Colorado's Division of Reclamation, Mining and Safety, within the Department of Natural Resources, is soliciting bids under IFB1 PKAA 2027*0055 for the Double Dick Underground Mine Fire Mitigation Project near Florence, Colorado, with a mandatory on-site pre-bid meeting on December 15, 2026 at 10:00 a.m. MT and bids due January 12, 2027 at 4:00 p.m. MT. Attendance at the pre-bid meeting is required for all interested bidders. Service-disabled veteran-owned small businesses (SDVOSB) registered and verified with the Center for Veteran Enterprise may receive a 5% preference on their bid if they submit proper certification documentation.
The work extinguishes an underground mine fire through excavation, blending, and backfilling within a 10-acre excavation area, followed by grading and revegetation. Bid line items cover mobilization and demobilization, safety planning, access road maintenance, box culvert installation, dust and ash control, sediment fencing, vegetation removal, topsoil stockpiling, onsite water storage for fire suppression, excavation and blending, and revegetation. Contractors must have directly completed at least two excavation projects exceeding 10,000 cubic yards, one survey-based grading project using GPS-enabled equipment, and one revegetation project greater than one acre within the past three years. Minimum equipment includes two excavators (302 flywheel horsepower minimum), two bulldozers (336 flywheel horsepower minimum), two 4,000-gallon water trucks with top-mounted cannons, and one low-ground-pressure bulldozer with GPS-enabled grading equipment. Optional equipment-time items 14.1 through 14.7 are not guaranteed. All costs for safety, health, and environmental measures under the SHEAP must sit within bid schedule items, with no separate itemization permitted. A completed equipment list must accompany the bid, or the bid may be deemed non-responsive.
Construction runs from March 1, 2027 through July 30, 2027, with 153 calendar days allowed after the Notice to Proceed, including 10 days for mobilization, and work must begin within 10 calendar days of that notice. Liquidated damages are $400 per day. A bid bond equal to 5% of the total bid price is required for bids over $50,000, and performance and labor and material payment bonds equal to 100% of the contract price are required for bids of $150,000 or greater, with 5% retainage held until completion. The project is funded in part by the U.S. Department of the Interior's Office of Surface Mining Reclamation and Enforcement under Assistance Listing Number 15.252. All work must comply with Davis-Bacon wage requirements, and Build America, Buy America and Buy Clean Colorado Act requirements apply to projects exceeding $500,000. A three-way agreement among the contractor, the State of Colorado, and the private landowner is required. Bidders must price every line item by unit and total, submit through Colorado Vendor Self Service, and attend a virtual public bid opening on January 13, 2027 at 12:00 p.m. MT. Written questions are due December 22, 2026 at 5:00 p.m. MT.