About this opportunity
Pennsylvania Department of Transportation is requesting bids for bridge replacement of State Route 2018 over Otter Creek in York County, Chanceford Township, with bids due September 17, 2026 at 11:00 a.m. at the Commonwealth Keystone Building in Harrisburg. Prequalification is required. The project is federally funded and subject to Buy America and Build America requirements.
The scope encompasses replacement of the existing structure with a single-span prestressed concrete spread box beam bridge, plus minor approach work, guide rail updates, roadway reconstruction, and miscellaneous construction across 350 linear feet (0.066 mile). Over 100 line items cover clearing and grubbing, excavation, asphalt paving, concrete work, drainage, guide rail installation, traffic control, bridge structure construction, and environmental and erosion control measures. Structure work comprises 64% of the contract value.
Environmental and regulatory constraints are significant: instream work on the trout-stocked Otter Creek is prohibited from February 15 through June 1 and October 1 through December 31. The project includes protection requirements for historic resources and wetlands. Erosion and sediment control plans, right-to-know law compliance, wage rates, and fall protection are specified. Material certifications and electronic submission through PennDOT's Electronic Contract Management System (ECMS) are required.
The estimated contract value falls between $1 million and $2.5 million. Anticipated Notice to Proceed is November 2, 2026, with required completion by November 22, 2027. No DBE requirement applies. All addenda will be electronically posted through ECMS. The project is on a non-NHS route under PennDOT oversight.
Opportunity text
This project consists of a bridge replacement of the SR 2018 structure over Otter Creek with a single-span prestressed concrete spread box beam bridge. Work also includes minor approach work, guide rail updates, roadway reconstruction, and other miscellaneous construction, all as indicated on the approved drawings included in the Bid Package for State Route 2018, Section 016, in York County, Chanceford Township, from Segment 0080 Offset 0490 to Segment 0080 Offset 0937 for an overall project length of 350 linear feet (0.066 mile).