The City of Doral is requesting quotes for roof repair at Morgan Levy Park under a purchase under $50,000, with quotes due June 5, 2026.

The scope of work covers removal of the existing roof system to the wood deck, installation of 1/4" tapered insulation for positive drainage, and mechanical fastening of GAF Everguard 60 mil single-ply TPO membrane adhered with GAF 1121 adhesive. Work includes mechanically fastened 3×3 galvanized eave drips, Everguard HW 6" cover strips on eave metals, GAF water-block installation between TPO membrane and parapet wall, termination bars and stucco stops per Florida building code, and robotically heat-welded laps at minimum 1.75" overlap. TPO boots must be installed on all penetrations; pitch pockets on irregular penetrations must be fabricated and installed using TPO-coated galvanized metals and filled with single-part pourable sealer. T-patches heat-welded over all t-joints with sealant applied to cut edges. The project includes three sheets of plywood and complete removal of roofing debris from the premises.

Opportunity text

The City of Doral is requesting quotes for the NO VALUE

Scope of work:

  1. Remove the existing roof system down to the wood deck
  2. Preliminary fasten 1/4" tapered insulation system for positive drainage
  3. Mechanically fasten GAF Everguard 60 mil single-ply TPO adhered with GAF 1121 adhesive to tapered insulation
  4. Mechanically fasten 3x3 galvanized eave drips
  5. Install Everguard HW 6" cover strip on eave metals to TPO membrane
  6. Install GAF water-block between TPO membrane and parapet wall
  7. Install termination bar and stucco stop as per Florida building codes specifications
  8. Robotically heat weld all laps with a minimum of 1.75"
  9. Install TPO boots on all penetrations
  10. Fabricate and install pitch pockets on all irregular penetrations using TPO coated galvanized metals
  11. Fill all pitch pockets with single part pourable sealer
  12. Heat weld t-patches over all t-joints
  13. apply sealant to all cut edges
  14. three sheets of plywood included
  15. removal of roofing debris from premises