About this opportunity
The St. Johns River Water Management District is issuing an Invitation for Bid (IFB) for the Crane Creek M-1 Canal Flow Restoration project in Brevard County, Florida. The work consists of constructing an operable control structure within the M-1 Canal, two stormwater pumping stations, approximately 5,000 feet of 24-inch underground HDPE force main, and a stormwater treatment area. Key objectives include restoring flow within the Crane Creek M-1 Canal and managing stormwater runoff. The engineer's construction estimate for the project is $19,823,000. Bids are due by 2:00 pm on September 8, 2022, and a non-mandatory pre-bid conference is scheduled for August 9, 2022. Bidders must have successfully completed at least three similar projects of $3 million or more in value within the past ten years and provide a bid bond in the amount of 0.5% of the total bid. The contract will be awarded to the lowest responsive, responsible bidder and will be funded across three fiscal years.
This contract opportunity does not appear to have any set-aside designations or restrictions on the types of organizations that can respond. The procurement documents do not indicate any incumbent vendors or current contractors, nor do they specify any existing infrastructure or technology that requires integration. The total awarded contract value is estimated at $19,823,000.
Opportunity text
The Work of this Project consists of the construction of five primary project elements:
- An operable control structure within the M-1 Canal east of Evans Road, including pneumatic crest gates (weirs), concrete hardened flow channel, flow channel center dividing wall, flow attenuation blocks, foundations, rip rap, mechanical equipment, power supply and equipment, concrete slabs, instrumentation and controls, paving, grading, and other incidental work.
- A stormwater pumping station, located east of I-95 adjacent to the M-1 Canal along Coastal Lane. Work includes intake structure and screens, intake piping and manholes, concrete wetwells, pumps, discharge piping, valves, pipe supports, power supply and equipment, concrete slabs and pavement, instrumentation and controls, paving, grading, and other incidental work.
- A stormwater pumping station, located west of the St. Johns Heritage Parkway. Work includes intake structure and screens, intake piping and manholes, concrete wetwell, pumps, discharge piping, valves, pipe supports, power supply and equipment, concrete slabs and pavement, instrumentation and controls, paving, grading, and other incidental work.
- Two sections of 24-inch-diameter underground high-density polyethylene (HDPE) stormwater force main from each of the pump stations. Installation by horizontal directional drilling and open-cut trenching, valves, fittings, surface restoration, plantings to restore temporary construction easements and other project areas, a precast outfall structure into the STA, an outfall structure north of 192, and other incidental work.
- A stormwater treatment area (STA) west of the St. Johns Heritage Parkway. The STA will include earthwork for regrading slopes of an existing borrow pit, an access road, and other incidental work.
The engineer's construction estimate for the project is $19,823,000.00.
Files
| File | Type | Posted |
|---|---|---|
| IFB_38004_Crane Creek M-1 Canal Flow Restoration_1.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity