Delivery Order N4008424D0066-N4008426F4308
Award Date 5/19/26
Potential Completion Date 12/18/26
Potential Value $253K
Funding Federal Agency
Contracting Federal Agency
Ultimate Awardee
Not listed PSC Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Japan
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
7
Legislative Mandate
Not listed National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Marine Corps issued a $325,043.29 delivery order to Nihon Meccs Co., Ltd. on May 1, 2026, to secure doors and window openings at Building 2821, Camp Hansen, Okinawa, Japan, with an ultimate completion date of May 3, 2027. The order is issued under the Camp Butler and Commander Fleet Activities Okinawa Marine Corps Base Design-Bid-Build MACC, a $250 million multiple-award vehicle supporting facility infrastructure projects across Marine Corps installations in Okinawa. Place of performance...
- The Marine Corps issued a delivery order to Witco Industries LTD. on September 11, 2024, with a ceiling value of $1,983,167.60 under the Camp Butler and Commander Fleet Activities Okinawa (CFAO), Japan Marine Corps Base Design-Bid-Build MACC for five combined projects at the 12th Marine Logistics Regiment at Camp Foster, Okinawa, Japan. The parent vehicle is a $250 million multiple-award Design-Bid-Build contract with the Marine Corps for small magnitude design-bid-build requirements at Marine...
- The Marine Corps issued a delivery order to Kyunan Co., LTD. on March 5, 2025, with a ceiling value of $1,920,407.77, under the Camp Butler and Commander Fleet Activities Okinawa (CFAO), Japan Marine Corps Base Design-Bid-Build MACC for interior refurbishment of three buildings at Camp Hansen, Okinawa, Japan. The parent vehicle is a $250 million multiple-award design-bid-build MACC established by the Marine Corps on June 28, 2024, with completion through June 27, 2029, supporting small-magnitude...
- The Marine Corps issued a delivery order to Ohna Denken Co., Ltd. on March 6, 2025, under the Camp Butler and Commander Fleet Activities Okinawa (CFAO), Japan Marine Corps Base Design-Bid-Build MACC for refurbishment of building interiors at Camp Hansen, Okinawa, Japan, with a ceiling value of $1,169,596.59. The parent MACC supports small magnitude design-bid-build construction requirements for Marine Corps Base Camp Butler and Commander Fleet Activities Okinawa. Place of performance is Japan....
- The Marine Corps issued a delivery order to Mitomo Co., LTD. on February 24, 2026, with a ceiling value of $305,766.69, to upgrade physical security at Building 2444, Camp Hansen, Okinawa, Japan, under a firm fixed-price delivery order. The order is issued under the Camp Butler and Commander Fleet Activities Okinawa (CFAO), Japan Marine Corps Base Design-Bid-Build MACC, a multiple-award construction contract vehicle supporting Marine Corps facilities infrastructure projects in Japan. Place of...
- <p>The Marine Corps issued a delivery order to Mitomo Co., LTD. on February 13, 2026, with a ceiling value of $214,701.40, under the Camp Butler and Commander Fleet Activities Okinawa (CFAO), Japan Marine Corps Base Design-Bid-Build MACC to replace bay doors at Building 5866, Camp Foster, Okinawa, Japan.</p> <p>Place of performance is Japan. Work is firm fixed price with an ultimate completion date of September 11, 2026.</p>
- The Marine Corps issued a $322,509.15 delivery order to Tecc Corporation on May 28, 2025, under the Camp Butler and Commander Fleet Activities Okinawa (CFAO), Japan Marine Corps Base Design-Bid-Build MACC for communications installation, repairs, and upgrades at two buildings at Camp Hansen, Okinawa. The order comprises two combined delivery orders: communications installation and repairs at Building 2390, and minor repairs and communications upgrade at Building 2439. Place of performance is...
- The Marine Corps issued a delivery order to American Engineering Corporation on May 18, 2026, with a ceiling value of $731,181.22 for replacement of exterior doors and port windows at Building 2450, Camp Hansen, Okinawa, Japan, under the Camp Butler and Commander Fleet Activities Okinawa (CFAO) Marine Corps Base Design-Bid-Build MACC. Place of performance is Japan. The order is priced firm fixed price with an ultimate completion date of May 17, 2027. The parent vehicle is a $250 million...
- The Marine Corps issued a delivery order to Witco Industries LTD. on May 15, 2026, for installation of new shower rooms, replacement of sanitary fixtures, and associated work at Building 4204, Camp Courtney, Okinawa, Japan, with a ceiling value of $332,222.16. The order is issued under the Camp Butler and Commander Fleet Activities Okinawa (CFAO) Design-Bid-Build MACC, a $250 million Marine Corps multiple-award construction contract vehicle effective through June 2029. Place of performance is...
- The Marine Corps issued a delivery order to Nihon Meccs Co., Ltd. on March 11, 2026, for installation of new window security bars at Building 2860, Camp Hansen, Okinawa, Japan, with a ceiling value of $167,972.27. The order is issued under the Camp Butler and Commander Fleet Activities Okinawa (CFAO), Japan Marine Corps Base Design-Bid-Build MACC, a multiple-award contract vehicle supporting design-build, design-bid-build, and infrastructure maintenance projects across U.S. military...
- N4008424D0066Indefinite Delivery Contract
- N4008424D0066-N4008426F4308Delivery Order
The Marine Corps issued a delivery order to Witco Industries LTD. on May 19, 2026, with a ceiling value of $252,589.88 for replacement of rusted doors at Building 2820, Camp Hansen, Okinawa, Japan. The order is issued under the Camp Butler and Commander Fleet Activities Okinawa (CFAO), Japan Marine Corps Base Design-Bid-Build MACC, a $250 million indefinite-delivery contract effective through June 2029. Place of performance is Camp Hansen, Okinawa, Japan. Ultimate completion is scheduled for December 18, 2026. The work is priced on a firm fixed-price basis with no set-aside designation.
Generated 8/17/26, 10:03 AM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $252.6k | 5/18/26 |