FAR 34.203 Solicitation provisions and contract clause

Section Federal Acquisition Regulation

Facts

Citation
FAR 34.203
Type
Section
Last amended
81 FR 83103 Effective Nov 18, 2016
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.

Text

(a) The contracting officer shall insert a provision that is substantially the same as the provision at FAR 52.234-2, Notice of Earned Value Management System-Preaward Integrated Baseline Review, in solicitations for contracts that require the contractor to use an Earned Value Management System (EVMS) and for which the Government requires an Integrated Baseline Review (IBR) prior to award.

(b) The contracting officer shall insert a provision that is substantially the same as the provision at 52.234-3, Notice of Earned Value Management System-Postaward Integrated Baseline Review, in solicitations for contracts that require the contractor to use an Earned Value Management System (EVMS) and for which the Government requires an Integrated Baseline Review (IBR) after contract award.

(c) The contracting officer shall insert a clause that is substantially the same as the clause at FAR 52.234-4, Earned Value Management System, in solicitations and contracts that require a contractor to use an EVMS.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation; Technical Amendments 81 FR 83103 · FAC 2005-92
Federal Acquisition Regulation; FAR Case 2004-019, Earned Value Management System (EVMS) 71 FR 38238 · FAC 2005-11

Sections cited

  • FAR 52.234-2 Notice of Earned Value Management System-Preaward Integrated Baseline Review
  • FAR 52.234-3 Notice of Earned Value Management System-Post Award Postaward Integrated Baseline Review
  • FAR 52.234-4 Earned Value Management System

Quick answers

What is FAR 34.203?

FAR 34.203 is a section of the Federal Acquisition Regulation, titled "Solicitation provisions and contract clause".

When was FAR 34.203 last changed?

The most recent final rule on record is "Federal Acquisition Regulation; Technical Amendments" (81 FR 83103), published Nov 18, 2016 and effective Nov 18, 2016.

Are changes to FAR 34.203 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract