The Colorado Department of Transportation (CDOT) is requesting bids for roadway and signalization improvements at the intersection of State Highway 45A (Pueblo Boulevard) and Mirror Avenue in Pueblo County, with proposals due October 14, 2026.
The scope includes installation of new traffic signal poles at all four corners of the intersection, construction of raised medians on Pueblo Boulevard extending approximately 1,200 feet east and 2,000 feet west of Mirror Avenue, and resurfacing of the eastbound to northbound left turn lane. The raised medians require 6-inch over-excavation of native fill below existing asphalt and replacement with Class 6 ABC material. The turn lane will receive a 2-inch mill and overlay with new striping and signage. All work is detailed in the project plans and specifications, which the bidding document references. Contractors must review all plans, specifications, and addenda prior to submission.
The project is funded through Colorado state transportation resources allocated for highway safety and infrastructure improvements. Specific details regarding pricing terms, performance timelines, bonding requirements, insurance specifications, and award criteria are contained in the bidding document referenced in the solicitation.
Opportunity text
2 versions
Update #2 · Latest ·
In general, this project will consist of the installation of new traffic signal poles in all four corners of the intersection of CO45A (Pueblo Boulevard) and Mirror Avenue, as detailed in the plans and specifications. This project also includes the installation of raised medians on Pueblo Boulevard approximately 1200 feet to the east and 2000 feet to the west of Mirror Avenue. The raised medians will include a 6-inch over-excavation of native fill below existing asphalt and replacement with Class 6 ABC. The east bound to north bound left turn lane will receive a 2-inch mill and overlay with new striping and signage and other incidental items
Update #1 ·
In general, this project will consist of the installation of new traffic signal poles in all four corners of the intersection of CO45A (Pueblo Boulevard) and Mirror Avenue, as detailed in the plans and specifications. This project also includes the installation of raised medians on Pueblo Boulevard approximately 1200 feet to the east and 2000 feet to the west of Mirror Avenue. The raised medians will include a 6-inch over-excavation of native fill below existing asphalt and replacement with Class 6 ABC. The east bound to north bound left turn lane will receive a 2-inch mill and overlay with new striping and signage and other incidental items.
Files
| File | Type | Posted |
|---|---|---|
| Bid Notice.pdf | ||
| biddoc.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity