Notice of Intent to Solicit Water Treatment Plant Replacement
Closed State & local contract opportunity Posted
- Solicitation number
- 25-10
- State
- Colorado
- Responses due
Opportunity facts
- Jurisdiction
- NIGP codes
- 031 Air Conditioning, Heating, And Ventilating Equipment, Parts And Accessories
- 175 Chemical Laboratory Equipment And Supplies
- 890 Water Supply, Groundwater, Sewage Treatment, And Related Equipment, Not For Air Conditioning, Steam Boiler, Or Laboratory Reagent Water
- 925 Engineering Services, Professional
- UNSPSC codes
- 12165301 Ceramic ball
- 41120000 Laboratory supplies and fixtures
- 81103300 Geomatics engineering
- 40100000 Heating and ventilation and air circulation
- 31250000 Pneumatic and hydraulic and electric control systems
- 81103400 Engineering procurement and project management services
- 81103404 Offshore engineering procurement and construction services
- 40000000 Distribution and Conditioning Systems and Equipment and Components
- 12165300 Adsorbent
- 12165302 Silica gel
Opportunity details come from bidnetdirect.com. Updated .
About this opportunity
The City of Gunnison, Colorado is seeking a progressive design-build team to replace its existing water treatment plant, transitioning from groundwater supply to treated surface water. The procurement will utilize a two-phase progressive design-build method, with an estimated project cost of $35 million. Phase one will involve reviewing existing information, initial design, and preconstruction activities, while phase two will focus on final design, construction, and facility commissioning. The project will be located at the VanTyl Ranch and has already developed a 30% design set for potential incorporation by the selected team. An Industry Pre-Procurement Briefing is scheduled for Thursday, May 15, 2025, from 1:00-2:00 PM Mountain Standard Time, which is open to all interested industry experts with no RSVP required. Optional site visits will be available from May 19-22, 2025, allocated on a first-come, first-served basis following the initial briefing. The procurement timeline indicates a proposal due date of May 15, 2025, with the project potentially subject to federal and state funding terms.
The solicitation does not explicitly specify set-aside designations or restrictions for disadvantaged business enterprises. The project appears open to design and construction firms with expertise in water treatment plant development and progressive design-build methodologies. While no incumbent vendors are mentioned, the city emphasizes that plans may change and no future procurement is guaranteed. The $35 million budget suggests a significant infrastructure investment requiring comprehensive engineering, design, and construction capabilities. The project's funding may involve federal and state sources, which could introduce additional compliance requirements for potential bidders. The two-phase approach indicates a preference for an integrated team that can collaboratively develop and implement the new water treatment facility, with the ability to effectively work with city stakeholders throughout the design and construction process.
Opportunity text
The City of Gunnison, Colorado plans to upgrade and replace its existing water treatment plant by using a progressive design/build project delivery method. The new facility is anticipated to be in the estimated cost range of $35 million. We're moving from groundwater supply to treated surface water. A progressive design/build approach has been selected to allow an integrated design/build team to effectively collaborate with the City to develop and implement an optimum new facility in a phased manner. Phase one includes review of existing information, design, and preconstruction. Phase two includes final design, construction, and commissioning and may be subject to federal and state funding terms. The project has developed a 30% design set that may be reviewed and incorporated. The purpose of this Notice of Intent is to (a) provide advanced notice to the design and construction industries of this project opportunity and (b) invite Industry experts to attend an informational session to learn about the project. Site visits will be scheduled after the informational session based on a first come, first served basis.
Files
| File | Type | Posted |
|---|---|---|
| FINAL FLYER eg Gunnison WTP Industry Briefing 15May2025 r2 (1).pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity