Fall Line Trail Southern Sections

Closed State & local contract opportunity Posted

Solicitation number
26-2970-5JL
State
Virginia
Responses due

Opportunity facts

Point of contact

Opportunity details come from constructionbidsource.com. Updated .

About this opportunity

Henrico County and Hampton City, Virginia are requesting proposals for the Fall Line Trail Southern Sections project, a multi-phase shared-use-path and pedestrian-infrastructure program with proposals due August 13, 2026.

The scope spans three trail segments totaling approximately 8,600 linear feet of shared-use path. Lakeside Community Trail Phase 2 (approximately 2,300 linear feet) includes a branch connection to Brook Run Drive, pedestrian crosswalks at Dumbarton Road and Gillespie Avenue, and two stream crossings over Upham Brook using approximately 150 linear feet of premanufactured truss and 380 linear feet of concrete boardwalk structures, plus drainage design, stormwater management, pavement marking, and signing. Lakeside Community Trail Phase 3 (approximately 3,500 linear feet) adds approximately 100 linear feet of premanufactured truss and 490 linear feet of concrete boardwalk to cross Upham Brook near the Grand Richmond at Brook Run on approach to Hilliard Road, with associated drainage, stormwater management, pavement marking, and signing. Brook Road and Hilliard Road Trail (approximately 2,800 linear feet) includes a pedestrian crosswalk across Hilliard Road (Route 161), a crossing over North Run using approximately 60 linear feet of premanufactured truss and 30 linear feet of concrete boardwalk adjacent to Belmont Golf Course, and a road diet reducing Hilliard Road from four to three lanes, plus drainage, stormwater management, pavement marking, and signing.

The source does not specify estimated contract value, contract term, evaluation criteria, incumbent contractor, set-aside or preference programs, or procurement timeline details beyond the proposal due date.

Opportunity text

The Work consists of the following: Lakeside Community Trail Phase 2 #FLT: The Lakeside Community Trail Phase 2 proposed improvements total approximately 2,300 linear feet of shared-use-path including a branch connection from the primary trail to Brook Run Drive, pedestrian crosswalks at the intersection of Dumbarton Road and Gillespie Avenue, and two crossings over Upham Brook. A combination of approximately 150 linear feet of premanufactured truss and 380 linear feet of concrete boardwalk structures will be used to cross Upham Brook near Dumbarton Road and on the approach to the Belmont Park baseball fields. The improvements also consist of drainage design, stormwater management (SWM), pavement marking, and signing. Lakeside Community Trail Phase 3 #FLT: The Lakeside Community Trail Phase 3 proposed improvements total approximately 3,500 linear feet of shared-use-path including a crossing over Upham Brook. A combination of approximately 100 linear feet of premanufactured truss and 490 linear feet of concrete boardwalk structures will be used to cross Upham Brook near the Grand Richmond at Brook Run on the approach to Hilliard Road. The improvements also consist of drainage design, stormwater management (SWM), pavement marking, and signing. Brook Road and Hilliard Road Trail #FLT: The Brook Road and Hilliard Road Trail proposed improvements total approximately 2,800 linear feet of shared-use path, including a pedestrian crosswalk across Hilliard Road (Route 161) and a proposed pedestrian crossing over North Run. A combination of approximately 60 linear feet of premanufactured truss and 30 linear feet of concrete boardwalk structures will be used to cross North Run adjacent to the Belmont Golf Course parcel near the intersection of Hilliard Road (Route 161) and Brook Road (Route 1). The Brook Road and Hilliard Road Trail improvements also include a portion of the road diet along Hilliard Road (Route 161) from four lanes to three lanes. The improvements also consist of drainage design, utility design, stormwater management (SWM), pavement marking, and signing. Hilliard Road Safety and Mobility Improvements: The Hilliard Road Safety and Mobility proposed improvements total approximately 2,700 linear feet of pavement marking and signing improvements within existing right-of-way to add bicycle lanes and accommodations. The improvements are along Hilliard Road between Lakeside Avenue and approximately 1,000 feet west of Brook Road, tying into the Brook Road and Hilliard Road Trail proposed improvements. The proposed bicycle lanes will be accompanied by a road diet from four lanes to three lanes.

Files

File Type Posted
832540roadHenr.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities