About this opportunity

The state of Georgia, through the Lowndes County Utility Department, is procuring the installation of 625 LF of 8" PVC watermain to interconnect the Grove Pointe and Nelson Hill water distribution lines in Liberty County. This public works project, known as the Grove Pointe-Nelson Hill Interconnection, involves the construction of new water infrastructure to improve system connectivity and reliability. Interested bidders must be licensed underground utility contractors in Georgia and submit a 5% bid bond. Lowndes County will hold a mandatory pre-bid meeting on September 3, 2024, and sealed bids are due by September 19, 2024 at 11:00 a.m. The contract time is 180 calendar days, and the bid documents specify unit pricing terms, a one-year warranty, and other standard contract provisions.

The procurement materials do not indicate any set-aside designations or restrictions on the types of organizations that can respond. No incumbent vendors or current contractors are listed. The total budget or anticipated award value for this project is not explicitly stated in the provided documents. Lowndes County reserves the right to accept or reject any or all bids received for this state and local government contracting opportunity.

Opportunity text

Advertisement listed in Supporting Documents section

Files

File Type Posted
GP to NH WM Interconnect Bid Document.pdf PDF
ADVERTISEMENT TO BID_GP to NH Interconnect.docx DOCX document
GPNH WATERMAIN EXT.pdf PDF