Advanced munitions technology complex, phase II, eglin air force base, florida award base bid & OPT 6,7,8.

Ended Definitive Contract Awarded Last action

Contract number
W9127820C0034
Awardee
Awarding agency
Obligated
$20,143,676

Award facts

Contract value 41% obligated
  • $20,143,676.00 Current, with exercised options
  • $49,364,676.00 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Army and Air Force Exchange Service Department of Defense
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Eglin AFB, FL 32542, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00007 · GEH08 steam oven piping & pump relocations $495,408
Change Order A00006 · GEH07 fire suppression relocations $330,590
Change Order A00005 · Additional pipe rack steel supports $78,962
Other Administrative Action P00002 · Removal of far clause 52.229-12 tax on certain foreign procurements $0
Change Order A00004 · Delete base bid items 4-6 -$34,910
Change Order A00003 · TS fred $0
Change Order A00002 · Cape deluge fire suppression relocation $4,569
Change Order A00001 · Equipment pads for condensate pumps $20,057
Other Administrative Action P00001 · Notice to proceed admtc phase 2 $0
Original award $19,249,000

About this award

This firm-fixed-price federal contract for $49,364,676.00 was awarded by the Army and Air Force Exchange Service (AAFES) to Hensel Phelps Construction Co for the Advanced Munitions Technology Complex, Phase II, at Eglin Air Force Base in Florida. The contract, which has a completion date of July 18, 2023, does not have a set-aside designation.

The Advanced Munitions Technology Complex includes the construction of two 484-square-foot bunkers, four 495-square-foot bunkers, and a 4,035-square-foot staging building to support explosive machining operations. This contract is part of the broader Tyndall Air Force Base Reconstruction Multiple Award Task Order Contract (MATOC) from the Army Corps of Engineers, which Hensel Phelps is also participating in. Through this MATOC, Hensel Phelps has already received over $140 million in task orders for dormitory construction and other work at Tyndall AFB following Hurricane Michael.

Quick answers

Who was awarded contract W9127820C0034?

W9127820C0034 was awarded to Hensel Phelps Construction Co by ENDIST Mobile (US Army Corps of Engineers) on September 30, 2020.

How much is contract W9127820C0034 worth?

The government has obligated $20,143,676 on W9127820C0034. Its potential value, with all options, is $49,364,676.

Which agency awarded contract W9127820C0034?

ENDIST Mobile (US Army Corps of Engineers) awarded W9127820C0034, with funding from Army and Air Force Exchange Service (Department of Defense).

Was contract W9127820C0034 competed?

The extent of competition for W9127820C0034 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award