FAR 44.204 Contract clauses
Section Federal Acquisition Regulation
Facts
- Citation
- FAR 44.204
- Type
- Section
- Last amended
- 71 FR 225 Effective Jan 3, 2006
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.
Text
(a)
(1) The contracting officer shall insert the clause at 52.244-2, Subcontracts, in solicitations and contracts when contemplating-
(i) A cost-reimbursement contract;
(ii) A letter contract that exceeds the simplified acquisition threshold;
(iii) A fixed-price contract that exceeds the simplified acquisition threshold under which unpriced contract actions (including unpriced modifications or unpriced delivery orders) are anticipated;
(iv) A time-and-materials contract that exceeds the simplified acquisition threshold; or
(v) A labor-hour contract that exceeds the simplified acquisition threshold.
(2) If a cost-reimbursement contract is contemplated, for civilian agencies other than the Coast Guard and the National Aeronautics and Space Administration, the contracting officer shall use the clause with its Alternate I.
(3) Use of this clause is not required in-
(i) Fixed-price architect-engineer contracts; or
(ii) Contracts for mortuary services, refuse services, or shipment and storage of personal property, when an agency-prescribed clause on approval of subcontractors’ facilities is required.
(b) The contracting officer may insert the clause at 52.244-4, Subcontractors and Outside Associates and Consultants (Architect-Engineer Services), in architect-engineer contracts.
(c) The contracting officer shall, when contracting by negotiation, insert the clause at 52.244-5, Competition in Subcontracting, in solicitations and contracts when the contract amount is expected to exceed the simplified acquisition threshold, unless-
(1) A firm-fixed-price contract, awarded on the basis of adequate price competition or whose prices are set by law or regulation, is contemplated; or
(2) A time-and-materials, labor-hour, or architect-engineer contract is contemplated.
Federal Register history
| Final rule | Published | Effective |
|---|---|---|
| Federal Acquisition Regulation; Elimination of Certain Subcontract Notification Requirements |
Sections cited
- FAR 52.244-2 Subcontracts
- FAR 52.244-4 Subcontractors and Outside Associates and Consultants (Architect-Engineer Services)
- FAR 52.244-5 Competition in Subcontracting
Quick answers
What is FAR 44.204?
FAR 44.204 is a section of the Federal Acquisition Regulation, titled "Contract clauses".
When was FAR 44.204 last changed?
The most recent final rule on record is "Federal Acquisition Regulation; Elimination of Certain Subcontract Notification Requirements" (71 FR 225), published Jan 3, 2006 and effective Jan 3, 2006.
Are changes to FAR 44.204 proposed?
No proposed rule from the last 3 years is waiting on a final rule.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract