(a)

(1) The contracting officer shall insert the clause at 52.243-1, Changes-Fixed-Price, in solicitations and contracts when a fixed-price contract for supplies is contemplated.

(2) If the requirement is for services, other than architect-engineer or other professional services, and no supplies are to be furnished, the contracting officer shall use the clause with its AlternateI.

(3) If the requirement is for services (other than architect-engineer services, transportation, or research and development) and supplies are to be furnished, the contracting officer shall use the clause with its AlternateII.

(4) If the requirement is for architect-engineer or other professional services, the contracting officer shall use the clause with its AlternateIII.

(5) If the requirement is for transportation services, the contracting officer shall use the clause with its AlternateIV.

(6) If it is desired to include the clause in solicitations and contracts when a research and development contract is contemplated, the contracting officer shall use the clause with its Alternate V.

(b)

(1) The contracting officer shall insert the clause at 52.243-2, Changes-Cost-Reimbursement, in solicitations and contracts when a cost-reimbursement contract for supplies is contemplated.

(2) If the requirement is for services and no supplies are to be furnished, the contracting officer shall use the clause with its AlternateI.

(3) If the requirement is for services and supplies are to be furnished, the contracting officer shall use the clause with its AlternateII.

(4) If the requirement is for construction, the contracting officer shall use the clause with its AlternateIII.

(5) [Reserved]

(6) If it is desired to include the clause in solicitations and contracts when a research and development contract is contemplated, the contracting officer shall use the clause with its Alternate V.

(c) Insert the clause at 52.243-3, Changes-Time-and-Materials or Labor-Hours, in solicitations and contracts when a time-and-materials or labor-hour contract is contemplated. The contracting officer may vary the 30-day period in paragraph (c) of the clause according to agency procedures.

(d) The contracting officer shall insert the clause at 52.243-4, Changes, in solicitations and contracts for-

(1) Dismantling, demolition, or removal of improvements; and

(2) Construction, when a fixed-price contract is contemplated and the contract amount is expected to exceed the simplified acquisition threshold.

(e) The contracting officer shall insert the clause at 52.243-5, Changes and Changed Conditions, in solicitations and contracts for construction, when the contract amount is not expected to exceed the simplified acquisition threshold.

(f) The contracting officer may insert a clause, substantially the same as the clause at 52.243-6, Change Order Accounting, in solicitations and contracts for supply and research and development contracts of significant technical complexity, if numerous changes are anticipated. The clause may be included in solicitations and contracts for construction if deemed appropriate by the contracting officer.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation; FAR Case 2004-025, Government Property 72 FR 27364 · FAC 2005-17
Federal Acquisition Regulation; Time-and-Materials or Labor-Hours 65 FR 46072 · FAC 97-19

Sections cited

Quick answers

What is FAR 43.205?

FAR 43.205 is a section of the Federal Acquisition Regulation, titled "Contract clauses".

When was FAR 43.205 last changed?

The most recent final rule on record is "Federal Acquisition Regulation; FAR Case 2004-025, Government Property" (72 FR 27364), published May 15, 2007 and effective Jun 14, 2007.

Are changes to FAR 43.205 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract