0 Stewart Street Remediation Cost Proposal Breakdown.xls

XLS spreadsheet 34 KB Posted

Attached to
0 Stewart Street Remediation Project
Solicitation number
SRC0000034703
Issued by
Russell County, Alabama

About this file

This is a Cost Proposal Breakdown document for the 0 Stewart Street Remediation Project in Alabama. The proposal template is structured to capture costs across multiple service categories including employees/labor, equipment, disposal of solid waste and tires, mobilization, and other materials such as seeding, mulching, and erosion control. The document provides line items for up to eight labor positions, eight pieces of equipment, and multiple disposal categories, with corresponding rate and hours or units fields to calculate total costs for each section. The template includes provisions for engineering services if needed and administrative costs, with all figures to be consolidated into a final project total.

The cost proposal currently shows a subtotal and project total of $1,250.00, with only equipment mobilization costs populated at $1,250.00. All other line items for labor rates, equipment rates, and disposal costs remain unfilled with zero values, indicating this is a blank or preliminary template awaiting contractor completion. The proposal structure allows bidders to itemize their costs transparently across labor, equipment, materials, and mobilization categories, providing the contracting agency with a detailed breakdown of remediation project expenses.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cost Proposal

Site Remdiation Cost Proposal
Date:
Project Name:
EMPLOYEES/ LABOR
LaborRateHours
1$ - 0
2$ - 0
3$ - 0
4$ - 0
5$ - 0
6$ - 0
7$ - 0
8$ - 0
Total$ - 0
EQUIPMENT
EquipmentRateHours
1$ - 0
2$ - 0
3$ - 0
4$ - 0
5$ - 0
6$ - 0
7$ - 0
8$ - 0
Total$ - 0
DISPOSAL
Solid Waste/ TiresRateTon/CYUnits
1tires$ - 0
2$ - 0
3$ - 0
4$ - 0
Total$ - 0
MOBILIZATION
Equipment Mobilization$ 1,250.001$1,250.00
OTHER
Materials - Seeding, Mulching & Erosion Control
Other Supplies
Engineering (if needed)
Total$0.00
SUB-TOTAL$ 1,250.00
Administrative Cost
PROJECT TOTAL$ 1,250.00