B21 building 9201 phase 2 design

Active Awarded Last action

Contract number
W912BV24F0019
Awardee
Awarding agency
Obligated
$11,164,763

Award facts

Contract value 92% obligated
  • $11,164,763.00 Current, with exercised options
  • $12,100,469.00 Potential, with all options
Completion date 95% complete
Current and potential, with all options
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Kansas City, MO 64114, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Exercise an Option P00002 · B21 building 9201 phase 2 design, tinker air force base, oklahoma $172,388
Other Administrative Action P00001 · Modification to extend period of performance to 27 april 2025. $0
Original award $10,992,375

About this award

Burns & McDonnell, Inc. was awarded a $12.1 million firm fixed-price delivery order on January 26, 2024, for the B21 Building 9201 Phase 2 Design project at Tinker Air Force Base in Oklahoma. The contract, which carries an ultimate completion date of December 15, 2026, represents design services for a critical Air Force facility and will be performed from the contractor's Kansas City, Missouri location. This delivery order was issued without a set-aside designation and is funded by the Air Force's ENDIST Tulsa (the Air Force Institute of Technology's Tinker location). Burns & McDonnell, a full-service engineering and architecture firm headquartered in Kansas City, brings extensive experience in Department of Defense facility design and construction, including previous work on military infrastructure projects such as the KC-46A depot corrosion control hangar at Tinker Air Force Base valued at $6.3 million.

The prime contractor assembled a specialized team of subcontractors to execute the design phase, including Crawford Consulting Services, Inc. (a women-owned small business providing construction management and cost engineering support); Avant Acoustics LLC (providing acoustical design services across multiple design phases from 35 percent through 100 percent design completion); Calibre Engineering Inc. (a service-disabled veteran-owned small business contributing architectural and engineering design services including parking lot design and FY25 design packages); Strategic Value Solutions, Inc. (a women-owned small business conducting value engineering studies); and Moca Systems, Inc. (providing project management support and cost controls). This subcontractor structure demonstrates Burns & McDonnell's collaborative approach to complex federal facility design projects while incorporating specialized expertise and small business participation across multiple disciplines critical to the project's success.

Subawards

Subcontractor Amount Awarded
Avant Acoustics LLC B21 BUILDING 9201 PHASE 2 DESIGN Base Scope (35% Design), Option 1 (65% Design), Option 2 (95% Design), Option 3 (100% Design), Reimbursable Cost, Mod to Option… $13,500
Calibre Engineering Inc. B21 BUILDING 9201 PHASE 2 DESIGN 35% Design, 65% Design, 95% Design, FY 24 Parking Lot Design & FY25 Design Package, Amendment 2, Amendment 3, Amendment 4,… $10,000
Calibre Engineering Inc. B21 BUILDING 9201 PHASE 2 DESIGN 35% Design, 65% Design, 95% Design, FY 24 Parking Lot Design & FY25 Design Package, Amendment 2, Amendment 3, Amendment 4 $91,629
Standard Testing & Engineering LLC B21 BUILDING 9201 PHASE 2 DESIGN Geotechnical $153,113
Calibre Engineering Inc. B21 BUILDING 9201 PHASE 2 DESIGN 35% Design, 65% Design, 95% Design, FY 24 Parking Lot Design & FY25 Design Package, Amendment 2 $67,000
Avant Acoustics LLC B21 BUILDING 9201 PHASE 2 DESIGN Base Scope (35% Design), Option 1 (65% Design), Option 2 (95% Design), Option 3 (100% Design), Reimbursable Cost, Mod to Option… $6,400
Crawford Consulting Services, Inc. B21 BUILDING 9201 PHASE 2 DESIGN Base Fee $53,692
Calibre Engineering Inc. B21 BUILDING 9201 PHASE 2 DESIGN 35% Design, 65% Design, 95% Design, FY 24 Parking Lot Design & FY25 Design Package $55,000
Avant Acoustics LLC B21 BUILDING 9201 PHASE 2 DESIGN Base Scope (35% Design), Option 1 (65% Design), Option 2 (95% Design), Option 3 (100% Design), Reimbursable Cost $82,090
Calibre Engineering Inc. B21 BUILDING 9201 PHASE 2 DESIGN 35% Design, 65% Design, 95% Design $238,000
Strategic Value Solutions, Inc. B21 BUILDING 9201 PHASE 2 DESIGN Value study $139,009
Moca Systems, Inc. B21 BUILDING 9201 PHASE 2 DESIGN Base Submittal $96,603
Moca Systems, Inc. B21 BUILDING 9201 PHASE 2 DESIGN Base Submittal, Option 001 Submittal 65%, Option 002 Submittal 95%, Option 003 Submittal 100% $130,904
Show all 13

Quick answers

Who was awarded contract W912BV24F0019?

W912BV24F0019 was awarded to Burns & Mcdonnell, Inc. by ENDIST Tulsa (US Army Corps of Engineers) on January 26, 2024.

How much is contract W912BV24F0019 worth?

The government has obligated $11,164,763 on W912BV24F0019. Its potential value, with all options, is $12,100,469.

Is contract W912BV24F0019 an order under another contract?

Yes. W912BV24F0019 is a delivery order under W912BV20D0030, an indefinite delivery contract.

Was contract W912BV24F0019 competed?

The extent of competition for W912BV24F0019 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award