NAVRAC NEIPT Remedial Construction 2012-2017

Ended Master IDIQ Awarded

Federal agency
Awardees
6
Task orders
20
Obligated
$21,334,985

Vehicle facts

Opportunity
  • N4008512R1701 Solicitation number
Agency
Combined task order value
$21,334,985 Current and potential, with all options
Last date to order 100% complete
Shared ceiling 43% used
$50,000,000.00

IDV award and task order details come from SAM.gov/FPDS.

About this vehicle

The Department of the Navy Naval Facilities Engineering Command awarded this Master IDIQ on September 26, 2012 for Remedial Action Construction (RAC) projects within the Northeast Integrated Product Team Area of Responsibility, with ordering closed as of September 27, 2017. This vehicle is no longer active; the ordering period ended eight years and nine months ago.

The contract scope encompasses construction of soil, sediment, and groundwater remediation systems including containment (soil covers, RCRA caps, slurry walls, pump-and-treat systems), in-situ treatment (natural attenuation, soil vapor extraction, enhanced bioremediation, air sparging), and ex-situ treatment (air stripping, constructed wetlands, offsite disposal, stabilization, solidification). Awarded task orders reflect demolition of contaminated military housing and buildings, environmental restoration at naval stations and weapons facilities, forest mitigation, and site-specific soil removal and remediation across Navy installations in the Northeast.

Twenty task orders were issued under the vehicle's $50 million shared ceiling. Combined task-order potential value totaled $21.3 million, and all $21.3 million has been obligated. Ordering activity peaked in 2014, 2015, and 2017, with 3, 3, and 4 orders respectively in those years. Task orders ranged from five thousand dollars minimum-guarantee vehicles to $6.2 million for Site 24 remedial action work, with typical substantive orders ranging from roughly $200 thousand to $3.6 million.

Six prime contractors were awarded. Ses-Tech Atlantic captured the largest share with $9.8 million across three orders, followed by the Tidewater-Sovereign joint venture with $5.7 million across eight orders and Terranear PMC LLC with $3 million across three orders. These three primes account for the vast majority of value. Approximately 65 percent of orders (thirteen) were competitive 8(a) set-asides, with 20 percent (four) unrestricted and 15 percent (three) total small business designated.

Funding came almost entirely from Naval Facilities Engineering Command (sixteen orders, $13.2 million) and Navy Installations Command (four orders, $8.2 million). Task orders performed at naval installations across the Northeast, including Naval Station Newport (Rhode Island), Naval Base Ventura County (California), Naval Surface Warfare Center Carderok Division (Pennsylvania), and other Navy facilities.

Description

Master IDIQ for services supporting Remedial Action Construction (RAC) projects within the Northeast Integrated Product Team (NEIPT) Area of Responsibility (AOR) including the construction of various soil, sediment and/or groundwater remediation systems that function as containment (e.g. soil cover, RCRA cap, slurry wall, pump & treat systems), in-situ treatment (e.g. natural attenuation, soil vapor extraction, enhanced bio-remediation, air sparging), and ex-site treatment (air stripping, constructed wetlands, offsite disposal, stabilization, solidification).

