FAR 52.243-3 Changes-Time-and-Materials or Labor-Hours

Clause Federal Acquisition Regulation Sep 2000 version

Facts

Citation
FAR 52.243-3
Type
Clause
Current version
September 2000
Prescribed in
FAR 43.205(c)
Last amended
65 FR 46072 Effective Sep 25, 2000
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.

Text

As prescribed in 43.205(c), insert the following clause:

Changes-Time-and-Materials or Labor-Hours (Sept 2000)

(a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:

(1) Description of services to be performed.

(2) Time of performance (i.e., hours of the day, days of the week, etc.).

(3) Place of performance of the services.

(4) Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the Government in accordance with the drawings, designs, or specifications.

(5) Method of shipment or packing of supplies.

(6) Place of delivery.

(7) Amount of Government-furnished property.

(b) If any change causes an increase or decrease in any hourly rate, the ceiling price, or the time required for performance of any part of the work under this contract, whether or not changed by the order, or otherwise affects any other terms and conditions of this contract, the Contracting Officer will make an equitable adjustment in any one or more of the following and will modify the contract accordingly:

(1) Ceiling price.

(2) Hourly rates.

(3) Delivery schedule.

(4) Other affected terms.

(c) The Contractor shall assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order. However, if the Contracting Officer decides that the facts justify it, the Contracting Officer may receive and act upon a proposal submitted before final payment of the contract.

(d) Failure to agree to any adjustment will be a dispute under the Disputes clause. However, nothing in this clause excuses the Contractor from proceeding with the contract as changed.

(End of clause)

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation; Time-and-Materials or Labor-Hours 65 FR 46072 · FAC 97-19

Quick answers

What is FAR 52.243-3?

FAR 52.243-3 is a clause of the Federal Acquisition Regulation, titled "Changes-Time-and-Materials or Labor-Hours".

What is the current version of FAR 52.243-3?

The current version is dated September 2000.

Where is FAR 52.243-3 prescribed?

It is prescribed in FAR 43.205(c), Contract clauses.

When was FAR 52.243-3 last changed?

The most recent final rule on record is "Federal Acquisition Regulation; Time-and-Materials or Labor-Hours" (65 FR 46072), published Jul 26, 2000 and effective Sep 25, 2000.

Are changes to FAR 52.243-3 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract