About this opportunity
Platte River Power Cooperative is requesting bids on a complete control enclosure for the Rawhide Combustion Turbine Substation, with bids due June 18, 2026. The awarded bidder will furnish all equipment, materials, labor, supervision, and management necessary to manufacture, deliver, and install the enclosure and associated shipping splits, including final field assembly, relays, wiring, auxiliary controls, and a remote terminal unit (RTU), delivered FOB to Platte River on Platte River-furnished piers. Work encompasses fabrication, delivery, and installation as detailed in the attached contract, technical specifications, and drawings (biddoc.pdf, 276 KB, posted May 19, 2026).
Opportunity text
3 versions
Update #3 · Latest ·
The Town of Parker is soliciting responses from qualified consultants to award contracts for pre-qualified construction management and inspection services. Various Town departments and/or project managers may utilize the services provided under the awarded contracts on individual projects with combined disciplines up to a maximum of $500,000 per project for contract management and inspection services.
Update #2 ·
The extent of the work is approximately as follows: The project generally includes architectural, structural, mechanical, electrical, telecommunications, and fire protection trades for the remodel of an approximately 1,500-square-foot office suite located at the Parker Fieldhouse, 18700 Plaza Drive, Parker, CO 80134.
Update #1 ·
The awarded bidder will furnish all equipment, materials, labor, supervision, administration and management necessary to manufacture, deliver, and install a complete Rawhide Combustion Turbine (RCT) Substation control enclosure, as well as fabricate, deliver, and install the associated shipping splits for the control enclosure. Supplier will furnish all fabrication, final field assembly, relays, wiring, auxiliary controls, and the remote terminal unit (RTU), delivered FOB to Platte River, on Platte River-furnished piers. The awarded bidder will perform all work as more specifically detailed in the attached Contract, including the Technical Specifications and Drawings.
Files
| File | Type | Posted |
|---|---|---|
| biddoc.pdf | ||
| Parker Fieldhouse Office Remodel.pdf | ||
| biddoc.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity