The City of Hollywood, Florida is soliciting bids under Invitation for Bid IFB-451-27-JM (Project No. 25-8071A) for construction of a backup electrical power generator at Lift Station E-08, with a non-mandatory pre-bid meeting on November 16, 2026 at 2:00 p.m., questions due November 19, 2026 at 5:00 p.m., and bids due December 9, 2026 at 3:00 p.m. via the City's OpenGov portal. The solicitation carries no set-aside or disadvantaged-business goal. Award goes to the lowest responsive and responsible bidder, and local Hollywood vendor preference applies only as a tie-breaker, after a drug-free workplace program preference.

The scope covers site, civil, structural, and electrical work: removing the existing generator, fuel tank, and electrical items, then installing a new emergency generator designed to withstand a 500-year flood event, with fuel tank and ancillary equipment. Work includes survey, utility locating and protection, maintenance of traffic, soil borings, dewatering, shop and record drawings, and testing. The contractor must coordinate with the City, FEMA, AT&T, and FPL, and must maintain existing water, sewer, stormwater, and franchise utility service throughout construction. Pricing must include all delivery, installation, and ancillary labor and materials, quoted FOB Destination.

Required financial instruments include a bid guaranty of 5% of the total bid amount (cashier's check, certified check, or bid bond), plus a performance bond and a payment bond each equal to 100% of the contract price. Insurance requirements are Commercial General Liability of $1 million per occurrence and $2 million aggregate, Commercial Automobile Liability of $1 million combined single limit, Workers' Compensation with Employers' Liability of $500,000 per category, and Contractors Pollution Liability of $1 million per claim. The awarded contractor must execute contract documents within ten days of award notification.

The contract term is 270 calendar days to final completion, with 240 calendar days to substantial completion. The City may extend the contract up to an additional 120 days beyond expiration if terms remain unchanged and both parties agree. Bid prices remain valid for 120 days from solicitation opening.

Opportunity text

The work to be performed includes site, civil, structural and electrical work associated with the construction of LS E-08 Backup Electrical Power Generator Project in the City of Hollywood. The work to be performed includes but is not limited to the removal of existing generator, fuel tank, electrical items, installation of new emergency generator that is designed to be protected against a 500-year flood event, fuel tank, access for maintenance with all ancillary equipment as required, as shown on the plans. The construction activities include but are not limited to survey, locating and protecting existing utilities, maintenance of traffic, soil boring, dewatering, electrical equipment installation, restoration, furnishing and installing emergency generator, temporary MOT, maintaining building access, maintaining continuous sanitary service and property access, coordination with different agencies such as the City, FEMA, AT & T, and FPL, preparation and submittal of shop drawings and record drawings, testing, and other repairs or restorations. Work shall be performed to ensure continuous operation and appropriate performance of all existing water, sewer, stormwater and franchise utilities systems, to minimize impacts to roadway traffic, parking, residents and/or businesses and shall be coordinated with the City in advance. It is the intent of the City to obtain a complete and working installation under this contract and any items of labor, materials or equipment, which may reasonably be assumed as necessary to accomplish this end, should be supplied whether or not specifically shown on the plans or described herein. Maintenance of the existing utility systems is mandated throughout the construction period.

Files

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for State & Local Contractors