Northview High School Athletic Stadium Addition & Renovation

Closed State & local contract opportunity Posted

Solicitation number
RFP NVP 260000002718 9
State
Michigan
Responses due

Opportunity facts

NIGP code
UNSPSC codes

Updated .

About this opportunity

Northview Public Schools of Grand Rapids, Michigan is soliciting trade-contractor bids for the NVPS Athletics Stadium Addition and Renovation at Northview High School, with bids due November 10, 2026 at 1:00 p.m. ET, a deadline that has passed as of November 11, 2026. Bid Clarification 06 and the October 30, 2026 Invitation to Bid set this date, superseding the November 3 and 3:00 p.m. dates in earlier documents, while the record's due date field lists November 11, 2026.

Eligibility requires sworn, notarized disclosure of familial relationships with school board members or the superintendent, plus an Iran Economic Sanctions Act certification, criminal background affidavit, non-collusive affidavit, legal status of bidder affidavit, and signed Equal Opportunity Form. Door hardware is single-source: no substitutes are permitted for certain Schlage L-series locks, Von Duprin exit devices and electric strikes, and LCN 4010/4110 closers, and contractors must engage DHI-certified architectural hardware consultants. Fire-door and air-barrier assemblies must meet NFPA 80 and NFPA 101 testing and certification requirements.

The scope covers the stadium addition and renovation at 4451 Hunsberger Avenue NE, Grand Rapids, across bid packages for selective demolition, cast-in-place concrete, masonry, structural steel, general trades, roofing, plumbing, HVAC, electrical, excavation, asphalt, landscaping, synthetic turf (BP 32D), and fencing and protective netting (BP 32C). Addendum 02 added a band tower to general trades (BP 06). Bid Clarification 04 requires an Alternate 4 for 52 oz turf under BP 32D, and Bid Clarification 06 requires bidders to price both the drawings-based base material and a geotechnical-report alternate for site-work base under BP 31.

Bid security must equal at least 5% of the base bid, in the form of a bid bond, certified check, or cashier's check payable to Northview Public Schools. Performance and Labor and Material Payment Bonds covering 100% of project value must be priced as a separate line item and excluded from the base bid. No single trade contract may exceed 50% of the lump-sum base bid without written approval from Rockford Construction, the construction manager. Change order fees are 10% for labor, 10% for material and equipment, and 5% for trade quotes, with a 5% credit for deleted work. Allowances are permitted. The project is not prevailing wage, Michigan use tax applies, and proposals remain firm for 90 days from bid opening. Northview may reject bids based on prior unsatisfactory performance, incomplete submissions, or inadequate financial condition.

The mandatory pre-bid walkthrough was held October 6, 2026, and questions and substitution requests were due September 10, 2026. Post-bid Zoom interviews, if selected, run November 11 through November 25, 2026. The anticipated award date is December 15, 2026, with construction starting in Fall 2027 and substantial completion per the Phasing Plan in the Project Manual.