 14 days from invoice approval.

17. TIMBER PAYMENT GUARANTEE

(1) General—(a) To guarantee payment for timber scheduled for removal under the IRSC, Contractor may earn Stewardship Credits in advance of removal or provide a Timber Payment Guarantee in the form of an acceptable surety payment bond, cash payment, or a deposit in a Federal Depository negotiable securities of the United States.

(b) Any earned Stewardship Credits and alternate Timber Payment Guarantee together will maintain a minimum unobligated balance equal to the applicable charges for timber the Forest Service estimates will be cut in 60 calendar days plus the value of any outstanding charges, or equal to the total value of the timber that has not been paid for.

(c) Securities shall be deposited through the Contracting Officer accompanied by a power of attorney and agreement authorizing the bond-approving officer to sell or collect such securities if payment is not made within 15 days of billing by Forest Service. The penal sum of such surety bond or the market value at time of deposit of such negotiable securities shall be the maximum amount of the payment guaranteed.

(2) A Timber Payment Guarantee for a single contract shall be provided utilizing FS Form 6500-12.

(3) Blanket Surety Bond—(a) Contractor may furnish an acceptable bond, or deposits securities, to guarantee payment for timber from multiple contracts. Contractor shall not start cutting hereunder until this contract receives an allocation that will meet the obligation for payment guarantee.

12363N26Q4124

San Juan National Forest Page 14 of 63

(b) The amount of such bond or deposited securities shall be allocated to such contracts by the Forest Service. The Contractor will provide the contact information for the Forest Service representative administering the Blanket Surety Bond.

(c) When there is to be no timber cutting hereunder for 30 days or more and payment of current charges has been made, the allocation to this contract shall be reallocated to other contracts at Contractor’s request.

(d) A Timber Payment Guarantee for multiple contracts (Blanket Guarantee) shall be provided utilizing FS Form 6500-12a.

(4) Letters of Credit for Payment Bond—Contractor may use letters of credit in lieu of a surety bond for payment bond purposes when approved by Contracting Officer.

18. EXCESS STEWARDSHIP CREDITS

In the event there are excess (unused) established Stewardship Credits when all of the included timber has been cut and removed the Forest Service, at its option, shall either add more timber or make cash payment for the unused credits.

19. EXCESS TIMBER VALUE

In the event the value of the included timber exceeds the total value of all of the mandatory activities plus the ordered Optional activities, the Contractor shall make cash payment for the excess timber value.

20. REFUND OF EXCESS CASH

If at any time the credit balance of the Integrated Resource Statement of Account exceeds the charges for timber removed to date and for timber that the Forest Service estimates will be cut within the next 60 calendar days, any portion of such excess from cash in the account shall be refunded if requested by Contractor. If no cutting is planned within the next 60 calendar days, refund of the entire unencumbered cash balance may be made. After a refund, deposits shall be made to meet the requirements of the clause entitled, “TIMBER PAYMENT GUARANTEE” before additional timber may be cut.

21. FOREST PRODUCT APPRAISAL METHODOLGY

Minimum acceptable offer rates for Timber and Product removal were determined using standard Forest Service appraisal methodologies. Specific cruise volumes and cost centers including Project Acres, Skid Cost, CCF/acre, Cf/tree, Road Maintenance Costs, Slash Costs, Temporary Road Costs and Haul Costs were used to determine rates. The final forest product appraisals will not be shared.

22. TIMBER PRODUCT VOLUME ESTIMATION

Quantities listed in Timber/Product removal schedules are estimates only. Volume quantities are made available with the understanding that values shown are Forest Service estimates and are not guaranteed. Contractors are urged to examine the contract areas and make their own estimates.

23. FINAL PAYMENT - RELEASE OF CLAIMS

The Government shall pay the full amount due the Contractor under this contract after—

(1) Completion and acceptance of all work;

(2) Presentation of a properly executed voucher; and

(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release.

12363N26Q4124

San Juan National Forest Page 15 of 63

24. POST AWARD CONFERENCE

A post award conference with the successful quoter is required. It will be scheduled within 10 days after the date of contract award. The conference will be held at Pagosa Ranger District Office or virtually via Microsoft Teams.

25. PHYSICAL DATA

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of, or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by visual observation.

(b) Additional informational material made available to contractors including but not limited to: environmental documentation, timber cruise data, maps, access permits, etc.

26. USE OF PREMISES

(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor. (b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (i) dispose of solid waste in accordance with applicable Federal, State and local regulations. Such permission, if granted, will be without charge to the Contractor.

The Contractor shall comply with the regulations governing the operation of premises which are occupied and shall perform his contract in such a manner as not to interrupt or interfere with the conduct of Government business.

The Contractor shall request permission (in writing) from the appropriate Ranger District to use campsites. If permission is granted, the District Ranger's letter shall specify all conditions and requirements.

It is further stipulated that in addition to clean-up of any camp sites, the Contractor is required to remove all their equipment from National Forest land before final acceptance and payment of the project.

