FAR 44.203 Consent limitations

Section Federal Acquisition Regulation

Facts

Citation
FAR 44.203
Type
Section
Last amended
69 FR 76358 Effective Dec 20, 2004
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.

Text

(a) The contracting officer’s consent to a subcontract or approval of the contractor’s purchasing system does not constitute a determination of the acceptability of the subcontract terms or price, or of the allowability of costs, unless the consent or approval specifies otherwise.

(b) Contracting officers shall not consent to-

(1) Cost-reimbursement subcontracts if the fee exceeds the fee limitations of 15.404-4(c)(4)(i);

(2) Subcontracts providing for payment on a cost-plus-a-percentage-of-cost basis;

(3) Subcontracts obligating the contracting officer to deal directly with the subcontractor;

(4) Subcontracts that make the results of arbitration, judicial determination, or voluntary settlement between the prime contractor and subcontractor binding on the Government; or

(5) Repetitive or unduly protracted use of cost-reimbursement, time-and-materials, or labor-hour subcontracts (contracting officers should follow the principles of 16.103(c)).

(c) Contracting officers should not refuse consent to a subcontract merely because it contains a clause giving the subcontractor the right of indirect appeal to an agency board of contract appeals if the subcontractor is affected by a dispute between the Government and the prime contractor. Indirect appeal means assertion by the subcontractor of the prime contractor’s right to appeal or the prosecution of an appeal by the prime contractor on the subcontractor’s behalf. The clause may also provide that the prime contractor and subcontractor shall be equally bound by the contracting officer’s or board’s decision. The clause may not attempt to obligate the contracting officer or the appeals board to decide questions that do not arise between the Government and the prime contractor or that are not cognizable under the clause at 52.233-1, Disputes.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation; Technical Amendments 69 FR 76358 · FAC 2001-26

Sections cited

Quick answers

What is FAR 44.203?

FAR 44.203 is a section of the Federal Acquisition Regulation, titled "Consent limitations".

When was FAR 44.203 last changed?

The most recent final rule on record is "Federal Acquisition Regulation; Technical Amendments" (69 FR 76358), published Dec 20, 2004 and effective Dec 20, 2004.

Are changes to FAR 44.203 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract