Award of the new federal building project in SAN juan, puerto rico.

Ended Definitive Contract Awarded Last action

Contract number
GS02P16AZC7000
Awardee
Awarding agency
Obligated
$81,661,585

Award facts

Opportunity
Contract value 100% obligated
$81,661,584.68 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
San Juan, 00918, Puerto Rico

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action PA45 · Deobligation of funds. -$275,000
Supplemental Agreement for work within scope PS42 · Final settlement agreement $0
Other Administrative Action PA43 · Administrative correction. $0
Funding Only Action PA40 · Modification no. PA40 is an administrative modification to make a correction to the accounting strings by deleting the program code from BA80 accounting… $0
Supplemental Agreement for work within scope PS38 · Modification is issued to reflect additional within scope work. $112,310
Supplemental Agreement for work within scope PS37 · Modification to reflect within scope work. $7,226
Supplemental Agreement for work within scope PS36 · The purpose of the modification is to reflect a credit to an allowance and to settle a request for equitable adjustment due to differing site conditions. $116,989
Additional Work (new agreement, FAR part 6 applies) PS35 · The purpose of this modification is to incorporate additional work and to reflect an extension to the substantial completion date. $139,133
Additional Work (new agreement, FAR part 6 applies) PS34 · PCO-166 pistol holders (millwork) $2,669
Additional Work (new agreement, FAR part 6 applies) PS33 · The purpose of this modification is to adjust the settled amount of modification no. PS32, clin 0104 (PCO-159) to account for state and municipal taxes that… $762
Additional Work (new agreement, FAR part 6 applies) PS32 · Contractor: walsh puerto rico, LLC contract no. GS-02-p-16-AZ-c-7000 PDN: EN-GS-02-p-16-AZ-c-7000 project: new federal building, SAN juan, puerto rico… $7,250
Other Administrative Action PA31 · The purpose for this mass modification change is to change the designated billing office code to bcfa and the designated billing office address code to 0001. $0
Additional Work (new agreement, FAR part 6 applies) PS30 $5,550
Supplemental Agreement for work within scope PS29 $7,550
Supplemental Agreement for work within scope PS28 $107,000
Additional Work (new agreement, FAR part 6 applies) PS27 $78,488
Additional Work (new agreement, FAR part 6 applies) PS26 $203,163
Supplemental Agreement for work within scope PS25 $111,128
Additional Work (new agreement, FAR part 6 applies) PS24 · Contractor: walsh puerto rico, LLC contract no. GS-02-p-16-AZ-c-7000 PDN: EN-GS-02-p-16-AZ-c-7000 project: new federal building, SAN juan, puerto rico… -$13,549
Change Order PS23 · Modification of contract GS-02-p-16-AZ-c-7000 modification no.: PS23 ADN: EN-GS-02-p-16-AZ-c-7000 new federal building, SAN juan, PR the purpose of this… $0
Change Order PS22 $162,404
Additional Work (new agreement, FAR part 6 applies) PS21 $10,557
Supplemental Agreement for work within scope PS20 $292,801
Supplemental Agreement for work within scope PS19 -$499,107
Additional Work (new agreement, FAR part 6 applies) PS18 $270,550
Change Order PS17 · Contractor: walsh puerto rico, LLC contract no. GS-02-p-16-AZ-c-7000 modification no. PS17 PDN: EN-GS-02-p-16-AZ-c-7000 project: new federal building, SAN juan,… $0
Change Order PS16 · The purpose of this modification is to incorporate, by reference, the below listed GSA potential change orders to include deduct work and credited items into… -$103,452
Additional Work (new agreement, FAR part 6 applies) PS15 · The purpose of this modification is to reflect additional items/ services within the original scope of the contract. $340,583
Other Administrative Action PA14 · Modification to transfer contracting authority to hillary gonzalez for the new federal building project in SAN juan, PR. $0
Supplemental Agreement for work within scope PS13 · Modification to incorporate PCO-013 - wall allowance reconciliation (finalizing the wall allowance amount) into the new federal building project in SAN juan,… $25,000
Other Administrative Action PS12 · Modification to extend the contract substantial completion date to november 1, 2019 for the new federal building project in SAN juan, PR. $0
Supplemental Agreement for work within scope PS10 · Modification to incorporate several pcos into the new federal building project in SAN juan, PR. $318,697
Supplemental Agreement for work within scope PS09 · Modification to incorporate pcos 033 & 082 into the new federal building project in SAN juan, PR. $1,067,789
Supplemental Agreement for work within scope PS08 · Modification to incorporate several pcos into the new federal building project in SAN juan, PR. $194,615
Supplemental Agreement for work within scope PS07 · Modification to incorporate pcos 031 & 059 into the new federal building project in SAN juan, PR. $23,668
Supplemental Agreement for work within scope PS06 · Modification to incorporate PCO-052 into the new federal building project in SAN juan, PR. $165,290
Supplemental Agreement for work within scope PS05 · Modification to incorporate several pcos into the new federal building project in SAN juan, PR. $244,560
Supplemental Agreement for work within scope PS04 · Modification to incorporate pcos-007, 019, 024 and 029 into the new federal building project in SAN juan, PR. $142,320
Supplemental Agreement for work within scope PS03 · Modification to incorporate "PCO-001 - POR and RDM revisions (design cost)" in the new federal building project in SAN juan, PR. $77,640
Other Administrative Action PA01 · Notice to proceed modification for the new federal building project in SAN juan, puerto rico. $0
Original award $78,317,000
Show all 41

About this award

This is a $81,661,584.68 firm fixed price contract awarded by the General Services Administration's Region 2 office to Walsh Puerto Rico, LLC for the construction of a new federal building in San Juan, Puerto Rico. The contract does not have a set-aside designation. Major subcontractors include Bermudez, Longo, Diaz-Masso, LLC for mechanical, electrical, and power work, Analytical Management Solutions, Inc. for scheduling services, Terrasol Engineering Group LLC for earthwork and sitework, Deya Elevator Services, Inc. for elevator work, Glasstra Aluminum Inc. for exterior glazing, Terracon Consultants, Inc. for geotechnical reporting, and SP Systems, Inc. for fire protection. The contract began on April 4, 2016 and is scheduled for completion on March 15, 2020. This award supports the GSA's effort to build new federal facilities to house government operations.

Quick answers

Who was awarded contract GS02P16AZC7000?

GS02P16AZC7000 was awarded to Walsh Puerto Rico, LLC by Region 2 (Public Buildings Service) on April 4, 2016.

How much is contract GS02P16AZC7000 worth?

The government has obligated $81,661,585 on GS02P16AZC7000.

Was contract GS02P16AZC7000 competed?

The extent of competition for GS02P16AZC7000 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award