IDV awards

Latest task orders

Task order Awardee Awarding agency Obligated Last action
Site 24 work, health and safety plans and remedial action. 0002 Ses-Tech Atlantic NAVFAC $6,226,900
NWS earle site 26 emac soil removal 0002 Koman Government Solutions, LLC NAVFAC $123,335
Demolition of public/private venture military housing at the former gas mask… FZ01 Ses-Tech Atlantic NAVFAC $3,536,847
XX35 FY17 phase 2 - housing demolition at the former N6247317F4725 Tidewater-Sovereign JV NAVFAC $3,639,503
The purpose of this task order is for performing soil excavation and… N4008517F4522 Tidewater-Sovereign JV NAVFAC $307,225
Nwirp bethpage, rehabilitation of town of oyster BAY N4008517F4984 Coastal Environmental Group Inc. NAVFAC $221,867
Demolish buildings A10CC, 25CC, 307CP, and 669 bridge walkway 0002 Watermark Environmental Inc. NAVFAC $2,444,701
Fund minimum guarantee 0001 Ses-Tech Atlantic NAVFAC $0
Minimum guarantee 0001 Tidewater-Sovereign JV NAVFAC $0
Guaranteed minimum 0001 Watermark Environmental Inc. NAVFAC $0
Ntcra at naval station newport, RI 0001 Terranear PMC LLC NAVFAC $451,400
Environmental multiple award contract forest mitigation JU01 Tidewater-Sovereign JV NAVFAC $1,223,540
Demolition of building 444, newport rhode island base year 0002 Terranear PMC LLC NAVFAC $1,952,199
Remedial action (pipeline product removal, limited soil removal, test pitting… 0005 Tidewater-Sovereign JV NAVFAC $209,870
Coastal plain outfall FFP the purpose of this contract task order (CTO) JU01… Terranear PMC LLC NAVFAC $643,739
Decommissioning of as/SVE system, site 7, nwirp calverton, new york 0004 Tidewater-Sovereign JV NAVFAC $88,520
Building 64 demolition 0002 Tidewater-Sovereign JV NAVFAC $222,609
Installation of water services at naval surface warfare center, carderok… 0003 Tidewater-Sovereign JV NAVFAC $32,730
Minimum guarantee 0001 Koman Government Solutions, LLC NAVFAC $5,000
Minimum guarantee 0001 Coastal Environmental Group Inc. NAVFAC $5,000
Show all 20

Top awardees by obligations

Rank Awardee Obligated Share
1 Ses-Tech Atlantic $9,763,747 46%
2 Tidewater-Sovereign JV $5,723,996 27%
3 Terranear PMC LLC $3,047,338 14%
4 Watermark Environmental Inc. $2,444,701 11%
5 Coastal Environmental Group Inc. $226,867 1%
6 Koman Government Solutions, LLC $128,335 1%

Top funding agencies by obligations

Rank Funding agency Obligated Share
1 Department of the Navy $21,334,985 100%

Obligations by fiscal year

Fiscal year Obligated
FY2020 $51,996
FY2019 $349,941
FY2018 $4,186,570
FY2017 $4,503,560
FY2016 $5,148,248
FY2015 $1,473,000
FY2014 $4,971,564
FY2013 $247,706
FY2012 $402,399

Quick answers

What is the NAVRAC NEIPT Remedial Construction 2012-2017 contract vehicle?

NAVRAC NEIPT Remedial Construction 2012-2017 is an indefinite delivery, indefinite quantity (IDIQ) contract vehicle run by Naval Facilities Engineering Command (Department of the Navy), awarded on September 26, 2012.

Which companies hold NAVRAC NEIPT Remedial Construction 2012-2017?

6 companies hold NAVRAC NEIPT Remedial Construction 2012-2017's IDV awards, one each. The latest went to Terranear PMC LLC on September 26, 2012. The awardees whose task orders obligated the most are Ses-Tech Atlantic, Tidewater-Sovereign JV and Terranear PMC LLC.

How much has been spent through NAVRAC NEIPT Remedial Construction 2012-2017?

20 task orders have been placed under NAVRAC NEIPT Remedial Construction 2012-2017, obligating $21,334,985.

What is the shared ceiling of NAVRAC NEIPT Remedial Construction 2012-2017?

NAVRAC NEIPT Remedial Construction 2012-2017's shared ceiling is $50,000,000; its task orders have used 43% of it.

Which agencies use NAVRAC NEIPT Remedial Construction 2012-2017 the most?

The departments whose task orders under NAVRAC NEIPT Remedial Construction 2012-2017 obligated the most are Department of the Navy ($21,334,985).

On GovTribe

See this vehicle's full record

  • Every IDV award and task order
  • Funding by agency, awardee, NAICS and set-aside
  • Teaming partners on this vehicle
  • Ask GovTribe AI about this vehicle