Portable chemical toilets, self-contained holding tanks, approved pit or vault toilets which meet State Code are required.

27. KEY PERSONNEL

(a) The Contractor shall assign to this contract the following key personnel:

Overall Project Manager Logging Supervisor

Road Reconstruction/Maintenance Supervisor

Individual Sub-Managers – Individuals supervising individual sub-contracts for work items not covered by personnel noted previously herein.

(b) During the first 90 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the

12363N26Q4124

San Juan National Forest Page 16 of 63 information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

Key Personnel- Representatives:

Unless otherwise agreed, Contractor shall designate, in writing, a representative who is authorized to receive notices in regard to performance under this contract and take related action. In no case shall Contractor designate any representative to this contract who is currently debarred, proposed for debarment, or suspended by the Federal Government. Contractor’s representative shall provide a copy of the contract to Contractor’s field supervisor and persons authorized to assume responsibilities in the field supervisor’s absence. Prior to initial operations and after shutdowns of 10 days or more, the Contractor’s representative shall notify Forest Service 2 days before, excluding weekends and Federal holidays, any operations resuming in the Contract Area.

The Contractor’s representative shall designate, in writing, a field supervisor, one of whose responsibilities shall be on-the-ground direction and supervision of Contractor’s Operations. The field supervisor shall be readily available to the area of operations when operations are in progress and shall be authorized to receive notices in regard to performance under this contract and take related action. The responsibilities of the field supervisor shall include the safeguarding of National Forest resources and performance within the terms of the contract. The Contractor’s representative will furnish the Forest Service with the names of persons authorized to assume responsibilities in field supervisor’s absence. Such delegations may be made as part of Contractor’s annual Operating Schedule.

Unless the Contracting Officer designates another Forest Service representative and notifies the Contractor in writing, the COR is the representative of Forest Service. The Forest Service representative shall:

(a) Receive notice in regard to performance under this contract,

(b) Take action in relation to this contract, and

(c) Be readily available to the area of work activities and logging operations.

The Contracting Officer shall designate other on-the-ground representatives in writing along with their specific contractual responsibilities and authority. Representatives with authority delegated in writing are the only Forest Service personnel authorized to provide notice or take related actions under the contract. Such a delegation shall be made within 60 days of contract award.

28. EMPLOYMENT OF ELIGIBLE WORKERS

This contract is subject to the Agricultural Worker Protection Act (MSPA), 29 United States Code (U.S.C) 1801- 1872, and to the U.S. Department of Labor (DOL) regulations implementing MSPA 29 Code of Federal Regulations (CFR) Part 500. MSPA eliminates activities detrimental to migrant and seasonal agricultural workers, requires registration of Farm Labor Contractors, and ensures necessary protection for the workers. Information regarding MSPA can be found at https://www.dol.gov/agencies/whd/agriculture/mspa.

If workers are hired under the H-2B program, (8 CFR Section 274A provisions of the Immigration and Nationality Act (INA) for the admission of nonimmigrants to the U.S. to perform temporary labor or services) a Temporary Employment Certification issued by the Office of Foreign Labor Certification (OFLC) in the Department of Labor Employment and Training Administration is required.

12363N26Q4124 Los Pinos DxP IRSC

San Juan National Forest Page 17 of 63 https://www.dol.gov/agencies/whd/agriculture/mspa

For further information on the requirements of the H-2B program, visit OFLC's website at https://www.dol.gov/agencies/eta/foreign-labor.

Compliance with MSPA and the INA is a material condition of this contract. If the contractor employs any unauthorized worker(s) during the performance of this contract that violates section 274A of the INA, the Government may terminate the contract, in addition to other remedies or penalties prescribed by law.

1. Definitions

A. H-2B worker: as used in this part means a nonimmigrant holding a visa authorizing the individual to legally work in the US to perform temporary labor or services. A worker with an H-2B visa (H-2B worker) may also be considered a migrant agricultural worker under MSPA depending on the type and nature of work performed.

2. Migrant Agricultural Worker and Seasonal Agricultural Worker: as used in this part means individuals employed for agricultural (including forestry) work on a seasonal or temporary basis.

a) A worker, moving from one seasonal activity to another, is employed on a seasonal basis even though the worker may continue to be employed during a major portion of the year.

b) An overnight absence from the migrant workers permanent place of residence is required.

c) Members of the contractor's immediate family are not considered migrant or seasonal workers.

Immediate family includes:

Spouse Children, stepchildren, or foster children Parents, stepparents, or foster parents, or Brothers and sisters

3. Farm Labor Contractor (FLC). As used in this part means a person including an individual, partnership, association, joint stock company or a corporation, who, for any money or other valuable consideration, paid or promised to be paid, performs any recruiting, soliciting, hiring, employing, furnishing, or transporting of any migrant or seasonal agricultural worker.

4. Registration Requirements

A. Any contractor providing or hiring H-2B nonimmigrants for work under…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .