South fork of boulder creek road relocation task order stewardship value of product: $0.00 value of service: $2,691,691 stewardship funding: $337,542

Ended Awarded Last action

Contract number
12363N21F4035
Awardee
Awarding agency
Obligated
$3,029,054

Award facts

Opportunity
  • 12363N21R4002 Solicitation number
Contract value 100% obligated
$3,029,054.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Region 6 - Pacific Northwest Region Forest Service, Department of Agriculture
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources · 3 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Kettle Falls, WA 99141, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00006 · Add rock excavation and hydroseeding stewardship value of product: $0.00 value of service: $3,029,054 stewardship funding: $513,977.99 $100,982
Supplemental Agreement for work within scope P00005 · Equitable adjustment for inflated fuel cost stewardship value of product: $0.00 value of service: $2,928,071.54 stewardship funding: $449,251.53 $96,585
Supplemental Agreement for work within scope P00004 · Extend deadline for base item road relocation due to excusable delay stewardship value of product: $0.00 value of service: $2,831,486.44 stewardship funding:… $0
Supplemental Agreement for work within scope P00003 · Modify approach radius & treat unforeseen spring stewardship value of product: $0.00 value of service: $2,831,486.44 stewardship funding: $449,251.53 $26,331
Supplemental Agreement for work within scope P00002 · Require additional rock excavation and upsize 48 inch culvert to 72 inch. Stewardship value of product: $0.00 value of service: $2,805,155 stewardship… $101,464
Supplemental Agreement for work within scope P00001 · RE-establish survey control points damaged during fire suppression activities stewardship value of product: $0.00 value of service: $2,703,691 stewardship… $12,000
Original award $2,691,691

About this award

The USDA Forest Service awarded a $3,029,054 firm fixed price delivery order to Versatile Industries, Inc. under the agency's R6 Road Construction indefinite delivery/indefinite quantity master contract vehicle. The order is for relocation of the South Fork of Boulder Creek Road in Kettle Falls, Washington, with $2,691,691 allocated for services and $337,542 in stewardship funding. Major subcontractors were not indicated. Work will be performed from August 2021 through October 2022 to support the Forest Service's Pacific Northwest Region road construction programs.

Quick answers

Who was awarded contract 12363N21F4035?

12363N21F4035 was awarded to Versatile Industries, Inc. by Forest Service (Department of Agriculture) on August 12, 2021.

How much is contract 12363N21F4035 worth?

The government has obligated $3,029,054 on 12363N21F4035.

Which agency awarded contract 12363N21F4035?

Forest Service (Department of Agriculture) awarded 12363N21F4035, with funding from Region 6 - Pacific Northwest Region (Forest Service).

Is contract 12363N21F4035 an order under another contract?

Yes. 12363N21F4035 is a delivery order under 1205M620D0018, an indefinite delivery contract, on Forest Service R6 Road Construction.

Was contract 12363N21F4035 competed?

The extent of competition for 12363N21F4035 was full and open competition after exclusion of sources. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award