FAR 34.202 Integrated Baseline Reviews

Section Federal Acquisition Regulation

Facts

Citation
FAR 34.202
Type
Section
Last amended
71 FR 38238 Effective Jul 5, 2006
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.

Text

(a) When an EVMS is required, the Government will conduct an Integrated Baseline Review (IBR).

(b) The purpose of the IBR is to verify the technical content and the realism of the related performance budgets, resources, and schedules. It should provide a mutual understanding of the inherent risks in offerors’/ contractors’ performance plans and the underlying management control systems, and it should formulate a plan to handle these risks.

(c) The IBR is a joint assessment by the offeror or contractor, and the Government, of the-

(1) Ability of the project’s technical plan to achieve the objectives of the scope of work;

(2) Adequacy of the time allocated for performing the defined tasks to successfully achieve the project schedule objectives;

(3) Ability of the Performance Measurement Baseline (PMB) to successfully execute the project and attain cost objectives, recognizing the relationship between budget resources, funding, schedule, and scope of work;

(4) Availability of personnel, facilities, and equipment when required, to perform the defined tasks needed to execute the program successfully; and

(5) The degree to which the management process provides effective and integrated technical/schedule/cost planning and baseline control.

(d) The timing and conduct of the IBR shall be in accordance with agency procedures. If a pre-award IBR will be conducted, the solicitation must include the procedures for conducting the IBR and address whether offerors will be reimbursed for the associated costs. If permitted, reimbursement of offerors’ pre-award IBR costs is governed by the provisions of FAR part 31.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation; FAR Case 2004-019, Earned Value Management System (EVMS) 71 FR 38238 · FAC 2005-11

Sections cited

Quick answers

What is FAR 34.202?

FAR 34.202 is a section of the Federal Acquisition Regulation, titled "Integrated Baseline Reviews".

When was FAR 34.202 last changed?

The most recent final rule on record is "Federal Acquisition Regulation; FAR Case 2004-019, Earned Value Management System (EVMS)" (71 FR 38238), published Jul 5, 2006 and effective Jul 5, 2006.

Are changes to FAR 34.202 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract