About this opportunity
Keys Energy Services (KEYS), the municipal electric utility for the City of Key West, Florida, is soliciting sealed bids for underground padmount transformer and switchgear inspections under Bid 1726, with proposals due December 4, 2026 at 10:00 a.m. The procurement carries no set-aside provisions.
The scope covers inspections of approximately 602 underground padmount transformers and 46 switchgear units in the Lower Florida Keys, evaluating structural integrity, electrical condition, safety, environmental condition, and serviceability. Inspections must be performed by or under the direct supervision of a qualified high-voltage electrician meeting OSHA 29 CFR 1910.269. Contractor personnel must maintain appropriate personal protective equipment and minimum approach distances at all times, and inspections occur on energized equipment unless KEYS specifically authorizes de-energizing.
Pricing is per unit for mobilization/demobilization, underground transformers, and switchgear, with payment based on quantities inspected and accepted. Bidders must submit a 5% bid bond or certified check, and prices must remain firm for 120 days minimum. Payment is due within 30 days of invoice acceptance, with 5% retainage held until 30 days after project completion and final acceptance. Required insurance includes commercial general liability at $2 million general aggregate, business automobile at $1 million combined bodily injury and property damage, and workers compensation at $1 million per accident, with the Utility Board named as additional insured.
The contract runs from execution through September 30, 2027, with extension at the same unit price if KEYS desires. All inspections must finish within 160 calendar days after Notice to Proceed, with final deliverables due 30 days later. Liquidated damages of $100 per day apply if work is not substantially complete by 190 calendar days after Notice to Proceed. The contractor bears responsibility for all equipment, materials, site conditions, and environmental compliance.
Evaluation criteria are experience with similar projects, range and suitability of services, project management approach, pricing, and references. KEYS reserves the right to award to the proposal it determines is in its best interest. Bids are submitted electronically via VendorLink or DemandStar, or on paper if received at 6900 Front Street Extended, Key West, Florida 33040 by the same deadline. The bid opening meeting is virtual on December 4, 2026 at 10:00 a.m.
Opportunity text
The successful Bidder(s) shall be responsible for The Underground Padmount Transformer and Switchgear Inspections Project.
Files
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity