$999M - UNR RDI#2 MATOC covering the contiguous united states (CONUS), alaska, hawaii, and outlying areas as defined by far part 2.
Active Awarded Last action
- Contract number
- W9128F20D0005
- Awardee
-
Weston Solutions Inc. UEI Z4XGALW7L9K6
- Awarding agency
-
ENDIST Omaha
US Army Corps of Engineers, Department of Defense
- Task orders
- 8 $1,564,630,988 obligated
Award facts
- Opportunity
-
- W9128F19R0043 Solicitation number
- Combined order value
- $1,565,232,248 Current and potential, with all options
- Last date to order 89% complete
- IDV ceiling 17% used
- $8,999,000,000.00
- Maximum order
- $999,000,000.00
- Award type
- Multiple award
- Who can order
- Only the awarding agency
- Contracting staff
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 7 offers Negotiated Proposal / Quote
- Pricing
- Cost Plus Fixed Fee
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
About this IDV
ENDIST Omaha (Defense) awarded an indefinite-delivery contract to Weston Solutions Inc. on October 10, 2019, as a multiple-award vehicle with no set-aside, carrying an $8.999 billion ceiling and an ultimate completion date of October 9, 2027. The prime is a large business. The vehicle is the Rapid Disaster Infrastructure Response MATOC, designated UNR RDI#2 in the government description, which lists a $999 million line covering the contiguous United States, Alaska, Hawaii, and outlying areas as defined by FAR Part 2. The government description also records the addition of FAR 52.222-90, addressing DEI discrimination by federal contractors. The vehicle's orders cover emergency infrastructure response, critical facility operations, and disaster-related repair, including temporary power generation and levee repair.
The base-period minimum guarantee was obligated through a $0.00 delivery order for work in Shawnee, Kansas, and a companion action deobligated that minimum guarantee. The most recent order, awarded September 24, 2025, is a $7.86 million cost-plus-fixed-fee embankment repair at the Waco Water Treatment Facility in Robinson, Texas, due for completion July 31, 2026. Earlier orders include temporary power generation at the San Juan Power Plant in San Juan, Puerto Rico (awarded April 10, 2023, cost-plus-fixed-fee, completion March 30, 2026), 150 megawatts of power to the grid at the Palo Seco Power Plant in Puerto Rico (February 24, 2023), $18.4 million in security improvements in Wilmington, Delaware (September 30, 2021), and $57.5 million in interim and final levee repairs at Watson, Missouri (February 14, 2020). NFE Power PR LLC is the named subcontractor on the San Juan order for temporary power generation and LNG fuel supply, with change orders totaling $38.8 million between February 2024 and December 2025.
Task orders
| Task order | Ordering agency | Obligated | Awarded |
|---|---|---|---|
| FY26 RDI schofield barracks water pump replacement | ENDIST Omaha (USACE) | $3,277,078 | |
| Embankment repair - waco water treatment facility | ENDIST Omaha (USACE) | $7,860,634 | |
| Temporary power generation at the SAN juan | ENDIST Omaha (USACE) | $667,651,149 | |
| Temporary power generation at the palo seco power plant | ENDIST Omaha (USACE) | $810,526,937 | |
| Security improvements wilmington, DE | ENDIST Omaha (USACE) | $18,374,704 | |
| Motsu- fire suppression line RPR, N.C. | ENDIST Omaha (USACE) | $265,964 | |
| L-550 interim/final levee repairs | ENDIST Omaha (USACE) | $56,674,561 | |
| Base period - UNR RDI #2 MATOC minimum guarantee | ENDIST Omaha (USACE) | $0 |
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $0 | |
| Exercise an Option | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Original award | $0 |
Subawards
Show all 42
Quick answers
Who was awarded contract W9128F20D0005?
W9128F20D0005 was awarded to Weston Solutions Inc. by ENDIST Omaha (US Army Corps of Engineers) on October 10, 2019.
How much is contract W9128F20D0005 worth?
Orders under W9128F20D0005 have obligated $1,564,630,988. Their combined current value, with exercised options, is $1,565,232,248. W9128F20D0005's own ceiling is $8,999,000,000. A single order can be worth up to $999,000,000.
How many orders have been placed under contract W9128F20D0005?
8 orders have been placed under W9128F20D0005, the latest on August 5, 2026.
Who can order from contract W9128F20D0005?
W9128F20D0005 is a multiple award indefinite delivery contract. Only the awarding agency can place orders on it.
Is contract W9128F20D0005 part of a contract vehicle?
Yes. W9128F20D0005 is part of Rapid Disaster Infrastructure Response MATOC.
Was contract W9128F20D0005 competed?
The extent of competition for W9128F20D0005 was full and open competition. The government received 7 offers.
On GovTribe
See this IDV's full record
- Every order and transaction
- The awardee's other awards and teaming partners
- Similar IDVs and recompete opportunities
- Ask GovTribe AI about this IDV