Design and related services for boiler refurbishment

Ended Awarded Last action

Contract number
GS03P01DXD0022GSP0305DX0010
Awardee
Awarding agency
Obligated
$1,085,510

Award facts

Contract value 100% obligated
$1,085,510.28 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Social Security Administration
NAICS code
541330 Engineering Services
PSC
C211 Architect And Engineering- General: Landscaping, Interior Layout, And Designing
Set-aside
No set-aside
Competition
Full and Open Competition · 7 offers Architect-Engineer FAR 6.102
Pricing
Firm Fixed Price
Place of performance
Catonsville, MD 21228, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out PA25 · SSA altmeyer boiler #4 replacement project, design and construction administration (CA) services, modification for closeout. $0
Supplemental Agreement for work within scope PS24 · SSA headquarters - boiler #4 replacement, CA services, modification to extend contract completion date due to construction delays. $0
Supplemental Agreement for work within scope PS23 · SSA altmeyer boiler #4 replacement project; construction administration (CA) services; modification to extend completion date due to necessary construction… $0
Supplemental Agreement for work within scope PS22 · SSA altmeyer boiler #4 project; construction administration services; modification to extend completion date due to necessary construction changes. $0
Supplemental Agreement for work within scope PS21 $3,037
Supplemental Agreement for work within scope PS20 · SSA altmeyer building boiler #4 replacement, design services contract, modification to add inspection of boiler at manufacturing plant site. $2,461
Supplemental Agreement for work within scope PS19 · SSA boiler #4 replacement design, modification to add lead paint testing $750
Other Administrative Action PA18 · SSA boiler #4 replacement, modification to change RWA funding code $0
Supplemental Agreement for work within scope PS17 · SSA altmeyer boiler replacement, AE design services, modification to add work associated with RFP #16 - economizer $8,589
Supplemental Agreement for work within scope PS16 · Modification to incorporate RFP#15 and new GSA personnel. $6,012
Supplemental Agreement for work within scope PS15 · Boiler #04 replacement design - the purpose of this modification is to incorporate CA services for the replacement of boiler #04. $55,279
Other Administrative Action PA99 · SSA boiler #4 replacement, design services, modification to extend completion date. $0
Supplemental Agreement for work within scope PS12 · Design the replacement for boiler #04. $118,998
Supplemental Agreement for work within scope PS11 · Altmeyer boiler refurbishment design - the reason for this modification is to incorporate additional ACM services during the setup and tear down of the boiler… $3,805
Supplemental Agreement for work within scope PS10 · The purpose of this modification is to incorporate RFP's 09 - 11 into the contract. $53,069
Definitize Change Order PS09 · Additional air monitoring services. -$1,034
Change Order PC08 · The purpose of this modification is for additional air monitoring services. $15,000
Supplemental Agreement for work within scope PS07 · Provide all design services to develop construction documents with an estimate for the phased replacement of steam condensate and hot water piping. $15,830
Supplemental Agreement for work within scope PS06 · The purpose of this MOD is to request the a/E to provide construction documents to rebuild/replace two steam stations. $23,256
Supplemental Agreement for work within scope PS05 · GS-03P-01-DX-D-0022 P-03-05-DX-0010 MOD # PS05, PJ5C01141 description-design services to: rebuild two steam stations at the south and west walls of the boiler… $26,268
Supplemental Agreement for work within scope PS04 · Contract administration services and redesign effort for the boiler refurbishment project at the SSA complex, woodlawn MD $263,084
Other Administrative Action 3 $0
Modification $461,612
Supplemental Agreement for work within scope 2 $24,876
Supplemental Agreement for work within scope PS01 $4,619
Show all 25

Quick answers

Who was awarded contract GS03P01DXD0022GSP0305DX0010?

GS03P01DXD0022GSP0305DX0010 was awarded to RMF Engineering, Inc., P.C. by Region 3 (Public Buildings Service) on March 5, 2005.

How much is contract GS03P01DXD0022GSP0305DX0010 worth?

The government has obligated $1,085,510 on GS03P01DXD0022GSP0305DX0010.

Which agency awarded contract GS03P01DXD0022GSP0305DX0010?

Region 3 (Public Buildings Service) awarded GS03P01DXD0022GSP0305DX0010, with funding from Social Security Administration.

Is contract GS03P01DXD0022GSP0305DX0010 an order under another contract?

Yes. GS03P01DXD0022GSP0305DX0010 is a delivery order under GS03P01DXD0022, an indefinite delivery contract.

Was contract GS03P01DXD0022GSP0305DX0010 competed?

The extent of competition for GS03P01DXD0022GSP0305DX0010 was full and open competition. The government received 7 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award