Temporary power generation at the palo seco power plant

Ended Awarded Last action

Contract number
W9128F23F0065
Awardee
Awarding agency
Obligated
$810,526,937

Award facts

Opportunity
  • W9128F19R0043 Solicitation number
Contract value 99% obligated
$816,199,718.54 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Multiple Award, Fair Opportunity
Pricing
Cost Plus Fixed Fee
Place of performance
FVCG+5HX San Juan National Historic Site, San Juan, 00901, Puerto Rico
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00007 -$5,672,782
Funding Only Action P00006 $19,131,401
Supplemental Agreement for work within scope P00005 · Provide 150MW of power to the grid at palo seco power plant in puerto rico $0
Supplemental Agreement for work within scope P00004 · POP extension for administrative requirements, palo seco power plant, puerto rico $0
Additional Work (new agreement, FAR part 6 applies) P00003 · O & m extension for power generation - palo seco $298,338,826
Supplemental Agreement for work within scope P00002 · Optimized efficiency, fuel-palo seco puerto rico $13,431,821
Supplemental Agreement for work within scope P00001 · !!PR-POWERFY23!! - incorporate demineralized water to the temp. Power generation system and other changes - palo seco $14,868,148
Original award !!PR-POWERFY23!! Temporary power generation at the palo seco power plant $470,429,523

About this award

The Army Corps of Engineers Engineering District Omaha issued a delivery order to Weston Solutions Inc. on February 24, 2023, for $816.2 million (ceiling) to provide 150 megawatts of power to the grid at Palo Seco Power Plant in Puerto Rico. The order is issued under the Rapid Disaster Infrastructure Response MATOC, a DoD-wide emergency infrastructure vehicle supporting rapid deployment of temporary power generation and critical systems repair across federal agencies.

Place of performance is San Juan, Puerto Rico. The order carries an ultimate completion date of March 30, 2026, and is priced as cost-plus-fixed-fee with no set-aside applied. Weston Solutions subcontracted temporary power generation and liquefied natural gas fuel supply services through Nfenergia LLC and NFE Power PR LLC, both Puerto Rico-based entities that have provided specialized power logistics and operations and maintenance support across multiple change orders issued between February 2024 and December 2025.

Subawards

Subcontractor Amount Awarded
Nfenergia PR Power LLC TEMPORARY POWER GENERATION AT THE PALO SECO POWER PLANT Change Order 8 Additional Services $8,123,632
NFE Power PR LLC TEMPORARY POWER GENERATION AT THE PALO SECO POWER PLANT Change Order 10 Additional Services $15,824,821
Nfenergia LLC O&M EXTENSION FOR POWER GENERATION - PALO SECO Change Order 6 Additional Services $50,427,222

Quick answers

Who was awarded contract W9128F23F0065?

W9128F23F0065 was awarded to Weston Solutions Inc. by ENDIST Omaha (US Army Corps of Engineers) on February 24, 2023.

How much is contract W9128F23F0065 worth?

The government has obligated $810,526,937 on W9128F23F0065. Its current value, with exercised options, is $816,199,719.

Is contract W9128F23F0065 an order under another contract?

Yes. W9128F23F0065 is a delivery order under W9128F20D0005, an indefinite delivery contract, on Rapid Disaster Infrastructure Response MATOC.

Was contract W9128F23F0065 competed?

The extent of competition for W9128F23F0065 was full and open competition. The government received 6 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award