About this opportunity

The Connecticut Department of Energy and Environmental Protection (DEEP) is soliciting bids for odor control improvements at the Water Pollution Control Facility through a competitive procurement process. The project scope encompasses four primary deliverables: installation of new carbon filtration equipment, demolition of the existing biofilter and aluminum grating from the primary clarifier effluent channel, installation of a stationary anti-rotation scum deflector on the secondary clarifiers, and covering of the anoxic tanks. Key objectives include improving operational efficiency and environmental performance of the facility. Qualified bidders must demonstrate appropriate licensing, adequate financial capacity, and relevant project experience in similar wastewater treatment facility upgrades. Award decisions will be based on bidder qualifications, pricing competitiveness, and technical merit of proposed solutions. The solicitation was posted on August 26, 2025, with a proposal due date of September 30, 2025. Contractors must comply with Connecticut regulations, maintain appropriate insurance and bonding coverage, and adhere to specified safety standards applicable to work at the Water Pollution Control Facility.

The solicitation document does not specify any designated set-asides or restrictions limiting response to particular classes of organizations such as disadvantaged enterprises or minority-owned businesses. No incumbent vendors or current contractors are identified in the available procurement materials. Similarly, the solicitation does not reference existing infrastructure or technology platforms requiring integration with the proposed improvements beyond the specific facility components being modified. The project budget or award value has not been disclosed in the posted opportunity information. Interested contractors should obtain the complete solicitation document for detailed specifications, technical requirements, project plans, evaluation criteria, and any additional contractual terms governing project execution and contractor selection.

Opportunity text

Installation of new carbon filtration equipment, the demolition of the existing biofilter and aluminum grating from the primary clarifier effluent channel, the installation of a stationary anti rotation scum deflector on the secondary clarifiers, and the covering of the anoxic tanks at the Water Pollution Control Facility.

Files

File Type Posted
32098_Jan_28_26_solicitation_doc.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities
  • Ask GovTribe AI about this opportunity