Construction services for the LBJ consolidation & switchgear renovation at the department of education federal building 400 maryland AVE SW washington DC

Active Definitive Contract Awarded Last action

Contract number
47PM0121C0006
Awardee
Awarding agency
Obligated
$53,179,895

Award facts

Opportunity
Contract value 83% obligated
  • $53,183,769.17 Current, with exercised options
  • $64,106,298.17 Potential, with all options
Completion date 83% complete
  • Current, with exercised options
  • Potential, with all options
Contracting staff
Funding agency
Contracts and Acquisition Management Department of Education
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Washington, DC 20024, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0039 · Modification PS0039 for constructability review services at the lyndon B johnson building renovation and department of energy relocation in washington, DC $32,708
Supplemental Agreement for work within scope PS0036 · Change order $209,506
Supplemental Agreement for work within scope PS0034 · MOD issued for CE 136 PR 208 alter electric stub UPS CE 140 PR 220 swgr 4 wiring issues CE 143 PR 225 furnish and install exit signs and CE 145 PR 224 demo stub… $41,671
Supplemental Agreement for work within scope PS0033 · 47PM0121C0006, MOD PS0033 - PS0033 package - CE 137, 138 & 139 BA55_62,097 - MOD to add CE137/CE138/CE139 services. POP unchanged at 05/05/2026. Located: lyndon… $62,097
Supplemental Agreement for work within scope PS0032 · 47PM0121C0006, MOD PS0032 - PS0032 package - CE 133, 134 & 135 BA55_172,168 - MOD to add CE133/CE134/CE135 services. POP unchanged at 05/05/2026. Location:… $172,168
Supplemental Agreement for work within scope PS0031 · 47PM0121C0006, MOD PS0031 - PS0031 package - 6TH floor unforeseens BA55 - 535,908 - MOD to add CE129/CE130/CE131 services. POP unchanged at 05/05/2026.… $535,908
Supplemental Agreement for work within scope PS0030 · 47PM0121C0006PS0030 - PS0030 package - 3RD floor signage changes and FLS updates BA55 - 38,467 - MOD to update signs/FLS needs. POP unchanged. Located at LBJ… $38,467
Supplemental Agreement for work within scope PS0029 · 47PM0121C0006, MOD PS0029 - corrective action - RE-obligation of PS0027 line items - MOD PS0028 accidentally DE-obligated the funds from MOD PS0027. This MOD… $4,748,074
Supplemental Agreement for work within scope PS0028 · Deob MOD -$4,748,074
Supplemental Agreement for work within scope PS0027 · 47PM0121C0006 PS0027 - PS0027 package - 6TH floor design changes, 6TH FL BR, 3RD FL closeout modifications _split BA55-BA80 - MOD to add CE83/CE107/CE120-127… $4,748,074
Exercise an Option PS0026 · 47PM0121C0006 - PS0026 package - 6TH floor option split BA55-BA80 - 9,078,842 - MOD to exercise option 3 for 6TH floor construction at the LBJ building, 400… $9,078,842
Supplemental Agreement for work within scope PS0025 · 47PM0121C0006, MOD PS0025 - split BA55-BA80 - 302,060 - MOD to add CE 86, CE 101, CE 102, CE 104, CE 105, CE 106, CE 108, CE 109, CE 110, CE 111, CE 112, CE… $302,060
Supplemental Agreement for work within scope PS0024 · 47PM0121C0006, MOD PS0024 - PS0024 package - split BA55-BA80 - 461,868 - MOD to CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, and CE 103 services to the… $461,868
Supplemental Agreement for work within scope PS0023 · 47PM0121C0006, MOD PS0023 - PS0023 package - split BA55-BA80 - 967864 - this modification is to cover the daily general conditions for a period of 101… $967,864
Definitize Change Order PS0022 · MOD PS0022 to definitize unilateral MOD PC0020 for CE82 $881,839
Supplemental Agreement for work within scope PS0021 · 47PM0121C0006, MOD PS0021 - LBJ consolidation construction & switchgear - supplemental work within scope $149,509
Change Order PC0020 · 47PM0121C0006, MOD PC0020 - LBJ consolidation construction & switchgear - PDL MOD $3,451,802
Supplemental Agreement for work within scope PS0019 · 47PM0121C0006, MOD PS0019 - LBJ consolidation construction & switchgear $99,880
Supplemental Agreement for work within scope PS0018 · 47PM0121C0006, MOD PS0018 - LBJ consolidation construction & switchgear. RWA #B5015467 & B5011858 $545,611
Exercise an Option PO0017 · MOD PO0017 exercise option 9 - 6TH floor bathrooms - split BA55-BA80 - $571,700. RWA# B5016442 (note: baov edited to reflect correct amount) $571,700
Exercise an Option PO0016 · MOD PO0016 - LBJ consolidation construction & switchgear - exercising option 2: 3RD floor construction. $7,471,398
Exercise an Option PO0015 · 47PM0121C0006, MOD PO0015 - LBJ consolidation construction & switchgear - exercise OPT 6 (clin 0007) for 3RD floor restrooms $546,700
Supplemental Agreement for work within scope PS0014 · 47PM0121C0006, MOD PS0014 - LBJ consolidation construction & switchgear $99,435
Change Order PC0013 · 47PM0121C0006, MOD PC0013 - LBJ consolidation construction & switchgear MOD 3RD floor demo as part of the 3RD floor lntp $1,522,758
Supplemental Agreement for work within scope PS0012 · MOD PS0012 supplemental work $99,469
Supplemental Agreement for work within scope PS0011 · MOD PS0011 supplemental work for the LBJ consolidation & switchgear project. RWA B5011858 $287,582
Supplemental Agreement for work within scope PS0010 · PS0010 - supplemental work (RWA# B5011858 and RWA# B5012763) $74,761
Supplemental Agreement for work within scope PS0009 · MOD PS0009 supplemental work $98,265
Supplemental Agreement for work within scope PS0008 · MOD PS0008 to contract 47PM0121C0006 $151,935
Supplemental Agreement for work within scope PS0007 · MOD PS0007 - CE 19, 19-1, 24 & 25 $328,661
Supplemental Agreement for work within scope PS0006 · 47PM0121C0006, MOD PS0006 - LBJ consolidation construction & switchgear $852,943
Supplemental Agreement for work within scope PS0005 · MOD PS0005 - unforeseen conditions $154,696
Supplemental Agreement for work within scope PS0004 · MOD PS0004 add CE05, CE07, CE10, CE11, CE13 to LBJ cons & switchgear project $235,830
Supplemental Agreement for work within scope PS0003 · PS0003 - add kahua requirement $0
Supplemental Agreement for work within scope PS0002 · MOD PS0002 credit/descope and add supplemental work $88,990
Supplemental Agreement for work within scope PS0001 · Covid-19 safety protocols $0
Original award $18,814,900
Show all 37

About this award

Contracts and Acquisition Management, the civilian agency named as funding agency, awarded a definitive, firm-fixed-price contract to John C. Grimberg Co., Inc. on September 28, 2021, with a ceiling value of $64.1 million. The award uses no set-aside and covers construction services for the Lyndon B. Johnson Federal Building consolidation and switchgear renovation at 400 Maryland Avenue SW, plus constructability review services under Modification PS0039 for the LBJ renovation and Department of Energy relocation. Place of performance is Washington, DC 20024, and ultimate completion is November 30, 2027.

The originating pre-solicitation, posted February 2, 2021 with responses due February 12, 2021, sought construction firms to renovate approximately 198,369 square feet of LBJ office space into an open floor plan, including interior alterations, systems upgrades, and electrical infrastructure renovation. It estimated a single firm-fixed-price budget of $50 million to $60 million under NAICS 236220 with a $39.5 million size standard. It required respondents to qualify as small businesses and self-perform at least 15% of the work, yet the resulting award carries no set-aside.

Subcontract records tied to the award include Hodges Window and Glass LLC for glass mirror work and Selective Demolition LLC for demolition, alongside multiple other specialty scopes covering testing and balancing, electrical, sprinkler, and partitions.

Service Contract Inventory data shows the awardee in a prime role. FY2025 invoiced government labor totaled $15.2 million across 19.8 FTEs and 41,205 contractor hours, a derived rate of $369.80 per hour. The rate declined from $765.90 per hour in FY2022, and FTEs rose from 5.2 in FY2022 to 19.8 in FY2025 after a dip to 15.8 in FY2024. Invoiced dollars grew from $8.3 million in FY2022. In FY2025, 12 subcontractors performed work, and 75% of contractor hours were subcontracted. The rates are blended prime and subcontractor figures and are approximate.

Subawards

Subcontractor Amount Awarded
Hodges Window And Glass LLC 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $17,958
Seneca Balance Of Maryland LLC 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $27,500
Selective Demolition LLC 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $240,000
Partition Plus Inc. 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $110,332
Film Works Window Film LLC 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $22,433
Kelly Floors, LLC 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $290,000
Fallston Supply Inc. 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $136,800
Nello Wall Systems Inc. 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $614,002
Phenomenal, LLC 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $121,125
Subcontractor not on record 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $108,300
Singleton Electric Company, Inc. 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $8,375,000
Metro Test And Balance Inc. 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $30,655
Everon, LLC 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $195,750
Goel Services Inc. 47PM0121C0006, MOD PS0024 - PS0024 PACKAGE - SPLIT BA55-BA80 - 461,868 - MOD TO CE 90, CE 94, CE 96, CE 97, CE 98, CE 99, CE 100, AND CE 103 SERVICES TO THE… $189,000
Show all 14

Quick answers

Who was awarded contract 47PM0121C0006?

47PM0121C0006 was awarded to John C. Grimberg Co., Inc. by National Capital Region (Public Buildings Service) on September 28, 2021.

How much is contract 47PM0121C0006 worth?

The government has obligated $53,179,895 on 47PM0121C0006. Its current value, with exercised options, is $53,183,769. Its potential value, with all options, is $64,106,298.

Which agency awarded contract 47PM0121C0006?

National Capital Region (Public Buildings Service) awarded 47PM0121C0006, with funding from Contracts and Acquisition Management (Department of Education).

Was contract 47PM0121C0006 competed?

The extent of competition for 47PM0121C0006 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award