FAR 52.242-17 Government Delay of Work
Clause Federal Acquisition Regulation Apr 1984 version
Facts
- Citation
- FAR 52.242-17
- Type
- Clause
- Current version
- April 1984
- Prescribed in
- FAR 42.1305(c)
- Last amended
- 86 FR 61017 Effective Dec 6, 2021
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.
Text
As prescribed in 42.1305(c), insert the following clause:
Government Delay of Work (Apr 1984)
(a) If the performance of all or any part of the work of this contract is delayed or interrupted (1)by an act of the Contracting Officer in the administration of this contract that is not expressly or impliedly authorized by this contract, or (2)by a failure of the Contracting Officer to act within the time specified in this contract, or within a reasonable time if not specified, an adjustment (excluding profit) shall be made for any increase in the cost of performance of this contract caused by the delay or interruption and the contract shall be modified in writing accordingly. Adjustment shall also be made in the delivery or performance dates and any other contractual term or condition affected by the delay or interruption. However, no adjustment shall be made under this clause for any delay or interruption to the extent that performance would have been delayed or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an adjustment is provided or excluded under any other term or condition of this contract.
(b) A claim under this clause shall not be allowed-
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved; and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the delay or interruption, but not later than the day of final payment under the contract.
(End of clause)
Federal Register history
Quick answers
What is FAR 52.242-17?
FAR 52.242-17 is a clause of the Federal Acquisition Regulation, titled "Government Delay of Work".
What is the current version of FAR 52.242-17?
The current version is dated April 1984.
Where is FAR 52.242-17 prescribed?
It is prescribed in FAR 42.1305(c), Contract clauses.
When was FAR 52.242-17 last changed?
The most recent final rule on record is "Federal Acquisition Regulation: Revision of Definition of “Commercial Item”" (86 FR 61017), published Nov 4, 2021 and effective Dec 6, 2021.
Are changes to FAR 52.242-17 proposed?
No proposed rule from the last 3 years is waiting on a final rule.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract