The Central Florida Tourism Oversight District (CFTOD) is seeking an Engineering Consultant to provide professional engineering services for process improvements to the condenser water and cooling tower systems associated with the chilled water plant at the Epcot Energy Plant in Lake Buena Vista, Florida. The requested improvements include modifying and installing a chemical treatment system, designing and installing electronically operated chemical valves, repairing structural concrete damage, installing sluice gates and a second condenser water piping header, and adding isolation valves and new flowmeters. The project has specific deliverables and tasks that the selected consultant will be required to complete, including design, bidding, permitting, and construction phase services. The bid is due on April 8, 2024, and bidders must be registered through the CFTOD's new PlanetBids platform to access the supporting attachments and submit bids.
The CFTOD emphasizes a preference for local, veteran small, and opportunity zone businesses to respond to this solicitation. The procurement documents do not mention any set-aside designations, incumbent vendors, or current contractors. Additionally, the available budget or award value is not specified in the Invitation to Bid (ITB) announcement. The CFTOD's Procurement Policy provides additional information on their contracting requirements and processes.
Opportunity text
The Engineering Consultant (Consultant) shall assist the Central Florida Tourism Oversight District (CFTOD or DISTRICT) by providing professional engineering services in the design, bidding, permitting, and construction phase services for the process improvements to the condenser water and cooling tower systems associated with the chilled water plant. The improvements will be located at the EPCOT Energy Plant (EEP), 751 Backstage Lane, Lake Buena Vista, Florida. The existing condenser water and cooling tower system includes four (4) cooling towers with associated pumps, valves, piping, and chemical control. Cooling towers 1-3 are original to the construction of the EEP in the 1980's and are connected via a common condenser water pump sump. In 1989 cooling tower 4 and associated pumps, valves, and piping were added.
Upgrades are needed to improve the ability to isolate individual towers for maintenance and flexibility in operation. Refer to Appendix A and B. Requested improvements include:
1. Modify, install, test and commission a chemical treatment system for cooling tower cell 4 to include piping and controls as needed.
2. Design/specify, install, test and commission electronically operated chemical valves for each cooling tower cell to operate in conjunction with the associated cells over tower valve (OTV).
3. Design/specify the repair of structural concrete damage within the basin of cooling tower cell 4.
4. Design/specify a solution using sluice gates to close existing openings between cooling tower cells 3 and 4, construct one (1) larger opening between the cells, and install means of mechanical isolation of new opening.
5. Design/specify, install, test and commission a second condenser water piping header from existing chillers to existing condenser water header to include piping, valves, hangars, and other appurtenances.
6. Design/specify, install, test and commission isolation valves in existing condenser water header.
7. Design/specify, remove existing, install, test and commission new flowmeters for each cooling tower condenser water flow.
Files
| File | Type | Posted |
|---|---|---|
| C006553 MFMP ITB Flyer.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity